Original source · versioned page text
Bulk_20231019152518
Attached to the e-mail MCU22_0119 - 1 Pitta Street Peregian Beach - Notice of Suspension of Appeal Period.
Noosa Council documents
17. All landscape works must be established and maintained in accordance with the
approved design for the life of the development, and in a manner that ensures healthy,
sustained and vigorous plant growth. All plant material must be allowed to grow to full
form and be refurbished when its life expectancy is reached.
18. All planting areas on the eaves must be planted and maintained at all times, with
replacement planting undertaken promptly where plants fail or do not have a healthy
and vigorous growth.
Coastal Protection
19. External colours and finishes must be of muted/environmental tones that blend with the
natural environment and low-reflective roofing and cladding materials.
20. Any fencing to the eastern boundary must not exceed 1.2 metres in height, be of open
construction, constructed of light weight materials (eg. timber) and be dark in colour to
blend with the natural landscape.
Site Access and Driveways
21. A sealed access driveway must be provided from Pitta Street to all parking and
manoeuvring areas of the development. The works must be undertaken generally in
accordance with Council’s Standard Drawings RS-049 and RS-050 and any associated
addendum.
Stormwater Drainage
22. The site must be provided with a stormwater drainage system connecting to a lawful
point of discharge. Stormwater runoff from the development must be disposed of on-
site without causing scour or damage to the subject site or any adjoining property and/or
discharged to the existing kerb and channel in Pitta Street.
Earthworks and Retaining Walls
23. All earthworks must be carried out in accordance with a site specific Geotechnical
Investigation/Report prepared by a qualified person* and endorsed through a Building
approval.
24. The site specific Geotechnical Investigation/Report must consider the potential for the
works to encounter acid sulfate soils and must include, but not be limited to:
d. Soil investigation and testing
e. Where Acid Sulfate Soils are likely to be encountered, inlcude an Acid Sulfate
Soils Management Plan that considers the treatment of the soils and where
relevant, export of the soils from the site
*(Refer to Advisory Note)
25. All earthworks and associated retaining structures/batters, both above and below ground
level, both temporary and permanent, must be contained entirely within the subject site
unless written permission from the respective landowner(s) is provided to Council.
26. All earthworks must be undertaken in accordance with the provisions of Australian
Standard AS3798: Guidelines on Earthworks for Commercial and Residential
Developments.
27. All retaining walls must be designed and constructed in accordance with the planning
scheme and must be certified by an RPEQ where exceeding 1.0m in height. All retaining
walls that are publicly accessible and exceed 1.0m in height must be fitted with a
commercial grade safety fence.
Page 5 of 9
Document Set ID: 22621442
Version: 4, Version Date: 19/10/2023 Print Date: 19 October 2023, 3:25 PM
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalSearchable page text hides email addresses. Original files are unchanged and may show email addresses.