Original source · versioned page text
2016008949 DECISION NOTICE - Signed
Attached to the e-mail Operational Works Application OPW16/0338.
CAA
Other approval requirements and compliance with all laws
9
This approval only authorises the connection to Unitywater’s infrastructure. This approval
does not remove the need for other approvals in order to carry out the necessary work for the
development.
For example, the Applicant should consider the need to comply with relevant standards and
obtain approvals for impacts arising from sediment and erosion control, flora and fauna and
traffic/roads, including traffic management etc.
The Applicant is responsible for obtaining all necessary approvals for its development and
complying with all laws including all environmental laws.
CAA
Third party property
10
If any infrastructure authorised by this approval is to be constructed on property that is not
owned or controlled by the Applicant, it is the Applicant’s or developer’s responsibility to gain
the necessary consents to install that infrastructure.
CAA
Connection to Unitywater network/s
11
Connections to the existing Unitywater water supply and/or sewerage network/s will only be
carried out by Unitywater or as agreed with Unitywater’s Private Works section and by
application. Connections will only be completed after the new infrastructure has been
accepted ‘On-Maintenance’.
Works on or in close proximity to existing Unitywater infrastructure require consultation with
Unitywater Private Works prior to commencement of construction. Private Works shall be
contacted (allow a minimum of five working days for processing) prior to commencing work.
The requirement for a Network Intervention application will require additional processing time.
CAA
Water service/s installation
12
If this application is subject to the payment of Infrastructure Charges, Unitywater will install
the water service/s within 20 business days after the payment of the Infrastructure Charges.
CAA
Errors and Omissions
13
This approval shall not be taken to mean that the drawings have been checked in detail,
Unitywater accepts no responsibility whatsoever for the survey information, the design, or for
the accuracy of any information or detail contained in the drawings and specifications.
Where errors or omissions occur in the design drawings or specifications, or where works do
not conform to or meet Unitywater standards, the Applicant’s Consultant shall rectify such to
comply with those standards at no cost to Unitywater.
Where drawings contain insufficient detail or do not contain details of works that are either
necessary or associated with the development then these works shall be designed and
constructed to Unitywater standards, as required by Unitywater.
Unitywater reserves the right to amend the approved drawings or request further information
should this become necessary. Only the Unitywater approved drawings shall be used for
construction.
CAA
Existing water meter/s
14
The Applicant is advised that if the existing water meter currently serving the property will no
longer be required, an application (Standard Connection Request) must be made to
Unitywater to disconnect the meter.
A fee is applicable for the disconnection of services.
Page 7 of 16
Unitywater is a statutory authority that provides water and sewerage services for the Unitywater has certification to
OH&S ISO 4801:2001 Reg No 4260
Moreton Bay, Sunshine Coast and Noosa Council areas. Environmental ISO 14001:2004 Reg No 4259
Quality Systems ISO 9001:2008 Reg No 4258
Revision No: 2 Effective Date: 19/02/2015 Next Review Date:19/02/2018
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalLog in to download the original (2016008949 DECISION NOTICE - Signed.pdf)
Searchable page text hides email addresses. Original files are unchanged and may show email addresses.