Attachment 9 - Development Approval 21675 DA
Noosa Council documents
Comment [DSP]: Page: 1
Form 6 – Compiled Decision Notice Insert name and address of agency.
Comment [DSP]: Page: 1
INTEGRATED PLANNING ACT 1997, S3.5.15, IDAS DEVELOPMENT APPLICATION
If refused, delete the section headed
Referral Agencies
Referral Agency Address
File No: 21675 DA Date of Decision: 7 December 2005
Comment [DSP]: Page: 1
Insert Designer’s
Application Name,
Type and Plan No.
Decision and
details
1. APPLICANT DETAILS Date ofdecided
Council Plan. to <
applicable codes
Name: PMM GROUP
Comment
The developer mustPage:
[DSP]: comply 1 with the
Insert Yes
following or No
codes in each column
for self-assessable
Postal address: PO BOX 149, WURTULLA QLD 4575 adjacent
developmentto each
relatedcategory.
to the development
approved under this Development Permit:-
1. <
Phone no: 5436 7812 Fax no: 5493 6630
SUBMISSIONS
Not applicable.
2. PROPERTY DESCRIPTION Conditions and insert reasons for
refusal.
Street address: 100 COOYAR STREET
Suburb/locality NOOSA HEADS
Real property LOT 9 RP 225312 PARISH WEYBA COUNTY MARCH
description:
3. OWNER DETAILS
Name: OZCARE
Postal address: PO BOX 912, FORTITUDE VALLEY QLD Postcode: 4006
4. REFERRAL AGENCIES
Referral Agency Address Basis
Nil
5. APPLICATION TYPE
Development Development Details Preliminary Development
Approval Permit
Material Change of Use Stage 3 - Aged Persons Home NO YES
(20 Beds)
6. DECISION DETAILS
Council, on 28 June 2001, decided to approve the application and grant a Development Permit, subject to
conditions.
In relation to representations made about Condition 2, Council on 9 August 2001 resolved to approve the change.
In relation to a request to change the development approval, Council on 7 December 2005 resolved to:
A. Approve the change with the approved plans to comprise those numbered DA-1 dated September 2005
and SD2, SD3, dated July 2005 and SD4 dated May 2005, prepared by Andrew Hillhouse Architect.
B. Amend Conditions 4, 15, and 19.
C. Delete Condition 5.
D. Include 24 additional conditions and 3 Advices.
E. Issue a Compiled Decision Notice.
F. Advise the applicant that a further Development Permit for Operational Works for access, car parking, site
civil works, stormwater drainage, landscaping is required prior to issue of a Development Permit for
Building Works.
Print Date: 7 April 2021, 3:41 PM
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalFull text of the other 12 pages
Page 2
Noosa Council documents
NOOSA COUNCIL IDAS Development Application Decision Notice 2
7. APPLICABLE CODES Comment [DSP]: Page: 2
Type name of officer signing
The developer must comply with the following codes for self-assessable development related to the development
approved under this Development Permit:-
Not applicable.
8. SUBMISSIONS
Not applicable.
9. CONDITIONS
The approval is subject to conditions. Noosa Council’s conditions are attached.
10. FURTHER DEVELOPMENT PERMITS REQUIRED
Type of Development Permit required Subject of the required Development Permit
Building Works Aged Persons Home
Operational Works Landscaping, Access, Stormwater Disposal, Sediment &
Erosion Controls
11. RIGHTS OF APPEAL
Rights of appeal in relation to this application are attached.
12. ASSESSMENT MANAGER
Name: Noosa Shire Council Signature: Date: 13/12/05
DECISION NOTICE HISTORY
Original Decision Notice 28 June 2001.
Negotiated Decision Notice with amendment to
Condition 2 approved on 9 August 2001.
Compiled Decision Notice with amendment to
Conditions 4, 15, and 19, deletion of Condition 5 and
inclusion of 24 additional conditions and 3 advices on
7 December 2005.
SEP o:\database\onestop\decision.doc
Print Date: 7 April 2021, 3:41 PM
Page 3
Noosa Council documents
NOOSA COUNCIL IDAS Development Application Decision Notice 3
Noosa Council Conditions
INTEGRATED PLANNING ACT 1997, IDAS DEVELOPMENT APPLICATION
Land Development
1. The temporary emergency vehicle access, located on Council land, that runs past the Noosa Heads Police
Station to the rear of the St Vincent De Paul site - is permitted to be utilised until the Manager of Land
Development advises in writing that “the access is to discontinue”.
After which advice, emergency vehicles shall gain access to the south east corner of the site internally in
accordance with proposal plan SK-04, Issue C, Job No. 01002, dated 3/4/01, as submitted by Andrew
Hillhouse Architects - except as modified herein.
2. The proposed alignment of the emergency vehicle access (as shown on proposal plan SK-04, Issue C,
Job No. 01002, dated 3/4/01, as submitted by Andrew Hillhouse Architects), shall be realigned to minimise
the destruction of existing vegetation. In this regard, the emergency vehicle access shall be at least 3
metres from the front boundary and at least 1 metres from the side boundary. The existing vegetation
shall be supplemented (where necessary), to ensure the buildings and the emergency vehicle access are
visually screened from Cooyar Street.
Plans and specifications for these works shall be prepared and submitted to Council for Operational Works
approval and the cost of constructing the internal emergency vehicle access shall be at no cost to Council.
3. Stormwater is to be disposed of on site so as to cause no scour or damage to adjoining properties to the
reasonable satisfaction of the Manager of Land Development. Details of the stormwater drainage scheme
shall be submitted in conjunction with a Development Permit for Operational Works.
4. Contributions shall be paid to Council in accordance with Planning Scheme Policies PSP28 and PSP30 on
Water Supply Headworks Contributions and Sewerage Headworks Contributions respectively and at the
rates applicable at the time of payment. An estimate only of the contribution rates under the current
policies is outlined below. These amounts will adjusted in line with changes to the Consumer Price Index,
All Groups Brisbane from September 2005 until the date of payment.
Stage 3 – March 2001
Water Supply $38,712
Sewerage $19,561
TOTAL $58,273
Stage 4 – September 2005
Water Supply $63,237
Sewerage $32,577
TOTAL $95,814
All headworks contributions must be paid prior to the issue of a Development Permit for Operational
Works.
Alternatively a trading bank guarantee shall be submitted to Council plus 20%. Should the headworks
contributions not be paid at the due time, Council shall call upon the trading bank guarantee in full.
In the event that the Development Permit for Material Change of Use of Premises lapses or is cancelled,
the contribution or trading bank guarantee will be returned.
5. Deleted.
6. The new building extensions shall be connected to Council's existing water supply and sewerage
reticulation systems in accordance with Council’s standards and requirements and at no cost to Council.
SEP o:\database\onestop\decision.doc
Print Date: 7 April 2021, 3:41 PM
Page 4
Noosa Council documents
NOOSA COUNCIL IDAS Development Application Decision Notice 4
7. To protect the environment against siltation/sediment export or soil erosion as a result of the proposed
building extensions, an erosion and sediment control plan shall be submitted in conjunction with any
Development Permit for Building Works. Site control measures such as silt fencing, controlled gravel
access to the site and controlled disposal of waste, may be necessary. Prior to commencement of
Building Works:-
7.1 all physical site control measures shall be installed and the plan adhered to, and
7.2 a $2,000 site control bond shall be lodged with Council to ensure compliance with this condition.
The $2,000 bond will be refunded less any costs incurred by Council in ensuring compliance with this
condition or any additional inspections incurred for substandard work or works undertaken not in
accordance with this permit.
Building
8. The plans submitted for a Development Permit for building works are to comply with the approved plans
9. The requirements of the Environmental Protection Amendment Regulation (No. 2) 1999 and Local Law No.
12, prevents a builder or building contractor carrying out building work on a building site in a way that
makes or causes audible noise to be made from the building work:-
9.1 On a Sunday or public holiday, at any time; or
9.2 On a Saturday or a business day, before 7.00am or after 6.30pm.
A maximum penalty of $1,500 applies to an offence under this legislation.
10. We advise ‘interested parties’ i.e. ‘developer’, ‘owner’, ‘tenant’ to consider their responsibilities under the
Disabled Discrimination Act (DDA) in regard to the installation of disabled access and the provision of
disabled facilities, and that access to this building and the provision of sanitary facilities may need to
comply with the requirements of Section D Part D3 and Section F Clause F2.4 of the Building Code of
Australia.
11. An identification survey of the subject site is to be carried out by a Licensed Surveyor and is to be
submitted to Council at the time of foundation inspection or immediately thereafter. Such survey shall set
out the boundaries of the site and the position of the buildings on the site.
12. The developer must provide a suitably screened imperviously paved area large enough for all refuse and
recycling containers. A wash down area is required with a cold-water tap, hose and drain outlet
connected to sewer. The drain outlet is to be designed to prevent stormwater entry to the sewerage
system.
13. Air conditioning units shall be located in a manner which prevents noise nuisance beyond the subject land
in accordance with the nuisance provisions of the Environmental Protection Regulation 1998. On the spot
fines apply for such offences.
14. All food preparation is to be conducted within the existing approved commercial kitchen.
Land Use
15. Development undertaken in accordance with this approval must generally comply with the approved plans
of development. The approved plans are numbered SK-06, 07 issue B SK-8 & 9 Issue A dated
26/01/2000, SD1 (titled ‘Site Plan’), SD2, SD3, dated July 2005, SD4 dated May 2005 and DA-1 dated
September 2005, prepared by Andrew Hillhouse Architect and as may be amended by these conditions.
16. The open space and setback areas are to be landscaped in accordance with Council’s Policy on
Landscaping Guidelines and a properly prepared landscape plan. Such landscaping is to be completed
prior to the premises being occupied and maintained at all times thereafter.
17. Existing trees on the site and within road reserves are to be retained, except where required to be
removed due to building operations or the conduct of the approved use.
SEP o:\database\onestop\decision.doc
Print Date: 7 April 2021, 3:41 PM
Page 5
Noosa Council documents
NOOSA COUNCIL IDAS Development Application Decision Notice 5
18. Any advertising sign or device is to comply with the provisions of Council's policies on advertising.
19. This Development Permit for a material change of use of premises lapses if the use has not happened by
7 December 2009, unless an application to extend the currency is approved by Council.
20. The developer must obtain all of the other Development Permits referred to in the Decision Notice, prior to
obtaining a Development Permit for building works.
Additional Conditions 7 December 2005
21. Bus parking shall be provided on site for a minimum of 2 buses.
22. Though no upgrading works/construction is required to the existing access off Cooyar Street, the existing
vegetation adjacent to the access shall be pruned to improve driver sight lines to both vehicles and
pedestrians travelling in Cooyar Street and along the footpath. The Australian Standard for Off-Street Car
Parking (AS2890.1) shall be used as a guide as with Austroads Guide to Traffic Engineering Practice Part
5 Intersections at Grade.
Plans submitted for Operational Works approval shall clearly show the required sight lines and the extent
of vegetation pruning required to achieve compliance.
Given the importance of maintaining clear sight lines, the applicant shall also submit a management plan
that demonstrates how these sight lines will be maintained for the long term.
23. As it is proposed to modify the existing internal roundabout to enable the construction of the new Low Care
Wing, the redundant part of the driveway/roundabout shall be removed and densely revegetated. In
addition the northern leg of the roundabout (which will now only provide access to the existing
maintenance shed) shall be appropriately sign posted and line-marked to encourage vehicles to travel
around to the right rather than into the maintenance area. These works shall clearly be shown on the plans
submitted for Operational Works approval.
24. All vehicles shall enter and leave the site in a forward direction.
Service Areas (Service Yard)
25. The proposed service yard (refuse collection area) is inadequately sized to accommodate the necessary
refuse storage and the area required for a refuse collection vehicle to manoeuvre. As such, the applicant
shall prepare detailed designs of the service yard demonstrating the refuse storage area and that the
Council refuse vehicle has adequate room to collect the refuse and carry out a 3-point turn in order to
enter and leave the area in forward gear.
26. As a result of the proposed extension three (3) existing delivery spaces (adjacent to the existing service
yard) will be removed and in this regard a minimum of two (2) new delivery spaces shall be provided in the
new service yard. The delivery spaces shall be at least 3.5m wide by 6.5m long and these spaces shall be
located outside of the refuse truck turning area. The 2 delivery spaces shall be provided adjacent to one
another and at the northern end of the refuse truck turning area.
To enable efficient use of these 2 delivery spaces appropriate signage shall be installed to limit delivery
parking to a maximum time of 30 minutes.
To this end, the proposed service yard shall be modified to not only cater for a Council refuse vehicle, but
to also cater for small delivery vehicles that frequent the site.
27. Revised plans of the service yard demonstrating compliance with the above conditions shall be submitted
to the Council for approval prior to obtaining a Development Permit for Operational Works.
Carparking
28. Carparking shall be provided within the site as generally shown on drawing 369/1/DA-1, dated September
2005 by Andrew Hillhouse Architects, and as prepared by Diamond Architects Pty Ltd, except as modified
herein.
29. The carparking area shall be designed to comply with the provisions of AS 2890.1-2004 for user class 2
with allowance for vehicles to enter and leave the site in a forward gear.
SEP o:\database\onestop\decision.doc
Print Date: 7 April 2021, 3:41 PM
Page 6
Noosa Council documents
NOOSA COUNCIL IDAS Development Application Decision Notice 6
30. All carparking shall be kept, maintained and line-marked in a condition fit for use.
Vegetation Protection & Preservation
31. Vehicular pavements within the drip zone of any of the existing trees on site to be retained shall be
designed as a pervious pavement (such as grass paving cells or similar), as this will allow water that falls
on this surface to penetrate to the trees root system. The pavement shall be constructed so as not to
damage the tree or their root system and in this regard temporary fencing shall be provided around the
trees during construction to help protect them.
Plans shall be submitted to the Council for approval that clearly show the type and extent of the pervious
pavement and the temporary fencing prior to obtaining a Development Permit for Operational Works.
Park Contributions
32. A Park contribution of $5,289 towards the acquisition of additional parkland or the improvement of existing
parkland and facilities in the locality shall be paid to the Council prior to obtaining a Development Permit
for Operational Works in accordance with Council’s Planning Scheme Policy PSP24 Park Requirements
for Development Applications. This amount will be subject to variations in the Consumer Price Index, All
Groups Brisbane from September 2005 until the date of payment.
Pathway Contributions
33. A pathway contribution of $5,343 towards external major pathways, in accordance with Planning Scheme
Policy PSP41 Pathway Trunk Network Contributions, shall be paid to the Council prior to obtaining a
Development Permit for Operational Works. This amount will be subject to variations in the Consumer
Price Index, All Groups Brisbane from September 2005 until the date of payment.
Stormwater Drainage
34. All stormwater drainage shall be collected on site and discharged so there is no net increase in stormwater
runoff from the site.
35. Roof runoff from any new buildings shall be directed to a rainwater storage system or tank (minimum
storage capacity equivalent to 20 litres/m2 of new roof area or greater) that is plumbed to service the toilets
in the new building and landscaping areas. The design of the rainwater storage system shall be to the
satisfaction of the Manager Plumbing Services.
36. To ensure that polluted run-off does not enter Council’s stormwater drainage system or nearby creeks,
stormwater run-off from the carparking areas and the driveways shall have the first flush (the first 12 mm of
rainfall or hose-down) collected in a grease/oil arrestor provided on site prior to being permitted to
discharge from the site.
All other clean stormwater, such as roof water, can bypass the grease/oil arrestor.
To this end, a detailed maintenance plan shall be prepared for the proposed grease/oil arrestors, which
shall be submitted to the Council for approval prior to obtaining a Development Permit for Operational
Works.
The approved maintenance plan shall be incorporated in the Management Plan for the development and a
copy of this shall be provided for Council’s records prior to commencement of the approved Use.
A Development Permit for Building Works shall not be granted until a Development Permit for Operational
Works has been issued in regard to the drainage scheme.
37. All site stormwater drainage shall be by means of a gravity system.
Sewer Mains
38. The existing sewer main that traverses the site and the ‘zone of influence’ (taken as the area within a 45-
degree angle measured from the invert of the sewer main to the finished surface level) shall be accurately
located and determined by a licensed Surveyor and shown on all plans submitted for Operational Works
approval.
SEP o:\database\onestop\decision.doc
Print Date: 7 April 2021, 3:41 PM
Page 7
Noosa Council documents
NOOSA COUNCIL IDAS Development Application Decision Notice 7
To ensure Council’s sewer main is accessible for maintenance purposes and is protected from risk of
damage no structures requiring a building permit (eg. buildings, swimming pools, retaining walls, raised
terraces, etc) shall be constructed within this ‘zone of influence’ and as such the applicant shall amend
Operational Works plans including Building plans to ensure compliance.
Town Water Supply
39. The new building and extensions shall be connected to Council’s existing town water supply and be
constructed in accordance with Council’s standards and requirements at no cost to Council.
Earthworks
40. Any filling works required on site shall be carried out in accordance with Section 3.8 of Council’s
Engineering Design Standards Manual and so as not to cause the additional ponding of water on any
adjoining lands or the blockage of, or interference with, any natural watercourses.
Erosion and Sediment Control
41. Any person acting on this permit shall prevent erosion and sediment export from leaving the site. Site
control measures such as silt fencing, controlled gravel access to the site and controlled disposal of waste,
will be necessary.
In this regard plans detailing the methods of controlling erosion and sediment are required to be submitted
to the Council for approval prior to obtaining a Development Permit for Operational Works.
General
42. Any damage caused to any public utility during the course of construction shall be repaired to Council’s
standards and at no cost to Council.
43. Any alteration of any public utility or other facilities necessitated by the development of the land or
associated construction works external to the site shall be at no cost to Council.
44. The transportation of all materials to and from the site shall be undertaken in a manner such that no
particle matter escapes onto a public road. All vehicles carrying materials either to or from the site shall be
covered to prevent materials including dust being windblown from the vehicle.
THE FOLLOWING ADVICES ARE FOR INFORMATION PURPOSES ONLY AND DO NOT FORM
CONDITIONS OF APPROVAL
1. The applicant is informed that approval of this development application will trigger an Infrastructure Charge
in accordance with the Coastal Major Road Network Infrastructure Charges Plan for the estimated amount
of $7,592 and is subject to variations in the Consumer Price Index, All Groups Brisbane from September
2005 until the date of payment. An Infrastructure Charge Notice will be issued in accordance with Chapter
5 of the Integrated Planning Act 1997.
2. The applicant is informed that payment via credit card transaction will not be an acceptable method of
payment for development contributions conditioned in this permit or for infrastructure charge notices
issued separately.
3. The applicant is advised that a Compliance Permit for all plumbing and drainage works within the
boundaries of the development site shall be obtained from Council’s Plumbing Services Section prior to
obtaining a Development Permit for Building Works.
SEP o:\database\onestop\decision.doc
Print Date: 7 April 2021, 3:41 PM
Page 8
Noosa Council documents
Kerri Coyle, 07 54495223
2001/210127 (21675 DA)
Email: [email protected]
13 December 2005
PMM Group Pty Ltd
PO Box 149
WURTULLA QLD 4575
Dear Sir/Madam,
Re: Application for a Change to a Development Approval for Stage 3 – Aged
Persons Home - Extensions & Alterations situated at 100 Cooyar Street,
Noosa Heads described as Lot 9 RP 225312
I refer to your request to make a change to the above development approval. On 7
December 2005 Council decided to:
A. Approve the change with the approved plans to comprise those numbered DA-1
dated September 2005 and SD2, SD3, dated July 2005 and SD4 dated May
2005, prepared by Andrew Hillhouse Architect.
B. Amend Conditions 4, 15, and 19.
C. Delete Condition 5.
D. Include 24 additional conditions and 3 Advices.
E. Issue a Compiled Decision Notice.
F. Advise the applicant that a further Development Permit for Operational Works for
access, car parking, site civil works, stormwater drainage, landscaping is required
prior to issue of a Development Permit for Building Works.
You are entitled to appeal against this decision. A copy of the relevant appeal
provisions from the Integrated Planning Act is also attached.
Please note that an Infrastructure Charge in accordance with the Coastal Major Road
Network Infrastructure Charges Plan has been triggered by the approval of this
development application. An Infrastructure Charge Notice is attached in compliance
with Chapter 5 of the Integrated Planning Act 1997.
Should you wish to obtain more information about Council’s decision, the reports and
staff recommendations regarding this application are available for viewing or purchase
at the Level 2 counter of Council offices. It would assist Council staff if you could bring
this letter with you.
Yours faithfully,
Shane Adamson
MANAGER - LAND USE
Encl: Compiled Decision Notice
Infrastructure Charge Notice
Print Date: 7 April 2021, 3:41 PM
Page 9
Noosa Council documents
EXTENSION “C EXISTING MIGH
CARE WING,
CARE ANG,
SOUSA S RECUCNCIL
PLANS 4PPROVED
SIONAIERE AEOL
po Tomes !}
(NOPSA SHIRE. COUNT",
TANS
APPROL)
PES TTED DEVELOPMENT
3. AECT IO TTNDMORS
Suet G =CME an
+ tke STREET
to
| eeore =
- . 2 t
SN DPEW SELHO
CR
AG TARE wins
NOOSA E025
sree SEPLOS
Print Date: 7 April 2021, 3:41 PM
Page 10
Noosa Council documents
7 fy es
Nad Land Cake ier
Pt
HE HEY
Bxctonins w caciatinne
re ahi
ST ae
PLANNING CRITERIA Sie 0 COND
eH PROPOSED ee
a se CES ee,
sateen ur ve a
ANDREW HILLHOUSE
ARCHITECT
alle be reloined
copied without wition pernision of Anatom
Hitwuse Archinect & Dirend Actsocts Py
MAMO
Dimond Architects Ply Lid
design + inovos
NEW LOW CARE WING AND ADDITIONS
TO EXISTING HIGH CARE WING.
COOYAR STREET, NOOSA HEADS
OZCARE NOOSA
Print Date: 7 April 2021, 3:41 PM
Page 11
Noosa Council documents ~ PLANS APPROVED Datta Zl €S. ANDREW HILLHOUSE | CO reo Sten ncee une ARCHITECT COOYAR STREET, NOOSA HEADS Dimond Architects Pry Lid OZCARE NOOSA ae cal Print Date: 7 April 2021, 3:41 PM
Page 12
Noosa Council documents EAST ELEVATION WEST ELEVATION ‘¢copiea wthoo! wiften permiion ol Anton vousa Ache! & Dimes Artic PL ARCHITECT Dimond Architec ts Phy Lid TO EXISTING HIGH CARE WING, COOYAR STREET, NOOSA HEADS OLCARE NOOSA }- PLANS AFPHOVED Moe DATE: 2haBS. oo AL Print Date: 7 April 2021, 3:41 PM
Page 13
Noosa Council documents STING HIGH CARE WING: PLANS APPROVED DAM onl heS i z c few LOW CARE WING AND ADDTTIONS. | FLOORPLAN ANDREW HILLHOUSE eee BIST HIGHT CARE WING, ‘ This crowing &scopyigh! and shal nol be retained ‘cope witout writen permasionct Anew me oma ee power 56 Peeee ie roar (eee Print Date: 7 April 2021, 3:41 PM