Town Planning Report - Material Change of Use Outdoor Sport and Recreation - Temporary relocation ~ Lake Macdonald Dr Lake Mac
Town Planning Report
Material Change of Use – Outdoor Sport and Recreation (Temporary Use)
8.2.6 Flood Hazard Overlay Code
Table 8.2.6.3 - Criteria for assessable development
Performance outcomes Acceptable outcomes Comments
Floodplain protection, immunity and safety - for development areas
PO1 AO1
Performance Response
Development provides that for all flood events up to and including the DFE :
The finished flood level is not less than the minimum design levels specified in Table 8.2.6.4
(a) the safety of people on the site is protected; and The proposed development ensures that for all flood events up to and including the
the risk of damage to property on the site is avoided or minimised as far as practicable. Defined Flood Event (DFE), the safety of people and property on the site is protected.
• The development comprises a temporary, non-habitable 40-foot shipping container,
with no regular occupation and no reliance on the site during flood events, thereby
protecting the safety of people.
• Seqwater’s active management of dam levels, including a significantly reduced Full
Supply Level (FSL) for the duration of the dam improvement works, substantially
lowers flood exposure.
• The container will be securely anchored to prevent movement in the unlikely event
of a major flood and will be watertight, with no chemicals or hazardous materials
stored, minimising the risk of property damage or environmental harm.
Given the temporary nature of the development, the limited footprint, and the proposed
mitigation measures, residual flood risk is negligible. The proposal therefore avoids or
minimises flood impacts as far as practicable and achieves the intent of PO1.
It is acknowledged that, notwithstanding the temporary nature of the development,
building approval and certification will be obtained for the placement and anchoring of
the structure.
PO2 AO2 Not Applicable
All lots have sufficient area that is above the DFE flood level or where modelling is not The minimum area above flood level (flood free area) for each lot, is in accordance with
available, the highest recorded flood level, to safely and adequately accommodate the Table 8.2.6.5. The proposed development does not involve a Reconfiguring a Lot and does not create
intended use. any new lots.
PO3 AO3 Not Applicable
For reconfiguring a lot or operational works, development is undertaken in a manner that Development areas are not filled to reduce flood risk.
ensures: No filling is proposed as part of the development. The structure will be placed at
(a) natural hydrological systems are protected from erosion, scour or flood damage on existing ground levels within an already cleared and disturbed area.
the premises or other premises;
(b) natural landforms and drainage lines are maintained to protect the hydraulic
performance of waterways and flood plain; and
(c) development integrates with the natural landform rather than modifying the
landform to suit the development as far as practicable.
PO4 AO4.1
Performance Response
Development provides an effective evacuation route that remains passable, with sufficient
For reconfiguring a lot, development does not compromise the safety of people resulting
flood warning time, to enable people to progressively evacuate to safe areas above the PMF The proposed development ensures that people are not exposed to flood risk during
from the flood risk associated with events exceeding the DFE. in the face of advancing flood or waters for events that exceed the DFE. events exceeding the DFE, having regard to its operational characteristics and
OR management controls.
AO4.2
Development provides for an area of sufficient size and dimensions on site above the PMF Rowing and associated activities will not occur during flood events, and this restriction
that allows for safe congregation and refuge. will be clearly incorporated into the Operation Management Plan. The development
Version No: Version Date: Document title Seqwater Document Number Page:
02 11/06/2026 Town Planning Report – Material Change of Use – Temporary Use D 56 of 59
This document is the property of Seqwater. It must not be copied or reproduced in any way whatsoever without the authority of Seqwater. This document is uncontrolled when printed. An electronic database manages and stores the controlled version.
See the original