Chris Page From: Daniel Kenna <[email protected]> Sent: 15 September 2022 10:24 AM To: Chris Page Cc: [email protected] Subject: FW: Request for in principle/no objection - 7 Ruby Street, Cooroy - 215101 Attachments: Unitywater GIS Map of 7 Ruby St Cooroy - Area to be CCTV Surveyed.pdf H iChris and Robyn, Please see attached/below forUnityw aterin principle approvalforthe build over. Regards, D anielKenna Beng CPEng M IEAust RPEQ N ER EC 0404157187 [email protected] From: Tony Stokman <[email protected]> Sent: Wednesday, 14 September 2022 10:06 AM To: Daniel Kenna <[email protected]> Cc: Mark Kettley <[email protected]> Subject: RE: Request for in principle/no objection ‐ 7 Ruby Street, Cooroy ‐ 215101 Hi Daniel, Thank you for your enquiry. In response to your request below, Unitywater provides in principle agreement/no objection in response to the MCU/development plans in relation to the proposed Multi‐residential development of 4 Units within the site and subject to the submission and subsequent assessment of a Build Over or Near Water Supply or Sewerage asset application with the following items to be considered in relation to building over the existing sewerage asset within the site: A CCTV survey of the 150mm Asbestos Cement sewerage main asset traversing the site will be required prior to the commencement of construction to determine the suitability of the condition of the asset as well as a subsequent post construction CCTV survey to determine any affect on the asset during the construction process. Should the applicant choose to have the pre‐construction CCTV survey completed to enable the video footage and written report to be submitted as a part of the Build Over or Near Water Supply or Sewerage asset application process, the following process must be adopted: The results of a Closed‐Circuit Television (CCTV) Survey of the sewer main as shown in the enclosed GIS Map. NOTE: o To submit the relevant CCTV video file/s and report documentation to Unitywater, send an email request to [email protected] to arrange an Objective Connect link to be provided to you for upload of the CCTV footage and CCTV written report to enable further processing of this application. o The survey must be undertaken to determine the condition and location of Unitywater’s asset. It is important to note that it will be a concurrence agency condition within the Referral Response that a further survey is required after construction of the footings so as to determine whether the construction has damaged or altered the condition of the asset. o The survey is to be carried out by a private contractor and the results (Video and Technical Report) are to be submitted to Unitywater for assessment. 1
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalFull text of the other 1 page
Page 2
o The survey must be performed using a tracked vehicle with a rotating camera head and the lens is to be
free of water and obstructive material. The asset numbers shown in the enclosed GIS Map must be
referenced within the Video and Technical Report. An example of a Technical Report that would be
accepted by Unitywater is enclosed for your reference.
o The Technical Report may be in hard copy and/or electronic format and must identify the location of
reportable features; such as the property connection and any defects, together with detail to clearly
establish the extent of the survey; such as the length of main, chainages of defects, etc.
The applicant will need to provide engineering detail demonstrating that no load from any proposed
structure over Unitywater’s asset will be transmitted to the existing infrastructure and that any
footing/foundation within the zone of influence of the infrastructure is founded below that zone
The attached GIS map indicates an existing sewerage property connection is located on the eastern
boundary of the site. If it is the intent of the applicant to re‐use this connection, it must be accurately
located and the applicant must demonstrate a minimum of 1.0m clearance from all part of this connection.
If it is the intent that the existing connection is to be abandoned with a new connection to be provided, the
applicant will need to demonstrate that the proposed new connection is compliant with the above clearance
requirements and also provide detail on the treatment of the existing sewerage property (i.e. cut back to
property boundary)
Regards,
Tony Stokman | Development Officer
Unitywater
Development Services, South | Sustainable Infrastructure Solutions
Ground Floor ‐ King Street Caboolture 4510
m: 0488 981 217
e: [email protected]
Unitywater acknowledges the Traditional Owners and Custodians of the land and waters of our service region; the Jinibara, Kabi
Kabi and Turrbal peoples. We pay our respects to Elders past, present and emerging.
2
Used in these records
RFI - Appendix E- Unity Water Letter.pdfRelated documentApplication case desk ↗
About this file
- File size
- 242 KB (small file)
- File type
No other editions are linked here.