4.0 EXISTING DRAINAGE:
4.1 Existing Drainage and Infrastructure:
Data obtained from Noosa Councils Interactive Mapping System accompanied with a detailed site survey
prepared by Noosa Cooloola Land Surveys confirms the following drainage infrastructure.
− Kerb and channel to Sidoni and Blakesley Street
− An underground drainage network discharging to the Noosa river.
Refer Appendix A for the detailed site survey and Appendix B for Noosa Council’s Drainage
Infrastructure Map
4.2 Lawful Point of Discharge:
The lawful point of discharge is described in Section 3.9.1 of QUDM 2017. The ‘Lawful Point of
Discharge Test’ may be helpful in assessing whether a lawful point of discharge exists at a particular
location. As defined in QUDM 2017 the criteria for determining the lawful point of discharge are: -
1. Will the proposed development alter the site’s stormwater discharge characteristics in a
manner that may substantially damage a third-party property (see section 3.6).
• If not, then no further steps are required to obtain tenure for a lawful point of
discharge (assuming any previous circumstances and changes were lawful).
• If there is a reasonable risk of such damage, then consider issue (2) or (3).
2. Is the location of the discharge from the development site under the lawful control of
the local government or other statutory authority from whom permission to discharge
has been received? This will include a park, watercourse, drainage or road reserve,
stormwater registered drainage easement, or land held by local government (including
freehold land).
Note: The regulatory authority (in its capacity as land holder) is likely to require
information about the potential impact of the site’s stormwater discharge characteristics
on third party properties (particularly those downstream of the proposed discharge
point) before it will consent to the discharge entering its land.
• If so, then no further steps are required to obtain tenure for a lawful point of
discharge.
• If not, then consider issue (3). A landowner or regulator may require that the
developer obtain an authority to discharge as described in (3) in order for the
stormwater to ultimately flow to a location described in (2).
3. An authority to discharge over affected properties will be necessary. In descending order
of certainty, an authority may be in the form of:
• Dedication of a drainage reserve or park
• A registered easement for stormwater discharge/works
• Written discharge approval.
SCG Consulting engineers 6 SCG Ref: 33094(SWM).Rev A
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalLog in to download the original (Reference Documents - MCU23-0142.pdf)
Searchable page text hides email addresses. Original files are unchanged and may show email addresses.