5. Noosa River Dredging - Design Drawings
Very large file (10.3 MB): the original may take a few minutes to open or download. The page text below is quick to read.
LOCALITY PLAN
SITE
NOOSA
HEADS
25
NOOSAVILLE
Noosa River Fish Habitat Area
25
NOTES
25
Drawin
g NRD
T34
T35
T36
T33 T37
COPSE 1
T42
COPSE 2
T43
-008
7
D -00
g NR
in
T1
505783 mE
7080270 mN
T2
T3
T4
T5
T6
T7
T8
T12
T13-T16
T9-T11
T17
T19 T21
T18 T20
T22
T23
T24
T25
T26 T27 T30
T28 T29
T32
T31
Draw Munna Point Caravan
Park Heritage Area
Drawi
ng NRD-
003
D-006
g N R
Drawing NR in
D-004 Draw
Drawing NR
D-005
0 320
160
Meters
Existing Vegetation
LAT
MHWS
GENERAL NOTES Extent of Works Fish Habitat Area
Extent
SCOPE OF WORKS Seaward Work
1. Dredging and nourishment up to maximum 10,000 tonnes Area Extent
2. Dredging undertaken periodically as required. Fish Habitat Area
3. No works within private lease jetty areas. 25m Buffer
4. No works within 25m of Noosa River Fish Habitat Area. Nourishment
5. No marine plants to be disturbed without approval. (Profile Type 2)
6. Works at Munna Point are in the Noosa River Caravan Park Heritage Area
Nourishment
Landward Extent
DESIGN BASIS Noosa River Caravan
7. Localised erosion occurs due to natural coastal processes and boat wakes. This impacts foreshore amenity, vegetation, parkland and Park Heritage Area
infrastructure. Dredge Area 1
8. Current approvals exist for dredge and nourishment, but these focus on historic sand shoals and erosion hotspots (refer drawing NRD-009). (-4.0m AHD max depth)
9. The Noosa River is dynamic. Shoals have migrated and additional areas require nourishment.
Dredge Area 2
10. The proposed works provide a more flexible approach for the Noosa River southern foreshore from Hilton Esplanade to Weyba Creek. This
(-2.5m AHD max depth)
will allow Noosa Shire Council to manage dredging and nourishment activities in response to changing conditions.
Nourishment Area
DESIGN CONDITIONS
VERTICAL DATUM: AHD HORIZONTAL DATUM: GDA94/56
11. Tide Levels from Queensland Tide Tables 2022 [Munna Point].
HAT +0.63m AHD REVISION REGISTER
MHWS +0.34m AHD - - - - - -
MLWS -0.28m AHD - - - - - -
LAT -0.42m AHD
- - - - - -
12. Bathymetric survey by HydraLogic (25/06/2019).
13. Aerial images from Nearmap dated 17/04/2020. - - - - - -
- - - - - -
DREDGING & NOURISHMENT
- - - - - -
14. All measurements in metres. Dimensions not to be scaled.
REV.NO. DATE DESCRIPTION BY ENG. APP.
15. Dredging is to be undertaken in accordance with the Noosaville Concept Dredge management Plan (ICM, 2022).
16. Material is to be sand suitable for nourishment. Any unsuitable material encountered is not to be placed on the foreshore.
17. Dredging to be undertaken with suitable plant (e.g. small cutter suction dredger with cyclone). International
18. Dredge areas are to target shoals in close proximity to the nourishment area and minimise dredge depth by targeting shoals.
19. Dredging is to target uniform extraction across wide area (i.e. avoid digging holes).
Coastal
20. Nourishment profile is to be consistent with natural foreshore profiles and transition smoothly to the existing profile at the works extent. Management
21. No Impacts on marine plants (including mangrove pneumatophores) is deemed to be achieved when works are not occurring within 1m of the OFFICE 50 / G Arm, SYC Marina, Main Beach, 4217, QLD, Australia
marine plant or a specialist marine plant expert provides written advice that the nourishment is beneficial to the stability or health of the marine POST PO Box 306, Main Beach LPO, Main Beach QLD, 4217, Australia
TELEPHONE +61 7 55640564 FAX +61 7 55329147
plant or stipulates that a smaller offset would result in no impact. WEBSITE www.coastalmanagement.com.au
MONITORING & MAINTENANCE PROJECT NAME
22. Foreshore to be monitored periodically, including post-storm events. Noosa River Dredging
23. Dredging to be undertaken as required in response to erosion. DRAWING TITLE
24. Monitoring of dredging activities to be undertaken in accordance with the Noosaville Concept Dredge management Plan (ICM, 2022).
Scheme of Works
DRAWING No. REVISION:
NRD-001 0
DRAWN : MM CHECKED : BC APPROVED : AJ
RPEQ 2876
SIZE: A3 SCALE : As shown DATE : 07 Dec, 2022
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalLog in to download the original file
The download may take a few minutes. On mobile data, it is best to wait for Wi-Fi.