Skip to the record
Mmm.. taste the original NoosaWatch™

Council archive · source document

Development Application - Part 2 of 2 - Planning report, Plans & Referral Agency Response · OPW11/0144

of 17

Check the original when the exact wording matters.

Plans and drawings: the text below has words only, no drawings.

Log in to see the plans as drawn
6.   The owner is to ensure that the ship berthed at this structure must maintain sufficient under keel
      clearance at all stages of tide. The ship must comply with any local restrictions placed on channel
      depths and draft restrictions.


7.   Any ships and equipment you or your agent use must comply with the Transport Operations
     (Marine Safety) Act 1994, the Transport Operations (Marine Safety) Regulation 2004 and the
       Transport Operations (Marine Pollution) Act 1995.


8.   Any ships using this structure must comply with the Transport Operations (Marine Safety) Act
     1994 and the Transport Operations (Marine Safety) Regulation 2004.


9.   Any ship moored at this pontoon must not impede the safe navigation of other ships or restrict
       safe access to or from neighbouring structures.


10. Any ship, dry berth or device (including Air Lifting Pontoons) berthed, moored or attached to the
    pontoon must not exceed the following sizes:


           Wet Berth                                                      Dry Berth
       Length Overall - 8      metres                                       N/A
       Beam -           3.5    metres


11. The contractor must construct the pontoon within two years from the date of approval. If
     construction is not completed, you will need additional or amended comments from the Regional
       Harbour Master.

Maritime Safety Queensland does not need to be further consulted if all of the above conditions are
met.

The above conditions must be included in your application to the assessment manager.


This agency will also forward a copy of this letter to the Assessment Manager.



Yours sincerely




Captain Richard C Johnson
Regional Harbour Master (Brisbane)




                                                                                                 Page 2 of 2

Used in these records

About this file

File size
3.2 MB (large file)
File type
PDF

No other editions are linked here.

Original file

Log in to download the original file

Development Application - Part 2 of 2 - Planning report, Plans & Referral Agency Response.pdf · 3.2 MB (large file)

The download may take up to a minute.

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.