GENERAL COMMITTEE MEETING AGENDA 17 JUNE 2019
ATTACHMENT 1
Page 7 of 20
GENERAL COMMITTEE MEETING AGENDA 17 JUNE 2019
ATTACHMENT 1
In the Planning and Environment Court No. 2881 of 2018
Held at: Brisbane
Between: NOOSA AIRFIELD PTY LTD Appellant
And: NOOSA SHIRE COUNCIL Respondent
MEDIATION AGREEMENT
The parties agree to resolve the appeal on the following basis:
1. The Appellant will remove:
(a) concrete and other builders waste from Location 1;
(b) concrete fill material and rubble adjacent to causeway in Location 2; and
(c) concrete and other builders waste in Location 3 and adjacent access way.
As shown on attached plan (Attachment A)
2. The Appellant will provide certification from a suitably qualified person that any material to be
retained on-site, for the purpose of the maintenance of the landing strip, is clean fill.
3. The Appellant will undertake the removal of fill (as per Point 1 above) and provide the
certification as per Point 2 within 90 days of this agreement. If the Appellant requires
additional time to complete the works due to circumstances beyond their control, it will
contact Council to seek an extension. Council will not unreasonably refuse to grant an
extension request.
4. By 4pm 26 April 2019, the Appellant will prepare and submit a dimensioned plan showing the
proposed vegetation rehabilitation areas and future car parking area in Location 3. This plan
does not imply any approval of the car parking area by the Council.
5. At the next available Council meeting, Council officers will recommend to Full Council that the
appeal be resolved on the basis of Points 1 to 4 above.
6. Subject to approval of the Full Council to the proposed works in Points 1 to 4 above, within:
a) 90 days of the Full Council approval, the Appellant will submit to Council for approval a
Revegetation Plan for Location 3 detailing the revegetation, species type and
maintenance regime. The maintenance regime being no less than 3 years. The Council
will not unreasonably withhold approval of the Revegetation Plan.
b) 90 days of the approval of the Revegetation Plan the Appellant will undertake the
works required by that Revegetation Plan.
Subject to Council approval in Point 5 above, the appeal will be dismissed and the parties agree to
bear their own costs.
Page 7 of 20See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalLog in to download the original file
Large file: the download may take up to a minute.
Searchable page text hides email addresses. Original files are unchanged and may show email addresses.