DEVELOPMENT ASSESSMENT DELEGATED REPORT
Author Felix Gough, Development Engineer
Development Assessment
APPLICATION DETAILS
Application No. OPW25/0073
Applicant Noosa Shire Council
Proposal Operational Works - Electrical and Street Lighting
Properly Made Date 2 May 2025
Information Request Date Not Applicable
Information Response Date Not Applicable
Decision Due Date 04/07/2025
Report Reviewed & Mark Lewis
Finalised By
12/06/2025
PROPERTY DETAILS
Property Address 62 Lake Macdonald Dr Cooroy Qld 4563
RP Description Lot 105 SP 118458
Land Area 35370.000 m²
Existing Use of Land The site is vacant.
STATUTORY DETAILS
SEQRP Designation Urban Footprint
Zone Community Facilities
Precinct Not applicable
Local Plan Area Cooroy
Overlays Biodiversity, Waterways and Wetlands
Extractive Resources – Separation Area
Landslide Hazard
Flood Hazard
Assessment Type Code
Document Set ID: 23742661
Version: 0, Version Date: 01/01/1900
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalFull text of the other 10 pages
Page 2
1. PROPOSAL
The application seeks approval for Operational Works - Electrical and Street Lighting.
The locality and proposal plan are included below.
Figure 1 – Locality
Page 2 of 11
Document Set ID: 23742661
Version: 0, Version Date: 01/01/1900
Page 3
Figure 2 – Site Plan 1
Figure 3 – Site Plan 2
Page 3 of 11
Document Set ID: 23742661
Version: 0, Version Date: 01/01/1900
Page 4
2. APPLICATION BACKGROUND
Approved Applications:
• OPW23/0190 for Vegetation Clearing
• RAL25/0004 for a Reconfiguring a Lot – 1 Lot into 6 Lots (including drainage and park lots)
The site is currently under assessment for:
• OPW25/0057 for Roadwork, Landscaping, Stormwater, Earthworks
3. SITE DETAILS
3.1. Site Description
The subject site is currently unused.
3.2. Surrounding Land Uses
North – Parkland, low density residential development
East – Low density residential development
South – Residential development, single detached house and multi-unit, undeveloped state land.
West – Council Cemetery
4. ASSESSMENT
4.1. Instruments for Statutory Assessment
Under the Planning Act 2016 the application must be assessed against each of the following
statutory planning instruments to the extent they are relevant to the development:
• State Planning Policy;
• South East Queensland Regional Plan;
• Planning Regulation 2017; and
• Noosa Plan 2020 (25 September 2020).
4.2. Noosa Plan 2020
The following codes from the Noosa Plan 2020 are applicable to this development:
• Works Codes
5. CONSULTATION
5.1. Referral Agencies
Not Applicable
5.2. Internal Council Referrals
Not applicable
6. CONCLUSION & REASONS FOR DECISION
The proposed development generally complies with the requirements of the planning scheme and
does not raise any significant issues that cannot be addressed by reasonable and relevant
conditions. The application is therefore recommended for approval.
The report is provided in accordance with Section 63(5) of the Planning Act 2016.
RECOMMENDATION
With regard to Application No OPW25/0073 for Operational Works - Electrical and Street Lighting
situated at 62 Lake Macdonald Dr Cooroy Qld 4563 and described as Lot 105 SP 118458, it is
recommended the application be approved in accordance with the following details for the Decision
Notice:
Page 4 of 11
Document Set ID: 23742661
Version: 0, Version Date: 01/01/1900
Page 5
1. APPLICATION DETAILS
Application No: OPW25/0073
Street address: 62 Lake Macdonald Dr Cooroy Qld 4563
Real property description: Lot 105 SP 118458
Planning Scheme: Noosa Plan 2020 (25 September 2020)
2. DECISION DETAILS
Council decided to issue the following type of approval:
• Development Permit for Operational Works - Electrical and Street Lighting
3. CURRENCY PERIOD OF APPROVAL
The currency period for this development approval is stated in the conditions below.
4. ASSESSMENT MANAGER CONDITIONS
APPROVED PLANS
1. Development undertaken in accordance with this approval must generally comply with the
approved plans of development. The approved plans are listed in the following table unless
otherwise amended by these conditions.
Plan No. Rev. Plan/Document Name Date
S4400379 P2 ELECTRICAL RETICULATION INSTALL 28/04/2025
1x 500kVA PMT TRANSFORMER, 4x
Sheet 1 of 7
PILLARS, AND 14x STREET LIGHTS
S4400379 P2 ELECTRICAL RETICULATION INSTALL 28/04/2025
1x 500kVA PMT TRANSFORMER, 4x
Sheet 2 of 7
PILLARS, AND 14x STREET LIGHTS
S4400379 P2 ELECTRICAL RETICULATION INSTALL 28/04/2025
1x 500kVA PMT TRANSFORMER, 4x
Sheet 3 of 7
PILLARS, AND 14x STREET LIGHTS
S4400379 P2 ELECTRICAL RETICULATION INSTALL 28/04/2025
1x 500kVA PMT TRANSFORMER, 4x
Sheet 4 of 7
PILLARS, AND 14x STREET LIGHTS
S4400379 P2 ELECTRICAL RETICULATION INSTALL 28/04/2025
1x 500kVA PMT TRANSFORMER, 4x
Sheet 5 of 7
PILLARS, AND 14x STREET LIGHTS
S4400379 P2 ELECTRICAL RETICULATION INSTALL 28/04/2025
1x 500kVA PMT TRANSFORMER, 4x
Sheet 6 of 7
PILLARS, AND 14x STREET LIGHTS
S4400379 P2 ELECTRICAL RETICULATION INSTALL 28/04/2025
1x 500kVA PMT TRANSFORMER, 4x
Sheet 7 of 7
PILLARS, AND 14x STREET LIGHTS
Page 5 of 11
Document Set ID: 23742661
Version: 0, Version Date: 01/01/1900
Page 6
CURRENCY PERIOD
2. The Currency Period for this development approval lapses if the development has not
substantially started by 12/06/2027, unless an application to extend the currency period is
approved by Council.
Site Specific Conditions
3. Street lighting to be hooded or screened preventing light spill into adjoining properties. The
type of light pole and hood to match existing local road lighting in the area for continuity.
Bonds
4. A site control and/or compliance bond of $2000 must be submitted to Council prior to the
pre-start meeting. The pre-start meeting will only be held once Council's Construction
Engineering Officer has confirmation that the bond monies have been received by Council.
The bond will be refunded less any costs incurred by Council in ensuring compliance with
these conditions or any additional inspections incurred for substandard work or work
undertaken not in accordance with this permit.
5. Bonds must:
a. meet the requirements of council’s relevant Planning Scheme Policy for performance
and uncompleted works.
b. be lodged with Council and accompanied by the Bond Administration Fee/s.
c. be requested for release by writing to Council, when relevant approval requirements
have been met.
PRIOR TO COMMENCEMENT OF WORKS
Engineering
6. All necessary approvals from external service providers (eg Unitywater) and external parties
on which the development works are proposed have been obtained and a copy supplied to
Council.
7. A condition report including photographs of the frontage of the site must be completed and
submitted to council at the prestart meeting / prior to any works commencing.
8. Certificates demonstrating currency of public liability insurance and works insurance covering
the works must be submitted to Council prior to the prestart meeting.
9. Council must be contacted at least 5 working days prior to any works commencing to
organise a prestart. The contact number to arrange a pre-start meeting is 5329 6500. The
pre-start meeting must include the relevant parties for the following aspects of the works:
a. Electrical reticulation works;
10. A Construction Management Plan must be submitted to Council prior to the pre-start meeting
and must specifically address the following:
a. Traffic Management during all aspects of the construct phase including:
i. A Traffic Management Control Plan in accordance with Manual of Uniform Traffic
Control Devices (MUTCD) detailing all temporary signage and traffic control
measures prior to construction.
ii. Maintenance of safe pedestrian access across the frontage of the site both during
daily construction and after daily construction has ceased
iii. Proposed fencing to the site during the construction phase of the development
iv. Adequate parking arrangements for construction workers
v. No queuing of trucks is permitted on residential streets, especially prior to
7.00am. Further parked trucks must have engines turned off
Page 6 of 11
Document Set ID: 23742661
Version: 0, Version Date: 01/01/1900
Page 7
b. Maintenance and protection of water quality and existing drainage lines through the
construction site through the implementation of appropriate erosion and sediment
control measures
c. Works programme identifying key components of the works and their respective
durations
d. Establishment of a communication protocol with the general public, adjoining owners,
emergency services and local businesses to advise of agreed construction times,
impacts on traffic and services and other relevant issues
e. Include a post out to the local residents and businesses advising of the proposed
development, the expected time frames and the site contact details
f. Include signage in prominent locations on the boundaries of the site advising of the
proposed development, the expected time frames and the site contact details.
g. identification of complaint management procedures including:
i. contact details for the on-site manager
ii. dispute resolution procedures
h. For haulage operations involving significant volumes of fill material or excavated
material being transported onto or off the site: details on the location of external fill
sites/sources, the haulage route, type of vehicle to be utilised during filling operations
and frequency of usage. NB any damage to the existing road system as a result of
haulage operations shall be fully repaired at the applicant’s expense.
11. Any changes to the details associated with the supervising RPEQ or Principal Contractor
during construction, must be notified to council in writing within five business days of the
change occurring.
12. Any conflict between the development and an existing or proposed service must be referred
to the relevant service authority for determination prior to commencement of works.
DURING CONSTRUCTION
Engineering
13. The developer must meet any costs to repair damage to any Council asset during
construction, where damage is a result of the development works. Damage to assets must
be repaired immediately where it creates a hazard to the community. In circumstances where
the damage does not create a hazard to the community, it must be repaired immediately on
completion of the works associated with the development.
14. All works must be supervised by a Registered Professional Engineer of Queensland (RPEQ)
who is independent of the Developer and Principal Contractor, and they must certify that all
works conform to the Operational Works permit. Where municipal works are involved, such
confirmation must be submitted for the respective hold points prior to any site inspection by
Council Officers.
15. All works must be constructed and work procedure undertaken in accordance with:
a. The approved plans/documents and conditions detailed in this Decision Notice
b. The relevant conditions of the higher order Reconfiguration of Lot approval viz.
RAL25/0004 to which this approval relates
c. All relevant Noosa Council Planning Scheme Policies, standard drawings, standard
specifications and guidelines
Page 7 of 11
Document Set ID: 23742661
Version: 0, Version Date: 01/01/1900
Page 8
Works within Road Reserve/Reinstatement
16. Safe pedestrian and vehicle access on all streets in the vicinity of the development must be
maintained at all times. Should footpath/road closures be necessary to carry out construction
works, Council’s Engineering Officer must be notified prior to the proposed closure and all
requirements complied with.
17. All frontage works must match neatly with existing road and verge/footpath features.
Additional works beyond the frontage may be required to provide an acceptable transition to
existing road and verge/footpath profiles.
18. Electrical conduits or other services proposed to be installed within existing and proposed
road reserves under existing sealed carriageways, concrete pathways, concrete/sealed
driveways or significant vegetation must be installed by boring. Trenching is not permitted,
unless specifically approved by Council.
Erosion and Sediment Control
19. Prescribed Water Contaminants (as defined in Schedule 10 of Environmental Protection
Regulation 2019) must not be released from the site or to waters within the site, or be likely
to be released should rainfall occur, unless all reasonable and practicable measures are
taken to prevent or minimise the release and concentration of contamination.
20. Sediment and erosion control measures must be in place prior to works commencing. If such
measures are not in place or are not satisfactory, “on the spot” fines may be issued. Such
fines can be issued if sediments from the site are found to enter or have the potential to enter
Council’s stormwater system, natural waterways, any downstream stormwater filtration
system or adversely impacting on other properties. The sediment and erosion control design
and measures have NOT been approved, it is the site's Supervising Engineer who is
responsible for ensuring that the sediment and erosion control measures have:
a. Been duly designed by an RPEQ or CPESC and constructed in accordance with "best
practise" methods,
b. Been revised by an RPEQ or CPESC to address the issues raised by changes in the
projected construction schedule and/or methods,
c. Been revised to address predicted rainfall events, and
d. Achieve the desired environmental outcomes.
Council may request further controls to be installed should the implemented measures be
found inefficient.
21. The erosion and sediment control measures must be designed, installed and maintained in
accordance with the supervising engineer instructions and the current best practice
standards * (Refer to Advisory Note).
22. The developer must ensure non-essential exposure of soil is prevented by restricting the
extent of disturbance and minimising the duration of soil exposure to adverse weather
conditions and effectively turf, cover or stabilise any disturbed area without delay and prior
to rainfall occurring.
23. The developer must ensure sediment does not leave the site or enter onto adjoining
properties or Council’s drainage system due to surface runoff or on tyres of vehicles and/or
machinery. It is essential to implement appropriate approved erosion and sediment control
measures throughout the site during all phases of construction including vehicle shakedown
pad/grid (or similar) at the access to the construction site. Where sediments or other
contaminants are deposited on a road, they must be removed so as not to enter Council’s
drainage system or waterways.
Page 8 of 11
Document Set ID: 23742661
Version: 0, Version Date: 01/01/1900
Page 9
24. Prior to the completion of the development works, all site surfaces must be effectively
stabilised using methods which have achieved effective short-term stabilisation and which
will continue to achieve effective stabilisation in the medium to long-term. For the purpose of
this condition, an effectively stabilised surface is defined as one that does not, or is not likely
to result in visible evidence of soil loss caused by sheet, rill or gully erosion or lead to
sedimentation, or lead to water contamination.
Damage to Services and Assets
25. Any damage caused to existing services and assets as a result of the development works
must be repaired at no cost to the asset owner at the following times:
a. where the damage would cause a hazard to pedestrian or vehicle safety, immediately;
or
b. where otherwise, upon completion of the works associated with the development.
Any repair work which proposes to alter the alignment or level of existing services and assets
must first be referred to the relevant service authority for approval.
FOLLOWING CONSTRUCTION / PRIOR TO COUNCIL SIGNING THE PLAN OF SURVEY
Certification
26. Upon completion of the work a certificate must be issued by an RPEQ certifying that the
works have been constructed in accordance with the Operational Works permit and are
suitable for the intended use.
5. REFERENCE DOCUMENTS
Not applicable.
6. REFERRAL AGENCIES
Not applicable.
7. ADVISORY NOTES
The following notes are included for guidance and information purposes only and do not form part
of the assessment manager conditions:
General Advisory Notes
1. Council has undertaken an audit check of the Operational Works drawings in relations to the
proposed works. A detailed check of the calculations and drawings has not been undertaken,
as they have been certified by a RPEQ. The RPEQ bears full responsibility for all aspects of
the engineering design. Council reserves the right to require further amendments and/or
additions at a later date should design errors become apparent.
2. Council reserves the right to call up any performance bond held or levy charges against the
property, should emergency works be required to be undertaken by Council to make the site
safe due to inactivity on the development site for extended periods of time.
3. Should any changes or modifications to the approved plans be required as a result of
construction constraints, a “Request to change an existing approval” under the Planning Act
2016 must be made. Amended plans clearly indicating the changes must be lodged with this
application along with the appropriate fees.
Prestart, On and Off Maintenance Inspections Request
4. Contact Council on 5329 6500 to arrange a prestart or an inspection giving a minimum of 5
business days notice of preferred inspection time.
5. If Council officers are required to undertake additional inspections of the same works, a
reinspection fee will be applicable in accordance with Council’s Fees and Charges register
applicable at the time.
Page 9 of 11
Document Set ID: 23742661
Version: 0, Version Date: 01/01/1900
Page 10
6. A minimum maintenance period of 12 months will apply to all municipal works and thereafter
until such time as the works are performing in accordance with the approved design unless
noted otherwise.
Environmental Advisory Notes
7. The Environmental Protection Act 1994 states that a person must not carry out any activity
that causes, or is likely to cause, environmental harm unless the person takes all reasonable
and practicable measures to prevent or minimise the harm. Environmental harm includes
environmental nuisance. In this regard persons and entities, involved in the civil, earthworks,
construction and landscaping phases of this development are to adhere to their ‘general
environmental duty’ to minimise the risk of causing environmental harm.
Erosion and Sediment Control
8. Accepted best practice standards include International Erosion Control Association
Australasia Best Practice Erosion and Sediment Control.
9. Qualified Person, for the purpose of erosion and sediment control is a Certified Professional
in Erosion and Sediment Control (CPESC) or suitably experienced Registered Professional
Engineer of Queensland (RPEQ).
10. As a general rule, a site is determined to have achieved effective short-term stabilisation if
at the time of the plan sealing inspection:
a. Methods of stabilisation are:
• appropriate for slopes and slope lengths; and
• are consistent with best practice environmental management practices such as in
the Manual for Erosion and Sediment Control or the IECA Manual; and
b. Stormwater runoff from the site is not currently, and is not likely to result in visible
evidence of sedimentation or erosion, or lead to water contamination.
If at the time of request for plan sealing, the method of short-term stabilisation has not
achieved a level of stability that Council's Officers believe will have a high probability
of achieving long term stability (i.e. until house construction has occurred on all lots),
Council Officers may take the following matters into consideration in determining
whether the site is capable of achieving medium to long-term stability:
• evidence that the site has been effectively stabilised in the short term;
• evidence that soil has been adequately ameliorated;
• evidence that seed of annual and perennial grass species has been applied at an
adequate rate; and
• that grass seed has germinated at a density that is likely to achieve an effective
grass cover.
For example, while hydromulch can provide an immediate and effective stabilising
cover to soils, the protective cover can be relatively short-lived if vegetation fails to
establish before the thin layer of mulch decomposes. So if hydromulch is selected as
the method of temporary short term stabilisation, Council Officers will seek to confirm
that perennial as well as annual grasses are well established at the time of plan sealing
to reduce the risk of instability of the site in the medium to long term. As a general rule,
hydromulch will only be accepted as a “patch” fix and should comprise no more than
20% of the exposed site area due to the high risk of failure. Due to the requirement to
progressively stabilise exposed areas, it is not envisioned that this will present any
difficulties for an appropriately managed and compliant site.
8. PROPERTY NOTES
Not applicable.
Page 10 of 11
Document Set ID: 23742661
Version: 0, Version Date: 01/01/1900
Page 11
9. VARIATION APPROVAL DETAILS
Not applicable.
10. FURTHER DEVELOPMENT PERMITS REQUIRED
Not applicable.
11. SUBMISSIONS
Not applicable.
12. RIGHTS OF APPEAL
You are entitled to appeal against this decision. A copy of the relevant appeal provisions from the
Planning Act 2016 is attached.
During the appeal period, you as the applicant may suspend your appeal period and make written
representations to Council about the conditions contained within the development approval. If
Council agrees or agrees in part with the representations, a negotiated decision notice will be
issued. Only one negotiated decision notice may be given.
13. OTHER DETAILS
If you wish to obtain more information about the decision, electronic copies are available online at
www.noosa.qld.gov.au or at Council Offices.
Page 11 of 11
Document Set ID: 23742661
Version: 0, Version Date: 01/01/1900
Used in these records
Delegated Report - Code - Planning OPW25 0073 (As Published).pdfRelated documentApplication case desk ↗
About this file
- File size
- 1.4 MB (small file)
- File type
No other editions are linked here.