2016-12-12 General Committee Meeting Notes

of 11

Page text shows just the words. Original shows the document exactly as it was published.

Text sections have not been matched to the original PDF pages. Use the original document to check page numbers.

RECOMMENDATIONS ONLY – NOT THE FINAL DECISION OF COUNCIL
GENERAL COMMITTEE MEETING                                                   12 DECEMBER 2016



GENERAL COMMITTEE MEETING - LIVE RECORD MEETING NOTES
12 DECEMBER 2016 – Crs. Frank Wilkie (Chair), Jess Glasgow, Ingrid Jackson,
Joe Jurisevic, Frank Pardon, Brian Stockwell and Tony Wellington.


1   MCU6/0066 & OPW16/0133 - DEVELOPMENT APPLICATION FOR MATERIAL CHANGE
    OF USE FOR A SERVICE STATION, CONVENIENCE SHOP AND FOOD OUTLET AND
    OPERATIONAL WORKS FOR SIGNAGE AT 6 TAYLOR COURT, COOROY
    Refer to Further Report provided at Item 3.

2   OPW16/0016 - APPLICATION FOR DEVELOPMENT PERMIT FOR OPERATIONAL
    WORKS - PRESCRIBED TIDAL WORKS (DECK) AT 2 PARKYN COURT, TEWANTIN
    Motion
    Moved:           Cr Pardon
    Seconded:        Cr Glasgow
    That Council note the report by the Coordinator Engineering to the Planning & Environment
    Committee Meeting dated 6 December 2016 regarding application OPW16/0016 for a
    Development Permit for Operational Works – Prescribed Tidal Works (Deck) at 2 Parkyn
    Court, Tewantin and refuse the application for the following reasons:
    1.   The proposed deck does not comply with Overall Outcome and Specific Outcomes of
         the Noosa Plan’s Watercourses Works Code,
    2.   The proposed deck is contrary to the “Purpose of Code” of the IDAS Code of the
         Coastal Protection and Management Regulation 2003 and does not comply with
         Specific Outcomes of the IDAS Code of the Coastal Protection and Regulation 2003,
    3.   The proposed development will create the potential to intensify the commercial uses
         by increasing the available deck areas within the marina,
    4.   The proposed deck adds a substantial area and additional built form on the Noosa
         River, is likely to increase traffic volumes on adjoining lands and there are insufficient
         parking facilities available in the area.

    Amendment No. 1
    Moved:           Cr Stockwell
    Seconded:        Cr Jurisevic
    The motion be amended by including at the end of item 1 the words “and the development
    reduces public access to the foreshore area and the natural values of the Noosa River” and
    adding a new item 5 to read:
    “5. The proposed deck does not comply with Overall Outcome and Specific Outcomes of
          the Noosa Plan’s Tewantin and Doonan Locality Code and has the potential to:
          adversely affect the amenity enjoyed by users of other premises including acoustic
             and visual qualities;
          reduce the area of open space conducive to community interaction and wellbeing;
             and
          establish a built form that impacts on natural landforms and reduce the natural
             character and visual amenity of the Noosa River system.”
                                                                                         Lost.

                                                                                     Page 1 of 11
Log in to download the original file

2016-12-12 General Committee Meeting Notes(PDF, 436KB).pdf · 446 KB (small file)

Searchable page text hides email addresses. Original files are unchanged and may show email addresses.

Full text of the other 10 sections

Section 2

RECOMMENDATIONS ONLY – NOT THE FINAL DECISION OF COUNCIL
GENERAL COMMITTEE MEETING                                                   12 DECEMBER 2016


    Amendment No. 2
    Moved:           Cr Wellington
    Seconded:        Cr Jurisevic
    The motion be amended by including at the end of item 1 the words “and Tewantin and
    Doonan Locality Code”.
                                                                                          Carried.
    Committee Recommendation
    Moved:           Cr Pardon
    Seconded:        Cr Glasgow
    That Council note the report by the Coordinator Engineering to the Planning & Environment
    Committee Meeting dated 6 December 2016 regarding application OPW16/0016 for a
    Development Permit for Operational Works – Prescribed Tidal Works (Deck) at 2 Parkyn
    Court, Tewantin and refuse the application for the following reasons:
    1.   The proposed deck does not comply with Overall Outcome and Specific Outcomes of
         the Noosa Plan’s Watercourses Works Code and Tewantin and Doonan Locality Code,
    2.   The proposed deck is contrary to the “Purpose of Code” of the IDAS Code of the
         Coastal Protection and Management Regulation 2003 and does not comply with
         Specific Outcomes of the IDAS Code of the Coastal Protection and Regulation 2003,
    3.   The proposed development will create the potential to intensify the commercial uses
         by increasing the available deck areas within the marina,
    4.   The proposed deck adds a substantial area and additional built form on the Noosa
         River, is likely to increase traffic volumes on adjoining lands and there are insufficient
         parking facilities available in the area.
                                                                                          Carried.


3   MCU16/0066 & OPW16/0133 - FURTHER REPORT - APPLICATION FOR SERVICE
    STATION, CONVENIENCE SHOP & FOOD OUTLET & SIGNAGE AT 6 TAYLOR COURT,
    COOROY
    Committee Recommendation
    Moved:           Cr Wellington
    Seconded:        Cr Pardon
    That Council note the reports by the Development Planner to the Planning & Environment
    Committee meeting dated 6 December 2016 and the General Committee meeting dated 12
    December 2016 and refuse Application No. MCU16/0066 & OPW16/0133 for a Development
    Permit for Material Change of Use of Premises - Retail Business Type 2 Shop & Type 5
    Vehicle Uses, Entertainment & Dining Business Type 1 - Food & Beverages and Operational
    Works for Signage, situated at 6 Taylor Court, Cooroy for the following reasons:
    1.   The development raises conflicts with The Noosa Plan and its current and future land
         use intent for the subject site and water supply catchment area.
    2.   The proposal is not conveniently located or readily accessible for the local community
         and will not provide a significant benefit to that community.



                                                                                     Page 2 of 11

Section 3

RECOMMENDATIONS ONLY – NOT THE FINAL DECISION OF COUNCIL
GENERAL COMMITTEE MEETING                                                     12 DECEMBER 2016


    3.   The development will adversely impact on the local villages and towns by reducing
         patronage to these centres and therefore will not improve community wellbeing.
    4.   The proposal is contrary to the SEQ Regional Plan’s Regional Policy 11.5.1 to identify
         and protect existing and potential drinking water catchments from inappropriate land
         use as the development would pose an unacceptable risk to water quality.
    5.   The proposal is contrary to the Environmental Protection (Water) Policy for Mary River
         Environmental Values and Water Quality Objectives as the proposed surface water
         quality exceeds these objectives in relation to Total Nitrogen and Total Phosphorous
         and the applicant has not addressed the impact the in-ground storage of fuel will have
         on ground water.
    6.   The proposal fails to meet the Plan of Development for the site, including the provision
         of a 10 metre landscape buffer to visually screen the development from the Bruce
         Highway.
    7.   The proposed illumination of the advertising devices is contrary to the Advertising
         Devices Code and the intent of the Plan of Development for the site.
                                                                                            Carried.


4   MCU16/0090 - DEVELOPMENT APPLICATION FOR MATERIAL CHANGE OF USE FOR
    WELLBEING TYPE 2 - SOCIAL (SUNSHINE BUTTERFLIES) AT 468 MCKINNON DRIVE,
    COOROIBAH
    Committee Recommendation
    Moved:            Cr Wellington
    Seconded:         Cr Pardon
    That Council note the report by the Development Planner to the General Committee Meeting
    dated 12 December 2016 regarding Application No. MCU16/0090 for a Development Permit
    for Material Change of Use of Premises - Wellbeing Type 2 - Social (respite centre) situated
    at 468 McKinnon Drive, Cooroibah and:
    A.   Approve the application in accordance with the following conditions:
                PLANNING
                Approved Plans
         1.     Development undertaken in accordance with this approval must generally comply
                with the approved plans of development. The approved plans are listed in the
                following table unless otherwise amended by these conditions.
                  Plan No.   Rev.   Plan/Document Name                                    Date
                  L002       A      Landscape Concept Plan, prepared by Sunshine          20.9.2015
                                    Gardens
                Nature and Extent of Approved Use
         2.     The approved use is Wellbeing Type 2 – Social being for a respite centre for
                people living with disabilities and their families and associated ancillary office and
                agricultural uses. The approval does not include a cafe.
         3.     The maximum number of special events per year is six (6).



                                                                                       Page 3 of 11

Section 4

RECOMMENDATIONS ONLY – NOT THE FINAL DECISION OF COUNCIL
GENERAL COMMITTEE MEETING                                                12 DECEMBER 2016


              Landscaping
        4.    Existing trees on the site and within road reserves must be retained, except
              where required to be removed to accommodate the approved use.
        5.    All native trees must be retained within the Biodiversity Overlay. The area must
              be rehabilitated with koala food trees such as Eucalyptus robusta, Eucalyptus
              tereticornis and Eucalyptus grandis.
        6.    Screening vegetation must be planted along all boundaries in accordance with
              Council’s Planning Scheme Policy PSP3 Landscaping Plants and Guidelines and
              the approved Landscape Concept Plan. The planted vegetation must consist of
              native and endemic species.
        7.    A minimum of 3m of screening vegetation must be provided between the
              boundary and any car parking.
              Built Form and Setbacks
        8.    The maximum height of the development must not exceed 9 metres at the pitch
              of the roof above the finished ground level and the natural ground level and must
              not exceed be 2 storeys.
        9.    All buildings and structures must be setback a minimum of 6 metres from all
              boundaries.
              Performance Bond
        10.   Security in the form of a cash bond or trading bank guarantee to the sum of
              $10,000 must be submitted to Council, to secure performance of all conditions of
              this approval, prior to the issue of a Development Permit for Operational Works.
              The cash bond or trading bank guarantee will be returned on performance of the
              conditions of approval less any costs incurred by Council in respect of enforcing
              performance of this permit. Council reserves the right to call upon the bond or
              guaranteed sum to effect compliance with conditions.
              Street Identification
        11.   The street address of the development must be clearly visible and discernible
              from the primary frontage of the site by the provision of a street number and,
              where appropriate, the developments name.
              ENGINEERING
              Site Access and Driveways
        12.   Sealed access driveways must be provided from McKinnon Drive to all parking
              and manoeuvring areas of the development. The works must be undertaken in
              accordance with the Department of Infrastructure, Local Government and
              Planning response reference number SDA-0816-032888 dated 7 November
              2016 and generally in accordance with Council’s standard drawing RS-056.
        13.   Approval from the Department of Transport and Main Roads for the final design
              of the site access and driveway works must be submitted in writing to Council
              prior to the issue of any Development Permit for Operational Works.




                                                                                 Page 4 of 11

Section 5

RECOMMENDATIONS ONLY – NOT THE FINAL DECISION OF COUNCIL
GENERAL COMMITTEE MEETING                                                  12 DECEMBER 2016


              Car Parking
        14.   A minimum of 21 car parking spaces must be provided and marked on the site
              and made available and accessible at all times while the use is open for business.
              The works must be undertaken in accordance with an Operational Works
              approval and must include in particular:
              a.    service vehicle parking, manoeuvring and standing spaces
              b.    dimensions, crossfalls and gradients in accordance with Australian
                    Standards      AS/NZS2890.1:2004,      AS/NZS2890.6:2009      and
                    AS2890.2:2002.
        15.   The carparking area must be constructed with either a sealed surface or other
              bound material that is suitable for the intended use. Certification of the proposed
              surfacing from an RPEQ must be submitted as part of the operational works
              application.
        16.   All car parking areas and access driveways must be maintained exclusively for
              vehicle parking and manoeuvring and kept in a tidy and safe condition at all times.
        17.   Directional signage must be provided to direct visitors and guests to the car
              parking spaces provided on site.
              Traffic Management
        18.   A traffic management plan for both the regular operation of the development and
              any special events must be submitted as part of the Operational Works
              application. The traffic management plan must include but not be limited to:
              a.    day to day parking of the various vehicle types
              b.    parking for larger vehicles (buses, deliveries, waste collection etc)
              c.    overflow parking for special events
              d.    temporary traffic control measures on McKinnon Drive
              e.    endorsement by the Department of Transport and Main Roads.
              Stormwater Drainage
        19.   Stormwater runoff from the development must be disposed of on-site without
              causing scour or damage to the subject site or any adjoining property. The works
              must be undertaken in accordance with an Operational Works approval and must
              include in particular:
              a.    collection of runoff from the buildings and hardstand areas
              b.    collection of runoff from the carparking areas and access aisles
              c.    certification from an RPEQ that states the development of the site will not
                    create a worsening for downstream properties in regard to stormwater
                    quality or quantity.
              Earthworks and Retaining Walls
        20.   All fill and associated batters must be contained entirely within the subject site
              unless written permission from the respective landowner(s) is provided to
              Council.




                                                                                   Page 5 of 11

Section 6

RECOMMENDATIONS ONLY – NOT THE FINAL DECISION OF COUNCIL
GENERAL COMMITTEE MEETING                                                   12 DECEMBER 2016


              Damage to Services and Assets
        21.   Any damage caused to existing services and assets as a result of the
              development works must be repaired at no cost to the asset owner at the
              following times:
              a.    where the damage would cause a hazard to pedestrian or vehicle safety,
                    immediately; or
              b.    where otherwise, upon completion of the works associated with the
                    development.
              Any repair work which proposes to alter the alignment or level of existing services
              and assets must first be referred to the relevant service authority for approval.
              Noise
        22.   Mechanical plant and equipment, a/c units, motors, refrigeration equipment,
              compressors, pumps etc on site should be situated within the building or suitably
              provided with noise reduction measures and located as to prevent a noise
              nuisance beyond the boundary of the site and not exceed the levels specified in
              Table 1.
              TABLE 1
                      NOISE LIMITS AT A SENSITIVE RECEPTOR
                               Noise level at noise sensitive place measured as the adjusted
               PERIOD
                               maximum sound pressure level (L10, adj,T)
               7am – 6pm           Background noise level (L90,T) plus 5 Db(A)
               6pm – 10pm          Background noise level plus 5 Db(A)
               10pm – 7am      Background noise level plus 3 Db(A)
                      NOISE LIMITS AT A COMMERCIAL PLACE
                               Noise level at a commercial place measured as the adjusted
               PERIOD
                               maximum sound pressure level (L10, adj,T)
               7am – 6pm           Background noise level (L90,T) plus 10 Db(A)
               6pm – 10pm          Background noise level plus10 Db(A)
               10pm – 7am          Background noise level plus 8 Db(A)

        23.   When requested by Council, a Noise Impact Assessment Report (NIAR) showing
              monitoring and recording of noise levels must be undertaken to investigate any
              complaint (other than a frivolous or vexatious complaint) caused by noise
              emissions from operations at the premises. Such monitoring must be undertaken
              within a reasonable and practicable timeframe nominated by Council and be
              performed by a suitably qualified person in accordance with accepted guidelines
              and standards. The report must be submitted to Council detailing the results of
              such monitoring and recommendations for any measures to achieve compliance
              with limits outlined in Table 1 of this Decision Notice.
              For the purpose of measuring and certifying relevant noise conditions and
              reporting (e.g. mechanical plant and equipment, a/c units, motors, refrigeration
              equipment, compressors, pumps, rooftop plant and equipment. Etc) a suitably
              qualified person is either:



                                                                                   Page 6 of 11

Section 7

RECOMMENDATIONS ONLY – NOT THE FINAL DECISION OF COUNCIL
GENERAL COMMITTEE MEETING                                                    12 DECEMBER 2016


               i)    a Registered Professional Engineer of Queensland, or
               ii)   an environmental consultant with a minimum of three (3) years current
                     experience in the field of acoustics.
               Public Health Act 2005 – Rainwater Tanks
         24.   In accordance with the Public Health Act 2005, rainwater tanks must be
               constructed with mosquito proof screens (made from either brass, copper,
               aluminium or stainless steel), and constructed with a mesh size of no more than
               1mm, and must be installed in a way that does not accelerate corrosion. Tanks
               that contain flap valves must be installed so that when closed, mosquitoes cannot
               pass through the valve. It is unlawful under the Public Health Act 2005 to
               construct, install or be in possession of a tank that does not comply with these
               requirements.
         25.   Where it is intended to use rainwater for drinking purposes, a suitable treatment
               system is required to be installed to disinfect or treat the water to microbiological
               and physical standards as described in the current Australian Drinking Water
               Guidelines 2011 to make it fit for drinking purposes.
               Refuse
         26.   The developer must provide waste storage and disposal facilities in accordance
               with Planning Scheme Policy No. 9 “Waste Management Multi-Dwellings and
               Commercial and Industrial Premises”, including an external imperviously paved
               area correctly sized for all refuse and recycling containers and suitably screened
               from public places and neighbouring properties.
    B.   Find the following are sufficient grounds to justify the decision despite the conflict with
         the Planning Scheme:
         1.    ‘Our Backyard’ offers rural type uses which are compatible with and maintains
               the rural residential character of the area.
         2.    The proposal partially fills a gap in support services for people living with
               disabilities and their families while not adversely impacting on surrounding rural
               residential properties.
         3.    The proposal will generally add positively to Noosa’s social fabric providing a
               benefit to the community and is consistent with the intent of Noosa Social
               Strategy.
    C.   Include the Department of Transport and Main Roads conditions as detailed in their
         Concurrence Agency response dated 7 November 2016.

                                                                                           Carried.




                                                                                      Page 7 of 11

Section 8

RECOMMENDATIONS ONLY – NOT THE FINAL DECISION OF COUNCIL
GENERAL COMMITTEE MEETING                                                    12 DECEMBER 2016


5   DRAFT DEVELOPMENT ASSESSMENT RULES FOR NEW PLANNING ACT
    Committee Recommendation
    Moved:           Cr Wellington
    Seconded:        Cr Glasgow
    That Council note the report by the Manager, Planning & Environment to the General
    Committee Meeting dated 12 December 2016 and request the Chief Executive Officer make
    a submission to the State government on the draft Development Assessment Rules for the
    Planning Act 2016 seeking that:
    1.   The assessment time frames of the Sustainable Planning Act 2009 be maintained. The
         time frames are proposed to be generally halved under the proposed Development
         Assessment Rules and have the potential to significantly impact on Council resources
         and achieving good planning outcomes for Noosa. The proposed shortened time
         frames will not allow time to undertake a thorough assessment of development
         proposals and consult appropriately with the community without additional resources
         to Council’s Development Assessment team. Additional resources would need to be
         funded by raising fees and charges for development applications, increasing costs for
         developers.
    2.   The Development Assessment Rules maintain and extend the time frame for applicants
         to be able to revive a development application where it lapses. This ability is not
         consistent with the identified intention for the development process to be ‘an applicant
         driven process’, and is likely to create administrative problems for councils and lead to
         significant confusion for the community, particularly submitters.
    3.   The opt-out step for information requests be deleted from the Development
         Assessment Rules. The ability to opt-out of an information request in the Development
         Assessment Rules is likely to add significant complexity to the development
         assessment process without adding value as an applicant currently has multiple
         options in regard to giving a response to a request for further information. It is critical
         that councils and state agencies retain the ability to raise issues and identify further
         information that is required in order to fully understand and assess development
         proposals.
    4.   Applicants be responsible for notifying all relevant entities of a change to the
         development application given the identified intention for the development process to
         be ‘an applicant driven process. S25.1 of the proposed Development Assessment
         Rules requires Councils to give a copy of a notice of change to a development
         application to the relevant referral agencies and advise on the effect of the change on
         the development process.’
    5.   Applicants be required to give notice of commencement of the public notification period
         to assessment managers, given Council is responsible for ensuring that application
         material is available for the community to review and determine whether submissions
         are properly made S17.4 of the proposed Development Assessment Rules states that
         ‘the applicant may give notice to the assessment manager of the intended start date of
         public notification’ and does not make this step mandatory.
                                                                                          Carried.




                                                                                      Page 8 of 11

Section 9

RECOMMENDATIONS ONLY – NOT THE FINAL DECISION OF COUNCIL
GENERAL COMMITTEE MEETING                                                   12 DECEMBER 2016


6   ENDORSEMENT OF BIODIVERSITY ASSESSMENT REPORT
    Committee Recommendation
    Moved:           Cr Wellington
    Seconded:        Cr Glasgow
    That Council note the report by the Principal Strategic Planner to the General Committee
    Meeting dated 12 December 2016, and:
    A.   Endorse the Biodiversity Assessment Report provided at Attachment 1 for the purpose
         of informing the development of an Environment Strategy and supporting Biodiversity
         Conservation Plan other than for the following issues:; and
         1.     Note that this is not the only substantial area of coastal mainland remnant
                vegetation between Byron Bay (300 km south in northern NSW) and Bundaberg
                (250 km to the north) as referred to on page 17, item 2.1, paragraph 2; and
         2.     Note that Noosa Council considers the koala as a threatened mammal for West
                Cooroy State Forest for the purposes of the table on page 128.
    B.   Request staff to prepare a discussion paper for the purposes of community consultation
         for the development of an Environment Strategy and Biodiversity Conservation Plan.
                                                                                          Carried.


7   AWARD OF TENDER 1516T043 WASTE MANAGEMENT CONTRACT 2017 - 2024
    Committee Recommendation
    Moved:           Cr Jurisevic
    Seconded:        Cr Stockwell
    That Council note the report by the Manager Waste and Environmental Health to the General
    Committee Meeting dated 12 December 2016 regarding the new 7 year waste management
    contract 2017 - 2024, and:
    A    Award the Contract to Cleanaway Pty Ltd for performance of a Waste Management
         Contract 2017 – 2024 as detailed in tender documents under Separable Portions A, B,
         and C, for an initial period of 7 years (at an estimated contract value of $46 million)
         commencing on Monday 4 Friday 1 September 2017, and including the ability to award
         a first extension of contract for a period of two years and a further second extension of
         one year;
    B    The awarding of the Contract being subject to Cleanaway Pty Ltd paying the specified
         Contract Performance Bonds for each Separable Portion A, B and C as detailed in the
         tender documents;
    C    Accept the option provided in the tender documents for the introduction of a 3 bin waste
         collection service to single unit domestic dwellings in the urban areas to include a third
         bin for garden waste from September 2017 as detailed in the tender documents, Part
         E Annexure 1, Schedule 1 “10 Maps detailing the external boundaries of Township
         Areas”
    D    Agree to the continued provision of an optional garden waste collection service to
         commercial and multi-unit domestic premises and other premises within 5 kilometres
         of the identified urban garden waste service area;


                                                                                     Page 9 of 11

Section 10

RECOMMENDATIONS ONLY – NOT THE FINAL DECISION OF COUNCIL
GENERAL COMMITTEE MEETING                                                 12 DECEMBER 2016


    E    Request that staff develop a Policy for the provision of the garden waste service and
         report to a future meeting of Council;
    F    Engage King and Company to finalise the relevant contractual documents including
         amendments resulting from contract negotiations and agreed contract departures, for
         signing by the successful tenderer.
                                                                                        Carried.


8   LEASING OF THE DEMOUNTABLE BUILDING AT BICENTENNIAL COMMUNITY
    CENTRE
    Committee Recommendation
    Moved:           Cr Jurisevic
    Seconded:        Cr Glasgow
    That Council note the report by the Community Facilities Manager to the General Committee
    meeting dated 12 December 2016 and:
    A.   Approve the leasing of the Bicentennial Community Centre (BCC) demountable
         building to Montessori Noosa (Education for Generations Ltd) on a 5 X 5 lease,
         commencing January 2017; and
    B.   Provide approval to lease the BCC annexe, also to Montessori Noosa, when the
         school’s enrolment levels reach sufficiently high numbers, likely within the next two to
         three years.
                                                                                        Carried.


9   NOOSA BIOSPHERE RESERVE BOARD ANNUAL REPORT
    Committee Recommendation
    Moved:           Cr Glasgow
    Seconded:        Cr Jurisevic
    That Council note the report by the Chief Executive Officer to the General Committee Meeting
    dated 12 December 2016 and note the annual report for the financial year 2015/16 to Council
    by the Noosa Biosphere Reserve Foundation which also incorporates their September 2016
    quarterly report.
                                                                                        Carried.




                                                                                  Page 10 of 11

Section 11

RECOMMENDATIONS ONLY – NOT THE FINAL DECISION OF COUNCIL
GENERAL COMMITTEE MEETING                                                             12 DECEMBER 2016


10   OYSTER RESTORATION PROJECT - ACCEPTANCE OF DRAFT RESOURCE
     ALLOCATION AUTHORITY CONDITIONS
     Cr Jackson declared a perceived conflict of interest in this matter (as defined in section 173 of the Local
     Government Act 2009) due to her membership of the Noosa Parks Association which is one of the project
     partners. Cr Jackson believed she could consider this item impartially and in the public interest and
     therefore remained in the meeting room for the debate and decision on this matter.
     Committee Recommendation
     Moved:              Cr Pardon
     Seconded:           Cr Jackson
     That Council note the report by the Environment Officer to the General Committee Meeting
     dated 12 December 2016, and:
     A.    Accept the Draft Resource Allocation Authority conditions proposed by the Department
           of Agriculture Forestry and Fisheries on behalf of the project partners;
     B.    Authorise the development application for the project to be submitted as soon as
           possible to facilitate deployment of the oyster reef restoration units in the March to May
           oyster spat recruitment season;
     C.    Authorise the Chief Executive Officer to negotiate and enter into a formal agreement
           with relevant project partners, which will result in nil additional cost to Council (following
           payment of development application fees) associated with the project, following receipt
           of the development approval.
                                                                                                      Carried.
     Cr Jackson voted in favour of the motion.



11   FINANCIAL PERFORMANCE REPORT - NOVEMBER 2016
     Committee Recommendation
     Moved:              Cr Jurisevic
     Seconded:           Cr Jackson
     That Council note the report by the Manager Financial Services to the General Committee
     Meeting dated 12 December 2016 providing the November YTD monthly financial
     performance report for the 2016/17 financial year.
                                                                                     Carried.




                                                                                               Page 11 of 11

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.