                        A person must not use equipment on any day if it makes or causes noise to be made -
                        From 10pm to 7am: More than the lower of either –
                        •       40 dB(A)
                        •       3 dB(A) above the background noise level
                        •       No audible noise for pool pumps apply during these hours.
                        From 7am to 7pm: More than the lower of either –
                        •       50 dB(A)
                        •       5 dB(A) above the background noise level
                        From 7pm to 10pm: More than 3 dB(A) above the background noise level.
                 56.    Submission of written certification from a suitably qualified person confirming that the
                        noise levels from all mechanical equipment comply with the cause above when
                        measured at either the residential boundary or outside the most exposed part of an
                        affected building, whichever is the closest to the equipment.
                        The assessment and certification is required immediately after installation of the
                        equipment and prior to any occupation of the building, and in a format approved by
                        Council. This assessment must take into account noise from any other fixed equipment
                        on the property e.g. swimming pool pump, heating/cooling equipment, etc that may
                        increase the overall noise level emitted.
                        Advice: It is highly recommended that the person you engage to certify the installation
                        Is involved at the plan development stage so they can recommend where this equipment
                        is best located. They can also advise about noise enclosures and can make other
                        suggestions to avoid noise problems. It is a lot more costly to try and deal with noise
                        problems after everything is built.
                 57.    All noise controlled measures set out in the Environmental Noise Level Study for
                        Proposed Residential Budget Accommodation – Development, 102 Pacific Avenue,
                        Sunshine Beach (Report No: R09043/02260/Rev.0/23.04.09) shall be incorporated into
                        the development.
                        Written certification shall be submitted from an Acoustic Consultant after completion of
                        works confirming that these noise control measures have been incorporated into the
                        development.
                 58.    All external facing windows to the south east and north east elevations of the buildings
                        shall be double glazed (or equivalent sound suppressant construction approved by
                        Council), so as to minimise the impacts of sound emanating from the development.
                 59.    Noise from building works associated with residential development shall comply with the
                        following –
                        59.1.          Limited to between 7:00am to 6:30pm Monday to Saturday.
                        59.2.          All reasonable measures are taken to minimise noise emissions.
                        59.3.          Not permitted on Sunday or public holidays
                 Additional Conditions – 17 December 2009
                 60.    Prior to the commencement of the use of each stage of development, the required
                        contributions shall be paid to Council.
                 61.    All access, carparking, stormwater, landscaping, frontage works, water and sewer works
                        are to be constructed prior to the commencement of the use of stage 1.
                 62.    Stage 2 is to be constructed within 4 years of the use of stage 1 commencing.
                 63.    Suitable dense screening vegetation is to be provided around the building pad of stage
                        2. A temporary landscaping plan is to be submitted and approved by Council prior to the
                        commencement of the use of stage 1.

                                                                                                        Page 10 of 24
Document Set ID: 24061481
Version: 7, Version Date: 28/08/2025

Used in these records

About this file

File size
254 KB (small file)
File type
PDF

No other editions are linked here.

Original file

Log in to download the original file

Other Change Decision Notice - Council Meeting Decision 132007 2446 05.pdf · 254 KB (small file)

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.