Delegated Report - Code - Planning OPW25 0073 (As Published) · OPW25/0073

of 11

Text shows just the words. Original shows the document exactly as it was published.

               DEVELOPMENT ASSESSMENT DELEGATED REPORT

               Author                  Felix Gough, Development Engineer
                                       Development Assessment



                  APPLICATION DETAILS

                  Application No.                  OPW25/0073

                  Applicant                        Noosa Shire Council

                  Proposal                         Operational Works - Electrical and Street Lighting

                  Properly Made Date               2 May 2025

                  Information Request Date         Not Applicable

                  Information Response Date        Not Applicable

                  Decision Due Date                04/07/2025

                  Report Reviewed &                Mark Lewis
                  Finalised By
                                                   12/06/2025


                  PROPERTY DETAILS

                  Property Address                 62 Lake Macdonald Dr Cooroy Qld 4563

                  RP Description                   Lot 105 SP 118458

                  Land Area                        35370.000 m²

                  Existing Use of Land             The site is vacant.


                  STATUTORY DETAILS

                  SEQRP Designation                Urban Footprint

                  Zone                             Community Facilities

                  Precinct                         Not applicable

                  Local Plan Area                  Cooroy

                  Overlays                         Biodiversity, Waterways and Wetlands
                                                   Extractive Resources – Separation Area
                                                   Landslide Hazard
                                                   Flood Hazard

                  Assessment Type                  Code




Document Set ID: 23742661
Version: 0, Version Date: 01/01/1900
Full text of the other 10 pages

Page 2

               1.     PROPOSAL
               The application seeks approval for Operational Works - Electrical and Street Lighting.
               The locality and proposal plan are included below.




                                                       Figure 1 – Locality




                                                                                                   Page 2 of 11

Document Set ID: 23742661
Version: 0, Version Date: 01/01/1900

Page 3

                                       Figure 2 – Site Plan 1




                                       Figure 3 – Site Plan 2


                                                                Page 3 of 11

Document Set ID: 23742661
Version: 0, Version Date: 01/01/1900

Page 4

               2.     APPLICATION BACKGROUND
               Approved Applications:
                  • OPW23/0190 for Vegetation Clearing
                  • RAL25/0004 for a Reconfiguring a Lot – 1 Lot into 6 Lots (including drainage and park lots)
               The site is currently under assessment for:
                  • OPW25/0057 for Roadwork, Landscaping, Stormwater, Earthworks
               3.     SITE DETAILS
               3.1. Site Description
               The subject site is currently unused.
               3.2. Surrounding Land Uses
               North – Parkland, low density residential development
               East – Low density residential development
               South – Residential development, single detached house and multi-unit, undeveloped state land.
               West – Council Cemetery
               4.     ASSESSMENT
               4.1. Instruments for Statutory Assessment
               Under the Planning Act 2016 the application must be assessed against each of the following
               statutory planning instruments to the extent they are relevant to the development:
               •      State Planning Policy;
               •      South East Queensland Regional Plan;
               •      Planning Regulation 2017; and
               •      Noosa Plan 2020 (25 September 2020).
               4.2. Noosa Plan 2020
               The following codes from the Noosa Plan 2020 are applicable to this development:
               •    Works Codes
               5.     CONSULTATION
               5.1. Referral Agencies
               Not Applicable
               5.2. Internal Council Referrals
               Not applicable
               6.     CONCLUSION & REASONS FOR DECISION
               The proposed development generally complies with the requirements of the planning scheme and
               does not raise any significant issues that cannot be addressed by reasonable and relevant
               conditions. The application is therefore recommended for approval.
               The report is provided in accordance with Section 63(5) of the Planning Act 2016.
               RECOMMENDATION
               With regard to Application No OPW25/0073 for Operational Works - Electrical and Street Lighting
               situated at 62 Lake Macdonald Dr Cooroy Qld 4563 and described as Lot 105 SP 118458, it is
               recommended the application be approved in accordance with the following details for the Decision
               Notice:




                                                                                                        Page 4 of 11

Document Set ID: 23742661
Version: 0, Version Date: 01/01/1900

Page 5

               1.      APPLICATION DETAILS

                   Application No:               OPW25/0073

                   Street address:               62 Lake Macdonald Dr Cooroy Qld 4563

                   Real property description:    Lot 105 SP 118458

                   Planning Scheme:              Noosa Plan 2020 (25 September 2020)

               2.      DECISION DETAILS

               Council decided to issue the following type of approval:
               •       Development Permit for Operational Works - Electrical and Street Lighting
               3.      CURRENCY PERIOD OF APPROVAL

               The currency period for this development approval is stated in the conditions below.
               4.      ASSESSMENT MANAGER CONDITIONS

               APPROVED PLANS
               1.      Development undertaken in accordance with this approval must generally comply with the
                       approved plans of development. The approved plans are listed in the following table unless
                       otherwise amended by these conditions.

                          Plan No.              Rev.   Plan/Document Name                          Date

                          S4400379              P2     ELECTRICAL RETICULATION INSTALL             28/04/2025
                                                        1x 500kVA PMT TRANSFORMER, 4x
                          Sheet 1 of 7
                                                        PILLARS, AND 14x STREET LIGHTS

                          S4400379              P2     ELECTRICAL RETICULATION INSTALL             28/04/2025
                                                        1x 500kVA PMT TRANSFORMER, 4x
                          Sheet 2 of 7
                                                        PILLARS, AND 14x STREET LIGHTS

                          S4400379              P2     ELECTRICAL RETICULATION INSTALL             28/04/2025
                                                        1x 500kVA PMT TRANSFORMER, 4x
                          Sheet 3 of 7
                                                        PILLARS, AND 14x STREET LIGHTS

                          S4400379              P2     ELECTRICAL RETICULATION INSTALL             28/04/2025
                                                        1x 500kVA PMT TRANSFORMER, 4x
                          Sheet 4 of 7
                                                        PILLARS, AND 14x STREET LIGHTS

                          S4400379              P2     ELECTRICAL RETICULATION INSTALL             28/04/2025
                                                        1x 500kVA PMT TRANSFORMER, 4x
                          Sheet 5 of 7
                                                        PILLARS, AND 14x STREET LIGHTS

                          S4400379              P2     ELECTRICAL RETICULATION INSTALL             28/04/2025
                                                        1x 500kVA PMT TRANSFORMER, 4x
                          Sheet 6 of 7
                                                        PILLARS, AND 14x STREET LIGHTS

                          S4400379              P2     ELECTRICAL RETICULATION INSTALL             28/04/2025
                                                        1x 500kVA PMT TRANSFORMER, 4x
                          Sheet 7 of 7
                                                        PILLARS, AND 14x STREET LIGHTS



                                                                                                      Page 5 of 11

Document Set ID: 23742661
Version: 0, Version Date: 01/01/1900

Page 6

               CURRENCY PERIOD
               2.     The Currency Period for this development approval lapses if the development has not
                      substantially started by 12/06/2027, unless an application to extend the currency period is
                      approved by Council.
                      Site Specific Conditions
               3.     Street lighting to be hooded or screened preventing light spill into adjoining properties. The
                      type of light pole and hood to match existing local road lighting in the area for continuity.
                      Bonds
               4.     A site control and/or compliance bond of $2000 must be submitted to Council prior to the
                      pre-start meeting. The pre-start meeting will only be held once Council's Construction
                      Engineering Officer has confirmation that the bond monies have been received by Council.
                      The bond will be refunded less any costs incurred by Council in ensuring compliance with
                      these conditions or any additional inspections incurred for substandard work or work
                      undertaken not in accordance with this permit.
               5.     Bonds must:
                      a.      meet the requirements of council’s relevant Planning Scheme Policy for performance
                              and uncompleted works.
                      b.      be lodged with Council and accompanied by the Bond Administration Fee/s.
                      c.      be requested for release by writing to Council, when relevant approval requirements
                              have been met.
               PRIOR TO COMMENCEMENT OF WORKS
                      Engineering
               6.     All necessary approvals from external service providers (eg Unitywater) and external parties
                      on which the development works are proposed have been obtained and a copy supplied to
                      Council.
               7.     A condition report including photographs of the frontage of the site must be completed and
                      submitted to council at the prestart meeting / prior to any works commencing.
               8.     Certificates demonstrating currency of public liability insurance and works insurance covering
                      the works must be submitted to Council prior to the prestart meeting.
               9.     Council must be contacted at least 5 working days prior to any works commencing to
                      organise a prestart. The contact number to arrange a pre-start meeting is 5329 6500. The
                      pre-start meeting must include the relevant parties for the following aspects of the works:
                      a.      Electrical reticulation works;
               10.    A Construction Management Plan must be submitted to Council prior to the pre-start meeting
                      and must specifically address the following:
                      a.      Traffic Management during all aspects of the construct phase including:
                              i.       A Traffic Management Control Plan in accordance with Manual of Uniform Traffic
                                       Control Devices (MUTCD) detailing all temporary signage and traffic control
                                       measures prior to construction.
                              ii.      Maintenance of safe pedestrian access across the frontage of the site both during
                                       daily construction and after daily construction has ceased
                              iii.     Proposed fencing to the site during the construction phase of the development
                              iv.      Adequate parking arrangements for construction workers
                              v.       No queuing of trucks is permitted on residential streets, especially prior to
                                       7.00am. Further parked trucks must have engines turned off

                                                                                                          Page 6 of 11

Document Set ID: 23742661
Version: 0, Version Date: 01/01/1900

Page 7

                      b.      Maintenance and protection of water quality and existing drainage lines through the
                              construction site through the implementation of appropriate erosion and sediment
                              control measures
                      c.      Works programme identifying key components of the works and their respective
                              durations
                      d.      Establishment of a communication protocol with the general public, adjoining owners,
                              emergency services and local businesses to advise of agreed construction times,
                              impacts on traffic and services and other relevant issues
                      e.      Include a post out to the local residents and businesses advising of the proposed
                              development, the expected time frames and the site contact details
                      f.      Include signage in prominent locations on the boundaries of the site advising of the
                              proposed development, the expected time frames and the site contact details.
                      g.      identification of complaint management procedures including:
                              i.       contact details for the on-site manager
                              ii.      dispute resolution procedures
                      h.      For haulage operations involving significant volumes of fill material or excavated
                              material being transported onto or off the site: details on the location of external fill
                              sites/sources, the haulage route, type of vehicle to be utilised during filling operations
                              and frequency of usage. NB any damage to the existing road system as a result of
                              haulage operations shall be fully repaired at the applicant’s expense.
               11.    Any changes to the details associated with the supervising RPEQ or Principal Contractor
                      during construction, must be notified to council in writing within five business days of the
                      change occurring.
               12.    Any conflict between the development and an existing or proposed service must be referred
                      to the relevant service authority for determination prior to commencement of works.
               DURING CONSTRUCTION
                      Engineering
               13.    The developer must meet any costs to repair damage to any Council asset during
                      construction, where damage is a result of the development works. Damage to assets must
                      be repaired immediately where it creates a hazard to the community. In circumstances where
                      the damage does not create a hazard to the community, it must be repaired immediately on
                      completion of the works associated with the development.
               14.    All works must be supervised by a Registered Professional Engineer of Queensland (RPEQ)
                      who is independent of the Developer and Principal Contractor, and they must certify that all
                      works conform to the Operational Works permit. Where municipal works are involved, such
                      confirmation must be submitted for the respective hold points prior to any site inspection by
                      Council Officers.
               15.    All works must be constructed and work procedure undertaken in accordance with:
                      a.      The approved plans/documents and conditions detailed in this Decision Notice
                      b.      The relevant conditions of the higher order Reconfiguration of Lot approval viz.
                              RAL25/0004 to which this approval relates
                      c.      All relevant Noosa Council Planning Scheme Policies, standard drawings, standard
                              specifications and guidelines




                                                                                                          Page 7 of 11

Document Set ID: 23742661
Version: 0, Version Date: 01/01/1900

Page 8

                      Works within Road Reserve/Reinstatement
               16.    Safe pedestrian and vehicle access on all streets in the vicinity of the development must be
                      maintained at all times. Should footpath/road closures be necessary to carry out construction
                      works, Council’s Engineering Officer must be notified prior to the proposed closure and all
                      requirements complied with.
               17.    All frontage works must match neatly with existing road and verge/footpath features.
                      Additional works beyond the frontage may be required to provide an acceptable transition to
                      existing road and verge/footpath profiles.
               18.    Electrical conduits or other services proposed to be installed within existing and proposed
                      road reserves under existing sealed carriageways, concrete pathways, concrete/sealed
                      driveways or significant vegetation must be installed by boring. Trenching is not permitted,
                      unless specifically approved by Council.
                      Erosion and Sediment Control
               19.    Prescribed Water Contaminants (as defined in Schedule 10 of Environmental Protection
                      Regulation 2019) must not be released from the site or to waters within the site, or be likely
                      to be released should rainfall occur, unless all reasonable and practicable measures are
                      taken to prevent or minimise the release and concentration of contamination.
               20.    Sediment and erosion control measures must be in place prior to works commencing. If such
                      measures are not in place or are not satisfactory, “on the spot” fines may be issued. Such
                      fines can be issued if sediments from the site are found to enter or have the potential to enter
                      Council’s stormwater system, natural waterways, any downstream stormwater filtration
                      system or adversely impacting on other properties. The sediment and erosion control design
                      and measures have NOT been approved, it is the site's Supervising Engineer who is
                      responsible for ensuring that the sediment and erosion control measures have:
                      a.      Been duly designed by an RPEQ or CPESC and constructed in accordance with "best
                              practise" methods,
                      b.      Been revised by an RPEQ or CPESC to address the issues raised by changes in the
                              projected construction schedule and/or methods,
                      c.      Been revised to address predicted rainfall events, and
                      d.      Achieve the desired environmental outcomes.
                      Council may request further controls to be installed should the implemented measures be
                      found inefficient.
               21.    The erosion and sediment control measures must be designed, installed and maintained in
                      accordance with the supervising engineer instructions and the current best practice
                      standards * (Refer to Advisory Note).
               22.    The developer must ensure non-essential exposure of soil is prevented by restricting the
                      extent of disturbance and minimising the duration of soil exposure to adverse weather
                      conditions and effectively turf, cover or stabilise any disturbed area without delay and prior
                      to rainfall occurring.
               23.    The developer must ensure sediment does not leave the site or enter onto adjoining
                      properties or Council’s drainage system due to surface runoff or on tyres of vehicles and/or
                      machinery. It is essential to implement appropriate approved erosion and sediment control
                      measures throughout the site during all phases of construction including vehicle shakedown
                      pad/grid (or similar) at the access to the construction site. Where sediments or other
                      contaminants are deposited on a road, they must be removed so as not to enter Council’s
                      drainage system or waterways.




                                                                                                        Page 8 of 11

Document Set ID: 23742661
Version: 0, Version Date: 01/01/1900

Page 9

               24.    Prior to the completion of the development works, all site surfaces must be effectively
                      stabilised using methods which have achieved effective short-term stabilisation and which
                      will continue to achieve effective stabilisation in the medium to long-term. For the purpose of
                      this condition, an effectively stabilised surface is defined as one that does not, or is not likely
                      to result in visible evidence of soil loss caused by sheet, rill or gully erosion or lead to
                      sedimentation, or lead to water contamination.
                      Damage to Services and Assets
               25.    Any damage caused to existing services and assets as a result of the development works
                      must be repaired at no cost to the asset owner at the following times:
                      a.      where the damage would cause a hazard to pedestrian or vehicle safety, immediately;
                              or
                      b.      where otherwise, upon completion of the works associated with the development.
                      Any repair work which proposes to alter the alignment or level of existing services and assets
                      must first be referred to the relevant service authority for approval.
               FOLLOWING CONSTRUCTION / PRIOR TO COUNCIL SIGNING THE PLAN OF SURVEY
                      Certification
               26.    Upon completion of the work a certificate must be issued by an RPEQ certifying that the
                      works have been constructed in accordance with the Operational Works permit and are
                      suitable for the intended use.
               5.     REFERENCE DOCUMENTS

               Not applicable.
               6.     REFERRAL AGENCIES

               Not applicable.
               7.     ADVISORY NOTES

               The following notes are included for guidance and information purposes only and do not form part
               of the assessment manager conditions:
                      General Advisory Notes
               1.     Council has undertaken an audit check of the Operational Works drawings in relations to the
                      proposed works. A detailed check of the calculations and drawings has not been undertaken,
                      as they have been certified by a RPEQ. The RPEQ bears full responsibility for all aspects of
                      the engineering design. Council reserves the right to require further amendments and/or
                      additions at a later date should design errors become apparent.
               2.     Council reserves the right to call up any performance bond held or levy charges against the
                      property, should emergency works be required to be undertaken by Council to make the site
                      safe due to inactivity on the development site for extended periods of time.
               3.     Should any changes or modifications to the approved plans be required as a result of
                      construction constraints, a “Request to change an existing approval” under the Planning Act
                      2016 must be made. Amended plans clearly indicating the changes must be lodged with this
                      application along with the appropriate fees.
                      Prestart, On and Off Maintenance Inspections Request
               4.     Contact Council on 5329 6500 to arrange a prestart or an inspection giving a minimum of 5
                      business days notice of preferred inspection time.
               5.     If Council officers are required to undertake additional inspections of the same works, a
                      reinspection fee will be applicable in accordance with Council’s Fees and Charges register
                      applicable at the time.


                                                                                                          Page 9 of 11

Document Set ID: 23742661
Version: 0, Version Date: 01/01/1900

Page 10

               6.     A minimum maintenance period of 12 months will apply to all municipal works and thereafter
                      until such time as the works are performing in accordance with the approved design unless
                      noted otherwise.
                      Environmental Advisory Notes
               7.     The Environmental Protection Act 1994 states that a person must not carry out any activity
                      that causes, or is likely to cause, environmental harm unless the person takes all reasonable
                      and practicable measures to prevent or minimise the harm. Environmental harm includes
                      environmental nuisance. In this regard persons and entities, involved in the civil, earthworks,
                      construction and landscaping phases of this development are to adhere to their ‘general
                      environmental duty’ to minimise the risk of causing environmental harm.
                      Erosion and Sediment Control
               8.     Accepted best practice standards include International Erosion Control Association
                      Australasia Best Practice Erosion and Sediment Control.
               9.     Qualified Person, for the purpose of erosion and sediment control is a Certified Professional
                      in Erosion and Sediment Control (CPESC) or suitably experienced Registered Professional
                      Engineer of Queensland (RPEQ).
               10.    As a general rule, a site is determined to have achieved effective short-term stabilisation if
                      at the time of the plan sealing inspection:
                      a.      Methods of stabilisation are:
                              •    appropriate for slopes and slope lengths; and
                              •    are consistent with best practice environmental management practices such as in
                                   the Manual for Erosion and Sediment Control or the IECA Manual; and
                      b.      Stormwater runoff from the site is not currently, and is not likely to result in visible
                              evidence of sedimentation or erosion, or lead to water contamination.
                              If at the time of request for plan sealing, the method of short-term stabilisation has not
                              achieved a level of stability that Council's Officers believe will have a high probability
                              of achieving long term stability (i.e. until house construction has occurred on all lots),
                              Council Officers may take the following matters into consideration in determining
                              whether the site is capable of achieving medium to long-term stability:
                              •    evidence that the site has been effectively stabilised in the short term;
                              •    evidence that soil has been adequately ameliorated;
                              •    evidence that seed of annual and perennial grass species has been applied at an
                                   adequate rate; and
                              •    that grass seed has germinated at a density that is likely to achieve an effective
                                   grass cover.
                              For example, while hydromulch can provide an immediate and effective stabilising
                              cover to soils, the protective cover can be relatively short-lived if vegetation fails to
                              establish before the thin layer of mulch decomposes. So if hydromulch is selected as
                              the method of temporary short term stabilisation, Council Officers will seek to confirm
                              that perennial as well as annual grasses are well established at the time of plan sealing
                              to reduce the risk of instability of the site in the medium to long term. As a general rule,
                              hydromulch will only be accepted as a “patch” fix and should comprise no more than
                              20% of the exposed site area due to the high risk of failure. Due to the requirement to
                              progressively stabilise exposed areas, it is not envisioned that this will present any
                              difficulties for an appropriately managed and compliant site.
               8.     PROPERTY NOTES

               Not applicable.




                                                                                                          Page 10 of 11

Document Set ID: 23742661
Version: 0, Version Date: 01/01/1900

Page 11

               9.     VARIATION APPROVAL DETAILS

               Not applicable.
               10.    FURTHER DEVELOPMENT PERMITS REQUIRED

               Not applicable.
               11.    SUBMISSIONS

               Not applicable.
               12.    RIGHTS OF APPEAL

               You are entitled to appeal against this decision. A copy of the relevant appeal provisions from the
               Planning Act 2016 is attached.
               During the appeal period, you as the applicant may suspend your appeal period and make written
               representations to Council about the conditions contained within the development approval. If
               Council agrees or agrees in part with the representations, a negotiated decision notice will be
               issued. Only one negotiated decision notice may be given.
               13.    OTHER DETAILS

               If you wish to obtain more information about the decision, electronic copies are available online at
               www.noosa.qld.gov.au or at Council Offices.




                                                                                                    Page 11 of 11

Document Set ID: 23742661
Version: 0, Version Date: 01/01/1900

Used in these records

About this file

File size
1.4 MB (small file)
File type
PDF

No other editions are linked here.

Original file

Log in to download the original file

Delegated Report - Code - Planning OPW25 0073 (As Published).pdf · 1.4 MB (small file)

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗