3. The development will adversely impact on the local villages and towns by reducing
patronage to these centres and therefore will not improve community wellbeing.
4. The proposal is contrary to the SEQ Regional Plan’s Regional Policy 11.5.1 to identify
and protect existing and potential drinking water catchments from inappropriate land
use as the development would pose an unacceptable risk to water quality.
5. The proposal is contrary to the Environmental Protection (Water) Policy for Mary River
Environmental Values and Water Quality Objectives as the proposed surface water
quality exceeds these objectives in relation to Total Nitrogen and Total Phosphorous
and the applicant has not addressed the impact the in-ground storage of fuel will have
on ground water.
6. The proposal fails to meet the Plan of Development for the site, including the provision
of a 10 metre landscape buffer to visually screen the development from the Bruce
Highway.
7. The proposed illumination of the advertising devices is contrary to the Advertising
Devices Code and the intent of the Plan of Development for the site.
Carried.
4 MCU16/0090 - DEVELOPMENT APPLICATION FOR MATERIAL CHANGE OF USE FOR
WELLBEING TYPE 2 - SOCIAL (SUNSHINE BUTTERFLIES) AT 468 MCKINNON DRIVE,
COOROIBAH
Committee Recommendation
Moved: Cr Wellington
Seconded: Cr Pardon
That Council note the report by the Development Planner to the General Committee Meeting
dated 12 December 2016 regarding Application No. MCU16/0090 for a Development Permit
for Material Change of Use of Premises - Wellbeing Type 2 - Social (respite centre) situated
at 468 McKinnon Drive, Cooroibah and:
A. Approve the application in accordance with the following conditions:
PLANNING
Approved Plans
1. Development undertaken in accordance with this approval must generally comply
with the approved plans of development. The approved plans are listed in the
following table unless otherwise amended by these conditions.
Plan No. Rev. Plan/Document Name Date
L002 A Landscape Concept Plan, prepared by Sunshine 20.9.2015
Gardens
Nature and Extent of Approved Use
2. The approved use is Wellbeing Type 2 – Social being for a respite centre for
people living with disabilities and their families and associated ancillary office and
agricultural uses. The approval does not include a cafe.
3. The maximum number of special events per year is six (6).
Page 3 of 11
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalSearchable page text hides email addresses. Original files are unchanged and may show email addresses.