Project No. PG-10899                                                                                                        Page | 4
November 2023
Ref: PG-10899, 2023-10-16, ASSMP VER 2
DD Sunnyside CD Sunnyside Pty Ltd – Acid Sulfate Soil Management Plan – Proposed Residence, 30 Mossman Court, Noosa Heads




                                     in relation to site management practices on a regular basis and
                                     improvement strategies should be developed as required.
Responsibility                       The satisfactory implementation of the ASSMP will be the
                                     responsibility of the Earthworks Contractor. The ASS Consultant will
                                     ensure that:
                                     • the contractor is made aware of site specific conditions and
                                         implications for the management of ASS within the site; and
                                     •     correct methods for the collection of samples and testing are
                                           employed and the reporting of results to the relevant site
                                           authorities.
                                     The Earthworks Contractor’s responsibilities will include:

                                     •     awareness of site conditions and requirements for the
                                           implementation of the ASSMP;
                                     •     modifying earthworks/construction procedures to comply with
                                           the ASSMP and erosion control plan;
                                     •     propose any corrective action measures to be approved by
                                           the ASS Consultant; and
                                     •     implementing approved correction actions.
Reporting                            The ASS Consultant shall report to the Project Manager on a regular
                                     basis on the performance of the site management plan.

                                     The Contractor’s Representative shall report to the Project
                                     Manager and to the ASS Consultant on:

                                     •     the effectiveness of the operating strategies;
                                     •     problems in implementing the ASSMP management strategies;
                                     •     compliance with testing requirements run-off control and
                                           materials handling; and
                                     •     effectiveness of any corrective action adopted.

Used in these records

About this file

File size
2.0 MB (small file)
File type
PDF

No other editions are linked here.

Original file

Log in to download the original file

Pacific Geotech report Nov 2023 v3.pdf · 2.0 MB (small file)

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.