Skip to the record
For the highest quality transcripts.

Original source · versioned page text

2016008949 DECISION NOTICE - Signed

Attached to the e-mail Operational Works Application OPW16/0338.

of 16
              (2) Despite subsection (1), if the reviewer is satisfied the outcome of the review would not
              be affected if the work is started before the review is decided, the reviewer may allow the
              work to start before the review is decided.

              Division 3 Appeals to a building and development committee

              99BRBE Appeals about applications for connections—general
              (1) This section applies to an applicant for a connection if—
              (a) for the application for a connection, the land to which the connection relates is subject
              to a development application mentioned in the Planning Act, section 519 or 522; and
              (b) the applicant applied for internal review of an approval decision or failure to decide;
              and
              (c) the review decision is not the decision sought by the applicant.

              (2) The applicant may appeal to a building and development committee against any of the
              following—
              (a) a refusal, or an approval in part, of an application;
              (b) a water approval condition;
              (c) another matter stated in the approval.

              (3) The appeal must be started within the standard appeal period.

              99BRBF Appeals about applications for connections—particular charges
              (1) This section applies to an applicant for a connection if—
              (a) the applicant applied for internal review of a charge decision or a decision to give an
              infrastructure charges notice; and
              (b) the review decision is not the decision sought by the applicant.

              (2) The applicant may appeal to a building and development committee about the review
              decision.

              (3) The appeal may be made only on 1 or more of the following grounds—
              (a) the decision involved an error relating to the application of the relevant charge;
              (b) if the decision is the giving of an infrastructure charges notice—
              (i) the decision involved an error relating to—
              (A) the working out, for section 99BRCJ, of additional demand; or
              (B) an offset or refund; or
              (ii) there was no decision about an offset or refund; or
              (iii) if the infrastructure charges notice states a refund will be given—the timing for giving
              the refund.

              (4) To remove any doubt, it is declared that the appeal must not be about—
              (a) the relevant charge itself; or
              (b) for a decision about an offset or refund for an infrastructure charges notice—
              (i) the establishment cost of infrastructure identified in the distributor-retailer’s water
              netserv plan; or
              (ii) the cost of infrastructure decided using the method included in the distributor-retailer’s
              infrastructure charges schedule.

              (5) The appeal must be started within the standard appeal period.

              99BRBFA Appeals against refusal of conversion application
              (1) This section applies to an applicant for a conversion application if—
              (a) the applicant applied for internal review of the conversion decision; and
              (b) the review decision is not the decision sought by the applicant.

                                                                                                                                          Page 12 of 16
Unitywater is a statutory authority that provides water and sewerage services for the                           Unitywater has certification to
                                                                                                                OH&S ISO 4801:2001 Reg No 4260
Moreton Bay, Sunshine Coast and Noosa Council areas.                                                            Environmental ISO 14001:2004 Reg No 4259
                                                                                                                Quality Systems ISO 9001:2008 Reg No 4258

                                                     Revision No: 2                Effective Date: 19/02/2015            Next Review Date:19/02/2018

Log in to download the original (2016008949 DECISION NOTICE - Signed.pdf)

Searchable page text hides email addresses. Original files are unchanged and may show email addresses.

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.