Decision Notice - OPW22 0251 [As Published]
Plan No. Rev. Plan/Document Name Date
21.024 - S010 P2 Site and General Arrangement Plan May 2022
21.024 - S020 P3 General Arrangement Plan and Details Jan 2023
21.024 - S030 P2 Sections and Details May 2022
Currency Period
2. The Currency Period for this development approval lapses if the development has not
substantially started by 21 August 2025, unless an application to extend the currency period
is approved by Council.
Performance Bond
3. Security in the form of a cash bond or trading bank guarantee to the sum of $2500 must be
submitted to Council, to secure performance of all conditions of this approval, prior to the
commencement of the works. The cash bond or trading bank guarantee will be returned on
performance of the conditions of this approval less any costs incurred by Council in respect
of enforcing performance of this permit. Council reserves the right to call upon the bond or
guaranteed sum to effect compliance with conditions.
General Conditions
4. All necessary approvals from external service providers (eg Unitywater) and external parties
on which the development works are proposed have been obtained and a copy supplied to
Council.
5. Council must be contacted at least 5 working days prior to any works commencing to
organise a prestart. The contact number to arrange a pre-start meeting is 5329 6500. The
pre-start meeting must include the relevant parties for the following aspects of the works:
a. Civil engineering works;
b. Erosion and sediment control works;
c. Other relevant parties
6. Certificates demonstrating currency of public liability insurance and works insurance covering
the works must be submitted to Council prior to the prestart meeting.
7. A Construction Management Plan must be submitted at least 5 working days prior to the pre-
start meeting and must include but not be limited to the following:
a. that works must not be undertaken on school holidays, public holidays and Sundays
with limited works on Saturdays
b. maintenance and protection of water quality and existing drainage lines through the
construction site through the implementation of appropriate erosion and sediment
control measures
c. provision for safe pedestrian access across the frontage of the site both during daily
construction and after daily construction has ceased
d. provision for construction traffic and access for equipment and deliveries
e. provision for storage of equipment and materials
f. appropriate traffic signage in accordance with the Manual of Uniform Traffic Control
Devices (MUTCD)
g. adequate parking arrangements for construction workers
h. restoration of Council assets and surfaces
8. All structures must have no detrimental effects on stormwater drains and/or easements.
Page 2 of 38
Document Set ID: 22549959
Version: 4, Version Date: 23/08/2023
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalLog in to download the original file
The download may take up to a minute.