8 Conclusions
Following the assessment and analyses presented in this report, it is concluded that:
An empirical assessment of the site’s peak car parking demand for the various uses at a full 299 bed
occupancy is summarised below:
- School Camp: 38 cars / 7 buses.
- School Holiday Camp:
102 cars / 4 buses at drop off.
118 cars / 4 buses at pick up.
- Weekend Use: 108 cars.
The proposed 126 car parks (88 formal / 38 informal) on the site is expected to accommodate
typical site demands.
The car parking is either existing, or informal, with the informal (new) parking designed in
consideration of the Australian Standards.
Appropriate on-site accessibility by 12.5m and 14.5m rigid vehicles has been demonstrated by
swept path assessments.
The traffic generation for the various use components is detailed in the body of this report.
Assuming the site’s 299 beds are fully occupied, the daily two-way traffic volume on Kabi Road,
with the addition of the development, is 73 – 403 vehicles per day. On this basis, upgrade of the
existing Kabi Road carriageway to a 6.2m wide seal width is recommended.
The traffic generated by the development at the Kabi Road / Cootharaba Road intersection does
not trigger upgrade works. It is however noted that the existing intersection does not meet the BAR
design requirements of AUSTROADS.
The intersection of Kabi Road / Cootharaba Road, at a minimum, will need to be upgrade to match
the upgraded 6.2m Kabi Road pavement width.
www.bmctraffic.com.au 26
BMC22089: 59 Kabi Road, Cootharaba
22 March 2023
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalLog in to download the original file
The download may take up to a minute.