Decision Notice - OPW22 0251 [As Published]

of 38

Page text shows just the words. Original shows the document exactly as it was published.

Page text read automatically using OCR, there may be inaccuracies

                        Plan No.             Rev.      Plan/Document Name                          Date

                        21.024 - S010        P2        Site and General Arrangement Plan           May 2022

                        21.024 - S020        P3        General Arrangement Plan and Details        Jan 2023

                        21.024 - S030        P2        Sections and Details                        May 2022

                      Currency Period
               2.     The Currency Period for this development approval lapses if the development has not
                      substantially started by 21 August 2025, unless an application to extend the currency period
                      is approved by Council.
                      Performance Bond
               3.     Security in the form of a cash bond or trading bank guarantee to the sum of $2500 must be
                      submitted to Council, to secure performance of all conditions of this approval, prior to the
                      commencement of the works. The cash bond or trading bank guarantee will be returned on
                      performance of the conditions of this approval less any costs incurred by Council in respect
                      of enforcing performance of this permit. Council reserves the right to call upon the bond or
                      guaranteed sum to effect compliance with conditions.
                      General Conditions
               4.     All necessary approvals from external service providers (eg Unitywater) and external parties
                      on which the development works are proposed have been obtained and a copy supplied to
                      Council.
               5.     Council must be contacted at least 5 working days prior to any works commencing to
                      organise a prestart. The contact number to arrange a pre-start meeting is 5329 6500. The
                      pre-start meeting must include the relevant parties for the following aspects of the works:
                      a.      Civil engineering works;
                      b.      Erosion and sediment control works;
                      c.      Other relevant parties
               6.     Certificates demonstrating currency of public liability insurance and works insurance covering
                      the works must be submitted to Council prior to the prestart meeting.
               7.     A Construction Management Plan must be submitted at least 5 working days prior to the pre-
                      start meeting and must include but not be limited to the following:
                      a.      that works must not be undertaken on school holidays, public holidays and Sundays
                              with limited works on Saturdays
                      b.      maintenance and protection of water quality and existing drainage lines through the
                              construction site through the implementation of appropriate erosion and sediment
                              control measures
                      c.      provision for safe pedestrian access across the frontage of the site both during daily
                              construction and after daily construction has ceased
                      d.      provision for construction traffic and access for equipment and deliveries
                      e.      provision for storage of equipment and materials
                      f.      appropriate traffic signage in accordance with the Manual of Uniform Traffic Control
                              Devices (MUTCD)
                      g.      adequate parking arrangements for construction workers
                      h.      restoration of Council assets and surfaces
               8.     All structures must have no detrimental effects on stormwater drains and/or easements.



                                                                                                       Page 2 of 38
Document Set ID: 22549959
Version: 4, Version Date: 23/08/2023
Log in to download the original file

Decision Notice - OPW22 0251 [As Published].pdf · 5.0 MB (large file)

The download may take up to a minute.

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.