Code Fees Impact Fees
Development Assessment
2016/17 2016/17
Type 3: Depot $ 3,980.00 $ 4,976.00
Type 4: Aeronautical
• minor (as determined by Manager, Planning and Environment e.g. private rural airstrip) $ 12,477.00 $ 15,595.00
• major (as determined by Manager, Planning and Environment) $ 103,411.00 $ 129,264.00
6 RESIDENTIAL USES
6.1 Detached House
Detached House (including display home) $ 1,124.00 $ 1,405.00
per display home thereafter $ 121.00 $ 152.00
6.2 Ancillary Dwelling Unit $ 1,880.00 $ 2,350.00
6.3 Multiple Housing
Example: For 7 units, the fee is 3 x $2274 + 4 x $920 = $10,502
Type 1: Relative or employee $ 807.00 $ 1,009.00
Type 2: Duplex $ 3,703.00 $ 4,628.00
Type 3: Retirement and special needs
Fee for unit, 1-3 units $ 1,826.00 $ 2,283.00
Fee per unit, 4-20 units $ 739.00 $ 923.00
Fee per unit, more than 20 units $ 421.00 $ 526.00
Base Fee, 1-5 beds $ 5,479.00 $ 6,849.00
Fee per bed, 6-25 beds $ 172.00 $ 215.00
Fee per bed, more than 25 beds $ 116.00 $ 145.00
Type 4: Conventional
Base fee, included 1-3 units $ 1,826.00 $ 2,283.00
Fee per unit, 4-20 units $ 739.00 $ 923.00
Fee per unit, more than 20 units $ 421.00 $ 526.00
Type 5: Relocatable
Base Fee $ 3,698.00 $ 4,622.00
• plus per site maximum fee capped at 60 sites $ 51.00 $ 65.00
6.4 Visitor Accommodation
Type 1: Home Hosted $ 2,231.00 $ 2,789.00
Type 2: Caravan Park
Base Fee $ 3,698.00 $ 4,622.00
• plus per site maximum fee capped at 60 sites $ 51.00 $ 65.00
Type 3: Rural $ 2,457.00 $ 3,071.00
Type 4: Conventional
Beds 1-5 $ 3,777.00 $ 4,722.00
Beds 6-20 $ 6,680.00 $ 8,350.00
Base fee, includes 21 beds $ 9,579.00 $ 11,974.00
Fee per bed, more than 21 beds $ 116.00 $ 145.00
Fee per unit, 1-3 units $ 1,826.00 $ 2,283.00
Fee per unit, 4-20 units $ 739.00 $ 923.00
Fee per unit, more than 20 units $ 421.00 $ 526.00
7 OTHER
7.1 Post Approval Process (Changes to Conditions / Approvals including Pre Response Request Notices)
Generally In Accordance request - assessment & endorsement of Plans & Documents following an approval $ 472.00 $ -
Reinspection fee relating to conditions of approval $ 663.00 $ -
Request for a permissible change to a development approval under Section 240 or Section 242 of the Sustainable
Planning Act or Section 316 of the Integrated Planning Act.
POA $ -
Request for a permissible change to a development approval, request for a Pre-Request Response Notice and
Conversion Application
Change to a Development Approval and/or a change to conditions for a Detached House $ 871.00 $ -
Minor matters (as determined by Manager, Planning & Environment) $ 1,656.00 $ -
More substantial matters (as determined by Manager Planning & Environment) $ 3,747.00 $ -
Major matter (as determined by Manager, Planning & Environment) 25% of applicable development application fee
Page 18
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalLog in to download the original file
Large file: the download may take up to a minute.
Searchable page text hides email addresses. Original files are unchanged and may show email addresses.