51 640 311 842
CONTACT
[email protected]
arcosgroup.com.au
OFFICES
Sunshine Coast | Brisbane | Gold Coast
reduce such risk is usually not required unless reasonably practicable measures are available at low
cost in terms of money, time and effort.”.
AGS suggest that regulators generally accept risk levels of “low” or lower as a level of
acceptable risk.
AGS prepared a semi-quantitative assessment tool for determining the level of risk for a site.
The tool separates the potential hazards for a site, from a stability context, and rates them with
a level of risk frequency. The multiplication of these individual risk frequency summates as the
risk frequency rating which is then measured against the levels of risk nominated by AGS.
The results of this analysis are shown in Table 1.
Table 1: Results of AGS Qualitative Risk Assessment
Hazard Likelihood Consequence Risk Level
Global Failure Barely Credible Catastrophic Low
Shallow slumping or slide of Unlikely Minor Low
surface soils
Based on the results of the AGS assessment, the perceived risk based on the conditions
encountered and information available at the time of the assessment is “Low”.
7.0 Hillside Construction
The following works should be implemented in addition to other items highlighted within this
document. These points are considered to be typical good hillside construction practice as
explained in attached documentation:
• Foundations should be founded into stiff (or stronger) residual clay.
• Where slopes are not supported by an engineer designed support system, natural slopes
within or near building envelope or movement sensitive areas should be no steeper than
2H:1V.
• Building platform fill should be limited to a maximum height of 1 m. The filling should be
step keyed into the natural slope and battered no steeper than 3H:1V unless an engineer
designed retention system is in place.
• Unsupported cuts steeper than 2.5H:1V will require engineer designed retention systems.
• All stormwater and surface water is to be collected and discharged by an approved
stormwater drainage system. The use of subsurface drainage systems are not suitable
unless greater than 50 m downslope from the envelope at this site.
• Ongoing maintenance of the effluent wastewater area is also considered mandatory. The
location of the application area should be located below the proposed building. Plumbing
and services must also not be allowed to leak and regular maintenance and inspections
should be undertaken.
09 Dec 2021 Proposed Subdivision and Residence
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalVery large file: the download may take a few minutes. If you are on mobile data, it is best to wait until you are on Wi-Fi.
Searchable page text hides email addresses. Original files are unchanged and may show email addresses.