Minor Change Report MCU21 0117 02 (As Published) · MCU21/0117.02
APPLICATION FOR A MINOR CHANGE TO A DEVELOPMENT APPROVAL
Author Senior Town planner, Andrew Gaffney
Development Assessment
APPLICATION DETAILS
Application No. MCU21/0117.02 & OPW21/0199.02
Development Approval MCU21/0117.01 & OPW21/0199.01
Applicant Cooroy Villas Ltd
Request Received On 26 August 2025
Report Reviewed By Andrew Gaffney – 10 April 2026
Decision Due Date 10 April 2026
PROPERTY DETAILS
Property Address 5 Pearl St Cooroy Qld 456354 Elm St Cooroy Qld 4563
RP Description Lot 2 RP 64750, Lot 2 RP 153798
Land Area 5 Pearl St - 759 m² 54 Elm St – 1,518m²
Existing Use of Land Vacant
STATUTORY DETAILS
SEQRP Designation Urban Footprint
Zone Medium Density Residential
Precinct Not applicable
Local Area Plan Cooroy Local Plan Area Code
Overlays Regional Infrastructure Overlay Code (Water Supply Pipeline)
Assessment Type Minor Change to Development Approval
1. PROPOSAL
The application seeks approval for a minor change to an existing Material Change of Use and
associated Operational Works approval.
Page 1 of 29
Document Set ID: 24138568
Version: 7, Version Date: 17/04/2026
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalFull text of the other 28 pages
Page 2
The proposed changes involve increasing the number of bedrooms within Units 11 and 12 from
two to three bedrooms, together with minor internal layout alterations and minor changes to
building façades. The requested changes include;
- conversion of Units 11 and 12 to 3 bedroom units which now results in 8 x two bedroom units
and 4 x two bedroom units;
- the extension of ground-level decks over the existing stormwater swale drain at the rear of the
site;
- updates to landscaping to reflect a 0.5-metre wide landscaped setback along the internal
driveway;
- amendments to car parking numbers to reflect the additional bedrooms; and
- updates to the approved stormwater and engineering plans to align with detailed operational
works drawings.
Changes to the following Conditions is required;
• Condition 2: Update approved plans list;
• Condition 29: Landscaping—include 0.5m setback along driveway;
• Condition 32: Update car parking numbers;
• Conditions 34 & 35: Stormwater drainage and quality treatment updates;
• Condition 48: Update approved engineering and landscaping plans;
• Condition 63: Update MCU reference to MCU21/0117.02;
• Condition 97: Align landscaping with MCU condition; and
• Delete Item 9 (Reference Documents): Remove Site-Based Stormwater Management Plan
The overall number of dwellings, building height, scale and development footprint remain
unchanged.
The locality and proposal plan are included below.
Page 2 of 29
Document Set ID: 24138568
Version: 7, Version Date: 17/04/2026
Page 3
a , il eT) TE = = | etal \ - Figure 1 — Locality Page 3 of 29 Document Set ID: 24138568 Version: 7, Version Date: 17/04/2026
Page 4
2
z
2
3?
ai
BUILDING 62 ~~~~-~--
BUILDING 01
BUILDING 03
Page 4 of 29
Version: 7, Version Date: 17/04/2026
Document Set ID: 24138568
Page 5
Figure 3 – Floor Plan
Page 5 of 29
Document Set ID: 24138568
Version: 7, Version Date: 17/04/2026
Page 6
Figure 4 – Elevations
2. BACKGROUND
19 January 2021 - MCU21/0117 - A development approval for a (Multiple Dwelling - 11 units)
was approved.
12 July 2024 - MCU21/0117.01 - A change request for a (Multiple Dwelling - 12
units) was approved.
3. ASSESSMENT
3.1. Instruments for Statutory Assessment
Under the Planning Act 2016 the application must be assessed against each of the following
statutory planning instruments to the extent they are relevant to the development:
• State Planning Policy;
• South East Queensland Regional Plan;
• Planning Regulation 2017; and
• Noosa Plan 2020 (25 September 2020).
3.2. Statutory Process
The applicant has requested to make a minor change to a development approval under s78 of the
Planning Act 2016. An application for a minor change to a development approval can only be made
in circumstances where a change would constitute a ‘minor change’.
The proposed change to the development approval requested by the applicant is determined to
constitute a minor change on the grounds that:
• the development would not result in substantially different development as the proposal does
not:
o involve a new use; or
o result in the application applying to a new parcel of land; or
o dramatically change the built form in terms of scale, bulk and appearance; or
o change the ability of the proposed development to operate as intended; or
o remove a component that is integral to the operation of the development; or
Page 6 of 29
Document Set ID: 24138568
Version: 7, Version Date: 17/04/2026
Page 7
o significantly impact on traffic flow and the transport network, such as increasing traffic
to the site; or
o introduce new impacts or increase the severity of known impacts; or
o remove an incentive or offset component that would have balanced a negative impact
of the development; or
o impact on infrastructure provisions.
• the change does not include prohibited development;
• the change would not require the application to be referred to an additional referral agency
or cause a referral agency to have regard to new matters prescribed by regulation;
• where the original application was code assessable, the change would not cause the
application to become impact assessable.
3.3. Statutory Instruments – Planning Scheme
The original application was lodged and assessed under the now superseded Noosa Plan 2020
(Sept 2020). Pursuant to s81 of the Planning Act 2017, Council must consider the planning scheme
in effect when the original development application was lodged, however Council may give weight
to Noosa Plan 2020 as the planning scheme in effect at the time of the minor change application
being lodged.
The following codes from Noosa Plan 2020 are applicable to this development:
• Medium Density Residential Zone Code;
• Cooroy Local Plan Code;
• Dual Occupancy and Multiple Dwelling Code;
• Works Codes; and
• Regional Infrastructure Overlay Code (Water Supply Pipeline).
Page 7 of 29
Document Set ID: 24138568
Version: 7, Version Date: 17/04/2026
Page 8
Existing Condition 2
Approved Plans
1. Development undertaken in accordance with this approval must generally comply with the
approved plans of development. The approved plans are listed in the following table unless
otherwise amended by these conditions.
Plan No. Rev. Plan/Document Name Date
7283 – DA02 - Location Plan and Notes, prepared 16/05/2024
by Blackburne Jackson
7283 – DA03 - Site Plan – Level 1 & Level 2 16/05/2024
prepared by Blackburne Jackson
Amendments The above plan is required to be amended to accommodate a 0.5
metre wide landscape bed along the full length of the driveway
(western side of driveway) from Pearl Street.
7283 – DA04 - Floor Plan – Level 1 prepared by 16/05/2024
Blackburne Jackson
Amendments The above plan is required to be amended to accommodate a 0.5
metre wide landscape bed along the full length of the driveway
(western side of driveway) from Pearl Street.
7283 – DA05 - Floor plan - Level 2 prepared by 16/05/2024
Blackburne Jackson
7283 – DA06 - Roof Plan - Level 2 prepared by 16/05/2024
Blackburne Jackson
7283 – DA07 - Elevations - prepared by Blackburne 16/05/2024
Jackson
As annotated by Noosa Council.
7283 – DA08 - Elevations - prepared by Blackburne 16/05/2024
Jackson
7283 – DA09 - Sections - prepared by Blackburne 16/05/2024
Jackson
7283 – DA10 - Finishes - prepared by Blackburne 16/05/2024
Jackson
7283 – DA17 - Elevations – Boundary prepared by 16/05/2024
Blackburne Jackson
7283_L01-01_G Landscape Notes and Schedules Sept 2023
7283_L03-01_G Landscape Planting Plan prepared Sept 2023
by Blackburne Jackson
As annotated by Noosa Council
Page 8 of 29
Document Set ID: 24138568
Version: 7, Version Date: 17/04/2026
Page 9
Amendments The above plan is required to be amended to accommodate a 0.5
metre wide landscape bed along the full length of the driveway
(western side of driveway) from Pearl Street.
7283_L07-01_G Landscape Details prepared by Sept 2023
Blackburne Jackson
Applicant’s Request
The applicant submits;
The change to condition 2 is sought as some minor changes to the built form and the internal layout
(1 bedroom added to each of Units 11 and 12) are proposed, and the plans reflect those changes.
As set out in the Table below, the development fully complies with all the key parameters including
building height and frontage setbacks to Pearl Street which are approved as part of
MCU21/0117.01.
The applicant has requested existing Condition 2 be amended and replaced with the following
amended condition:
Approved Plans
2. Development undertaken in accordance with this approval must generally comply with the
approved plans of development. The approved plans are listed in the following table unless
otherwise amended by these conditions.
Plan No. Rev. Plan/Document Name Date
DA01 10 Cover Page, prepared by 04-08-25
Blackburne Jackson
DA02 10 Location Plan & Notes, prepared
by Blackburne Jackson 04-08-25
DA03 11 Site Plan – Level 1 & 2, prepared 14-08-25
by Blackburne Jackson
DA04 11 Floor Plan – Level 1, prepared by 14-08-25
Blackburne Jackson
DA05 10 Floor Plan – Level 2, prepared by 04-08-25
Blackburne Jackson
DA06 10 Roof Plan, prepared by Blackburne 04-08-25
Jackson
DA07 10 Elevations, prepared by Blackburne 04-08-25
Jackson
DA08 10 Elevations, prepared by Blackburne 04-08-25
Jackson
DA09 10 Sections, prepared by Blackburne 04/08/25
Jackson
Page 9 of 29
Document Set ID: 24138568
Version: 7, Version Date: 17/04/2026
Page 10
DA14 10 Perspectives, prepared by 04-08-25
Blackburne Jackson
DA15 10 Perspectives, prepared by 04-08-25
Blackburne Jackson
L01-01_I I Landscape Notes & Schedules, 08-08-25
prepared by Blackburne Jackson
L03-01_J J Landscape Planting Plan, 14-08-25
prepared by Blackburne Jackson
L03-02_J J Landscape Planting Plan, 14-08-25
prepared by Blackburne Jackson
L07-01_I I Landscape Details, prepared by 08-08-25
Blackburne Jackson
L07-02_A A Landscape Details, prepared by 08-08-25
Blackburne Jackson
Assessment of Request
Agree.
The condition is required to be amended to reflect the requested changes and to includes the plan
amendments from the original approval.
Recommendation
It is recommended existing Condition 2 be amended to read as follows:
Approved Plans
2. Development undertaken in accordance with this approval must generally comply with the
approved plans of development. The approved plans are listed in the following table unless
otherwise amended by these conditions.
Plan No. Rev. Plan/Document Name Date
DA01 10 Cover Page, prepared by 04-08-25
Blackburne Jackson
DA02 10 Location Plan & Notes, prepared
by Blackburne Jackson 04-08-25
DA03 11 Site Plan – Level 1 & 2, 14-08-25
prepared by Blackburne
Jackson
DA04 13 Floor Plan – Level 1, prepared by 17-12-25
Blackburne Jackson
Annotated by Council
Page 10 of 29
Document Set ID: 24138568
Version: 7, Version Date: 17/04/2026
Page 11
DA05 10 Floor Plan – Level 2, prepared by 04-08-25
Blackburne Jackson
DA06 10 Roof Plan, prepared by 04-08-25
Blackburne Jackson
DA07 10 Elevations, prepared by 04-08-25
Blackburne Jackson
DA08 10 Elevations, prepared by 04-08-25
Blackburne Jackson
DA09 10 Sections, prepared by 04/08/25
Blackburne Jackson
DA14 10 Perspectives, prepared by 04-08-25
Blackburne Jackson
DA15 10 Perspectives, prepared by 04-08-25
Blackburne Jackson
DA17 06 Elevations - Boundary, prepared 04-08-25
by Blackburne Jackson
L01-01_I I Landscape Notes & Schedules, 08-08-25
prepared by Blackburne Jackson
L03-01_J J Landscape Planting Plan, 14-08-25
prepared by Blackburne
Jackson
L03-02_J J Landscape Planting Plan, 14-08-25
prepared by Blackburne Jackson
L07-01_I I Landscape Details, prepared by 08-08-25
Blackburne Jackson
L07-02_A A Landscape Details, prepared by 08-08-25
Blackburne Jackson
Existing Condition 29
29. The development site must be landscaped. The works must be undertaken in accordance
with the Noosa Plan PSP 2 – Landscaping and generally in accordance with the approved
Landscaping Plans and in particular:
a) A dense 2m minimum landscaped setback to the full length of the site’s frontage to
Pearl Street (excluding access, fence and bin enclosure).
Page 11 of 29
Document Set ID: 24138568
Version: 7, Version Date: 17/04/2026
Page 12
b) A dense 2.0 m minimum landscaped setback to the full length of the site’s frontage to
Elm Street.
c) A dense 1.0 m minimum landscaped setback to all side boundaries (excluding
stormwater infrastructure).
d) The provision of 3 new street trees in accordance with PSP 2 – Landscaping.
e) All landscape works must be established and maintained in accordance with the
approved design for the life of the development, and in a manner that ensures healthy,
sustained and vigorous plant growth. All plant material must be allowed to grow to full
form and be refurbished when its life expectancy is reach.
Applicant’s Request
The applicant has requested existing Condition 29 be amended and replaced with the following
amended condition:
29. The development site must be landscaped. The works must be undertaken in accordance
with the Noosa Plan PSP 2 – Landscaping and generally in accordance with the approved
Landscaping Plans and in particular:
a) A dense 2m minimum landscaped setback to the full length of the site’s frontage
to Pearl Street (excluding access, fence and bin enclosure).
b) A dense 2m minimum landscaped setback to the full length of the site’s frontage
to Elm Street.
c) A dense 1m minimum landscaped setback to all side boundaries (excluding
stormwater infrastructure) except along the proposed driveway which adjoins Lot 1
RP153798 where a 0.5m wide landscape setback must be provided.
d) The provision of 3 new street trees in accordance with PSP 2 – Landscaping.
e) All landscape works must be established and maintained in accordance with the
approved design for the life of the development, and in a manner that ensures healthy,
sustained and vigorous plant growth. All plant material must be allowed to grow to full
form and be refurbished when its life expectancy is reached.
Assessment of Request
The requested amendment includes a clarification that the side boundary adjacent to the internal
driveway includes a 0.5metre landscaped setback as required under the plan amendments.
Recommendation
Agree.
It is recommended existing condition 29 be amended to read as follows:
29. The development site must be landscaped. The works must be undertaken in accordance
with the Noosa Plan PSP 2 – Landscaping and generally in accordance with the approved
Landscaping Plans and in particular:
a) A dense 2m minimum landscaped setback to the full length of the site’s frontage to Pearl
Street (excluding access, fence and bin enclosure).
b) A dense 2.0 m minimum landscaped setback to the full length of the site’s frontage to
Elm Street.
c) A dense 1.0 m minimum landscaped setback to all side boundaries (excluding
stormwater infrastructure) except along the proposed driveway which adjoins Lot 1
RP153798 where a 0.5m wide landscape setback must be provided.
d) The provision of 3 new street trees in accordance with PSP 2 – Landscaping.
Page 12 of 29
Document Set ID: 24138568
Version: 7, Version Date: 17/04/2026
Page 13
e) All landscape works must be established and maintained in accordance with the
approved design for the life of the development, and in a manner that ensures healthy,
sustained and vigorous plant growth. All plant material must be allowed to grow to full
form and be refurbished when its life expectancy is reach.
Existing Condition 32
Car Parking
32. A minimum of 20 car parking spaces must be provided and marked on the site. The works
must include in particular:
a) 14 covered parking spaces within the total;
b) Four visitor parking spaces within the total, which are clearly marked for that purpose
and accessible at all times for visitor use; and
c) Dimensions, crossfalls and gradients in accordance with Australian Standard AS2890:
Parking Facilities.
Applicant’s Request
A change to Condition 32 is required to reflect the carparking required resulting from the increase
in bedrooms proposed. Noting the carparking numbers fully comply with the Planning Scheme.
The applicant has requested existing condition 32 be amended and replaced with the following
amended condition:
Car Parking
32. A minimum of 20 car parking spaces must be provided and marked on the site. The works
must include in particular:
a) 16 covered parking spaces within the total;
b) Four visitor parking spaces within the total, which are clearly marked for that purpose
and accessible at all times for visitor use; and
c) Dimensions, crossfalls and gradients in accordance with Australian Standard AS2890:
Parking Facilities.
Assessment of Request
Agree. The condition is required to be amended to reflect the onsite carparking numbers which
results from the additional bedrooms.
Recommendation
It is recommended existing Condition 32 be amended to read as follows:
Car Parking
32. A minimum of 20 car parking spaces must be provided and marked on the site. The works
must include in particular:
a) 14 16 covered parking spaces within the total;
b) Four visitor parking spaces within the total, which are clearly marked for that purpose
and accessible at all times for visitor use; and
c) Dimensions, crossfalls and gradients in accordance with Australian Standard AS2890:
Parking Facilities.
Page 13 of 29
Document Set ID: 24138568
Version: 7, Version Date: 17/04/2026
Page 14
Existing Conditions 34 and 35
Stormwater Drainage
34. The site must be provided with a stormwater drainage system connecting to a lawful point of
discharge and be in accordance with the Queensland Urban Drainage Manual (QUDM). The
works must be undertaken in accordance with an Operational Works approval and include in
particular:
a) The works generally as shown on concept plan 23098/SK10 Revision G as prepared
by Morgan Consulting Engineers,
b) Collection and lawful discharge of stormwater to ensure that adjoining properties,
reserves and roads are protected from ponding or actionable nuisance from stormwater
as a result of any works undertaken.
c) the site stormwater system is to accommodate stormwater from Lot 1 RP153798
external to the site, including registration of drainage easements over the site drainage
system in favour of Lot 1 RP153798
d) the use of gravity stormwater drainage and not surcharge pits
35. A stormwater quality treatment system must be provided for the development. The works
must be undertaken in accordance with the Bioretention Technical Design Guidelines (Water
by Design, 2012), and must include in particular stormwater quality treatment devices of a
size and location generally in accordance with those shown in cross sections shown on
concept plan 23098/SK10 Revision G as prepared by Morgan Consulting Engineers.
Applicant’s Request
The applicant submits that Conditions 34 and 35 are required to be amended to support the
updated plans required by Council and extensions of the ground level decks requested by the
applicant over the stormwater swale at the rear of Units 6 & 8.
The applicant has requested existing condition 34 and 35 be amended and replaced with the
following amended condition:
Stormwater Drainage
34. The site must be provided with a stormwater drainage system connecting to a lawful point of
discharge and be in accordance with the Queensland Urban Drainage Manual (QUDM). The
works must be undertaken in accordance with an Operational Works approval and include in
particular:
a) The works generally in accordance with the approved engineering operational works
plans as prepared by Morgan Consulting Engineers.
b) Collection and lawful discharge of stormwater to ensure that adjoining properties,
reserves and roads are protected from ponding or actionable nuisance from stormwater
as a result of any works undertaken.
c) The site stormwater system is to accommodate stormwater from Lot 1 RP153798
external to the site, including registration of drainage easements over the site drainage
system in favour of Lot 1 RP153798.
d) the use of gravity stormwater drainage and not surcharge pits
Page 14 of 29
Document Set ID: 24138568
Version: 7, Version Date: 17/04/2026
Page 15
36. A stormwater quality treatment system must be provided for the development. The works
must be undertaken in accordance with the Bioretention Technical Design Guidelines (Water
by Design, 2012), and must include in particular stormwater quality treatment devices of a
size and location generally in accordance with the approved engineering operational works
plans as prepared by Morgan Consulting Engineers.
Assessment of Request
The requested amendment was referred to development engineering for consideration.
Development engineering advise;
The proposed engineering related changes include:
1. A deck extension to the Unit 6 terrace spanning across the proposed stone pitched swale;
2. Replacement of the Unit 8 terrace with a deck spanning across the level spreader /
stormwater discharge location;
3. Re-configuration of the bio-retention basin resulting in an increase of the bio-retention
area from 9m² to 16m².
A site inspection confirmed that construction has occurred at the site regarding the enlargement
level spreader and bio retention area. The bio-retention basin results in an increase area from 9m²
to 16m². It is unclear why the inconsistency between the approved plans and the constructed
infrastructure has occurred however the works do not impact the functioning of the stormwater
design approved for the development consistent with Council’s Planning Scheme Policy - SC6.7.6
Stormwater Management.
Plans relevant to the MCU have been amended to ensure maintenance of the bio retention area
can occur via common property and as such Council support the proposed changes.
Recommendation
Agree. It is recommended existing conditions 34 and 35 be amended as follows.
Stormwater Drainage
34. The site must be provided with a stormwater drainage system connecting to a lawful point of
discharge and be in accordance with the Queensland Urban Drainage Manual (QUDM). The
works must be undertaken in accordance with an Operational Works approval and include in
particular:
a) The works generally as shown in accordance with on concept plan 23098/SK10
Revision G the approved engineering operational works plans as prepared by Morgan
Consulting Engineers.
b) Collection and lawful discharge of stormwater to ensure that adjoining properties,
reserves and roads are protected from ponding or actionable nuisance from stormwater
as a result of any works undertaken.
c) The site stormwater system is to accommodate stormwater from Lot 1 RP153798
external to the site, including registration of drainage easements over the site drainage
system in favour of Lot 1 RP153798.
d) the use of gravity stormwater drainage and not surcharge pits
35. A stormwater quality treatment system must be provided for the development. The works
must be undertaken in accordance with the Bioretention Technical Design Guidelines (Water
by Design, 2012), and must include in particular stormwater quality treatment devices of a
Page 15 of 29
Document Set ID: 24138568
Version: 7, Version Date: 17/04/2026
Page 16
size and location generally in accordance with those shown in cross sections shown on
concept plan 23098/SK10 Revision G with the approved engineering operational works
plans as prepared by Morgan Consulting Engineers.
Page 16 of 29
Document Set ID: 24138568
Version: 7, Version Date: 17/04/2026
Page 17
Existing Condition 48 (OPW approval)
APPROVED PLANS
48. Development undertaken in accordance with this approval must generally comply with the
approved plans of development. The approved plans are listed in the following table unless
otherwise amended by these conditions.
Plan No. Rev. Plan/Document Name Date
7283_L01-01_G Landscape Notes and schedules Sept 2023
7283_L03-01_G Landscape planting plan Sept 2023
Amendments The above plan is required to be amended to accommodate a 0.5
metre wide landscape bed along the full length of the driveway
(western side of driveway) from Pearl Street.
7283_L07-01_G Landscape Details Sept 2023
The following plans require amendment.
Plan No. Rev. Plan/Document Name Date
23098/SK10 G Concept Site Levels and Drainage Plan 14/05/2024
1. The drawing is marked as conceptual and includes a note
Amendments
advising the drawing is not to be used for construction. Provide
an amended plan that is suitable for Operational Works
Construction for Council approval prior to the prestart meeting.
2. Prior to the prestart meeting, provide an amended plan to Council
for approval that includes the frontage works required in
accordance with the MCU Conditions.
3. Prior to the prestart meeting, provide updated engineering plans
which specifically address the following:
a. A piped solution is proposed for Lot 1 SP153798. Due to the
proposed surface levels of the development driveway, when
events exceed the 2%AEP, or when blockage of the pipe inlet
occurs, flooding/ponding on the upstream lot will occur.
Revise the design to ensure that no ponding/flooding on the
upstream lot will occur in the 1%AEP event based on design
blockage allowance for any pipe system, consistent with
QUDM.
b. Provide cross and long sections and hydrologic and hydraulic
calculations for the swales proposed in the following
locations:
i. On the eastern boundary of the development site to
convey flows from outlet 2/1 to the LPD
ii. From the driveway low-point to the bioretention basin
iii. On the northern and eastern boundaries of Lot 1
SP153798 to convey runoff from the external
catchment to inlet 1/1
Page 17 of 29
Document Set ID: 24138568
Version: 7, Version Date: 17/04/2026
Page 18
c. Provide ILs for the structures on the proposed stormwater
line and confirm what type of structure is 1/1 (headwall or
field inlet)
Applicant’s Request
The applicant submits that;
The Landscaping Plans have been amended to reflect the required 0.5m garden along the western
boundary of the driveway and as a result the listed amendment can be deleted and the detailed
engineering plans included in the Table of approved plans.
The applicant has requested existing Condition 48 be amended and replaced with the following
amended condition:
APPROVED PLANS
48. Development undertaken in accordance with this approval must generally comply with the
approved plans of development. The approved plans are listed in the following table unless
otherwise amended by these conditions.
Plan No. Rev. Plan/Document Name Date
L01-01_I I Landscape Notes & Schedules, prepared 08-08-25
by Blackburne Jackson
L03-01_J J Landscape Planting Plan, prepared by 14-08-25
Blackburne Jackson
L03-02_J J Landscape Planting Plan, prepared by 14-08-25
Blackburne Jackson
L07-01_I I Landscape Details, prepared by 08-08-25
Blackburne Jackson
L07-02_A A Landscape Details, prepared by 08-08-25
Blackburne Jackson
23098/C00 F Cover Sheet and Drawing Index, 07.08.25
prepared by Morgan Consulting
Engineers
23098/C01 B Bulk Earthworks Layout Plan, prepared 07.08.25
by Morgan Consulting Engineers
23098/C02 A Bulk Earthworks Sections, prepared by 07.08.25
Morgan Consulting Engineers
23098/C03 B Concept Erosion and Sediment Control 09.08.24
Plan – Pre Construction, prepared by
Morgan Consulting Engineers
23098/C04 B Concept Erosion and Sediment Control 09.08.24
Plan – Pre Construction, prepared by
Morgan Consulting Engineers
Page 18 of 29
Document Set ID: 24138568
Version: 7, Version Date: 17/04/2026
Page 19
23098/C05 B Concept Erosion and Sediment Control 09.08.24
Details, prepared by Morgan Consulting
Engineers
23098/C10 I Site Works and Drainage Plan Layout 19.08.25
Plan, prepared by Morgan Consulting
Engineers
23098/C11 H Site Works and Drainage Plan – Sheet 1, 19.08.25
prepared by Morgan Consulting
Engineers
23098/C12 H Site Works and Drainage Plan – Sheet 2, 19.08.25
prepared by Morgan Consulting
Engineers
23098/C13 G Site Works and Drainage Details – Sheet 19.08.25
1, prepared by Morgan Consulting
Engineers
23098/C14 F Site Works and Drainage Details – Sheet 19.08.25
2, prepared by Morgan Consulting
Engineers
23098/C15 C Site Works and Drainage Details – Sheet 19.08.25
3, prepared by Morgan Consulting
Engineers
23098/C20 F Stormwater Drainage Catchment Plan, 19.08.25
prepared by Morgan Consulting
Engineers
23098/C21 F Stormwater Drainage Long Sections, 19.08.25
prepared by Morgan Consulting
Engineers
23098/C22 F Stormwater Drainage Calculations, 19.08.25
prepared by Morgan Consulting
Engineers
23098/C30 F External Roadworks Plan, prepared by 19.08.25
Morgan Consulting Engineers
23098/C40 B Sewage Plan Plan, prepared by Morgan 09.08.24
Consulting Engineers
23098/C50 B Water Reticulation Plan, prepared by 09.08.24
Morgan Consulting Engineers
23098/C51 A Water Reticulation Details, prepared by 09.08.24
Morgan Consulting Engineers
23098/C60 B Pavement Jointing Plan, prepared by 07.08.25
Morgan Consulting Engineers
Page 19 of 29
Document Set ID: 24138568
Version: 7, Version Date: 17/04/2026
Page 20
23098/C61 B Pavement Jointing Details, prepared by 08.08.25
Morgan Consulting Engineers
Assessment of Request
Agree. The landscape plans have been amended to include the requested changes.
During the assessment of the request it has come to Council’s attention that the list of approved
plans include several engineering plans which are not relevant to Council’s assessment involving
water / sewer infrastructure etc. Engineering plans not relevant to Council’s assessment have
been removed for the endorsed approved plans for Operational works.
Recommendation
It is recommended existing Condition 48 be amended to read as follows:
Plan No. Rev. Plan/Document Name Date
L01-01_I I Landscape Notes & Schedules, prepared by 08-08-25
Blackburne Jackson
L03-01_J J Landscape Planting Plan, prepared by 14-08-25
Blackburne Jackson
L03-02_J J Landscape Planting Plan, prepared by 14-08-25
Blackburne Jackson
L07-01_I I Landscape Details, prepared by Blackburne 08-08-25
Jackson
L07-02_A A Landscape Details, prepared by Blackburne 08-08-25
Jackson
23098/C00 F Cover Sheet and Drawing Index, prepared 07.08.25
by Morgan Consulting Engineers
23098/C01 B Bulk Earthworks Layout Plan, prepared by 07.08.25
Morgan Consulting Engineers
23098/C02 A Bulk Earthworks Sections, prepared by 07.08.25
Morgan Consulting Engineers
23098/C10 I Site Works and Drainage Plan Layout Plan, 19.08.25
prepared by Morgan Consulting Engineers
23098/C11 H Site Works and Drainage Plan – Sheet 1, 19.08.25
prepared by Morgan Consulting Engineers
Page 20 of 29
Document Set ID: 24138568
Version: 7, Version Date: 17/04/2026
Page 21
23098/C12 H Site Works and Drainage Plan – Sheet 2, 19.08.25
prepared by Morgan Consulting Engineers
23098/C13 G Site Works and Drainage Details – Sheet 1, 19.08.25
prepared by Morgan Consulting Engineers
23098/C14 F Site Works and Drainage Details – Sheet 2, 19.08.25
prepared by Morgan Consulting Engineers
23098/C15 C Site Works and Drainage Details – Sheet 3, 19.08.25
prepared by Morgan Consulting Engineers
23098/C20 F Stormwater Drainage Catchment Plan, 19.08.25
prepared by Morgan Consulting Engineers
23098/C21 F Stormwater Drainage Long Sections, 19.08.25
prepared by Morgan Consulting Engineers
23098/C22 F Stormwater Drainage Calculations, 19.08.25
prepared by Morgan Consulting Engineers
23098/C30 F External Roadworks Plan, prepared by 19.08.25
Morgan Consulting Engineers
23098/C60 B Pavement Jointing Plan, prepared by 07.08.25
Morgan Consulting Engineers
23098/C61 B Pavement Jointing Details, prepared by 08.08.25
Morgan Consulting Engineers
Existing Condition 63 (OPW approval)
63. All works must be constructed and work procedure undertaken in accordance with:
a) The approved plans/documents and conditions detailed in this Decision Notice;
b) The relevant conditions of the higher order Material Change of Use approval viz.
MCU21/0117.01 to which this approval relates;
c) All relevant Noosa Council Planning Scheme Policies, standard drawings, standard
specifications and guidelines;
d) The latest version of the Healthy Waterways document “Water Sensitive Urban Design
Technical Design Guidelines for South East Queensland” for all water quality devices
to be constructed on site.
Applicant’s Request
Page 21 of 29
Document Set ID: 24138568
Version: 7, Version Date: 17/04/2026
Page 22
The applicant has requested existing Condition 63 be amended and replaced with the following
amended condition:
63. All works must be constructed and work procedure undertaken in accordance with:
a) The approved plans/documents and conditions detailed in this Decision Notice;
b) The relevant conditions of the higher order Material Change of Use approval viz.
MCU21/0117.02 to which this approval relates;
c) All relevant Noosa Council Planning Scheme Policies, standard drawings, standard
specifications and guidelines;
d) The latest version of the Healthy Waterways document “Water Sensitive Urban Design
Technical Design Guidelines for South East Queensland” for all water quality devices
to be constructed on site..
Assessment of Request
Agree.
The condition is required to be amended to reflect the current application number.
Recommendation
It is recommended existing condition 63 be amended to read as follows:
63. All works must be constructed and work procedure undertaken in accordance with:
a) The approved plans/documents and conditions detailed in this Decision Notice;
b) The relevant conditions of the higher order Material Change of Use approval viz.
MCU21/0117.01 MCU21/0117.02 to which this approval relates;
c) All relevant Noosa Council Planning Scheme Policies, standard drawings, standard
specifications and guidelines;
d) The latest version of the Healthy Waterways document “Water Sensitive Urban Design
Technical Design Guidelines for South East Queensland” for all water quality devices
to be constructed on site.
Existing Condition 97 (OPW approval)
Landscaping
97. The development site must be landscaped. The works must be undertaken in accordance
Noosa Plan PSP 2 – Landscaping and generally in accordance with the approved
Landscaping Plans and in particular:
a) A dense 2m minimum landscaped setback to the full length of the site’s frontage to
Pearl Street (excluding access, fence and bin enclosure).
b) A dense 2m minimum landscaped setback to the full length of the site’s frontage to Elm
Street.
c) A dense 1m minimum landscaped setback to all side boundaries (excluding stormwater
infrastructure).
d) Retention of all existing street trees.
Page 22 of 29
Document Set ID: 24138568
Version: 7, Version Date: 17/04/2026
Page 23
Applicant’s Request
The applicant has requested existing condition 97 be amended and replaced with the following
amended condition:
Landscaping
97. The development site must be landscaped. The works must be undertaken in accordance
Noosa Plan PSP 2 – Landscaping and generally in accordance with the approved
Landscaping Plans and in particular:
a) A dense 2m minimum landscaped setback to the full length of the site’s frontage to
Pearl Street (excluding access, fence and bin enclosure).
b) A dense 2m minimum landscaped setback to the full length of the site’s frontage to Elm
Street.
c) A dense 1m minimum landscaped setback to all side boundaries (excluding stormwater
infrastructure) except along the proposed driveway which adjoins Lot 1 RP153798
where a 0.5m wide landscape setback must be provided.
d) The provision of 3 new street trees in accordance with PSP 2 – Landscaping.
e) All landscape works must be established and maintained in accordance with the
approved design for the life of the development, and in a manner that ensures healthy,
sustained and vigorous plant growth. All plant material must be allowed to grow to full
form and be refurbished when its life expectancy is reached.
Assessment of Request
The requested amendment includes a clarification that the side boundary adjacent to the internal
driveway includes a 0.5metre landscaped setback as required under the plan amendments.
Recommendation
Agree.
It is recommended existing Condition 97 be amended to read as follows:
Landscaping
97. The development site must be landscaped. The works must be undertaken in accordance
Noosa Plan PSP 2 – Landscaping and generally in accordance with the approved
Landscaping Plans and in particular:
a) A dense 2m minimum landscaped setback to the full length of the site’s frontage to
Pearl Street (excluding access, fence and bin enclosure).
b) A dense 2m minimum landscaped setback to the full length of the site’s frontage to Elm
Street.
c) A dense 1m minimum landscaped setback to all side boundaries (excluding stormwater
infrastructure) except along the proposed driveway which adjoins Lot 1 RP153798
where a 0.5m wide landscape setback must be provided.
d) Retention of all existing street trees. The provision of 3 new street trees in
accordance with PSP 2 – Landscaping.
e) All landscape works must be established and maintained in accordance with the
approved design for the life of the development, and in a manner that ensures
healthy, sustained and vigorous plant growth. All plant material must be allowed
to grow to full form and be refurbished when its life expectancy is reached.
Page 23 of 29
Document Set ID: 24138568
Version: 7, Version Date: 17/04/2026
Page 24
Existing Part 9 - REFERENCE DOCUMENT
Plan No. Rev. Plan/Document Name Date
23098 - SBSMP/4 4 Site-Based Stormwater Management Plan 14/5/2024
prepared by Morgan Consulting Engineers
Applicant’s Request
The applicant has requested the referenced Site Based Stormwater Management Plan can be
removed because the submitted detailed engineering Operational works plans are requested to be
included as part of the approved plans.
Assessment of Request
Agree. The amended Stormwater Management Plans have been recommended for inclusion as
Approved plans within the Operational works permit.
Recommendation
Plan No. Rev. Plan/Document Name Date
23098 - SBSMP/4 4 Site-Based Stormwater Management Plan 14/5/2024
prepared by Morgan Consulting Engineers
4. CONSULTATION
4.1. Referral Agencies
Not applicable
4.2. Internal Council Referrals
The application was forwarded to the following internal Council officers for review and/or comment:
• Senior Development Engineer, Development Assessment
5. CONCLUSION & REASONS FOR DECISION
The proposed development generally complies with the requirements of the planning scheme and
does not raise any significant issues that cannot be addressed by reasonable and relevant
conditions. The application is therefore recommended for approval.
The report is provided in accordance with Section 83(9) of the Planning Act 2016.
RECOMMENDATION
With regard to Application No. MCU21/0117.02 to make a minor change to an existing approval
situated at 5 Pearl St Cooroy Qld 456354 Elm St Cooroy Qld 4563 and described as Lot 2 RP
64750, Council on 10 April 2026 decided to:
A. Approve the change - Development Permit for Material Change of Use – Multiple Dwelling
(12 Units)
B. Amend Conditions 2, 29, 32, 34 & 35 of the Development Permit for Material Change of Use
to read as follows:
Page 24 of 29
Document Set ID: 24138568
Version: 7, Version Date: 17/04/2026
Page 25
Approved Plans
2. Development undertaken in accordance with this approval must generally comply with the
approved plans of development. The approved plans are listed in the following table unless
otherwise amended by these conditions.
Plan No. Rev. Plan/Document Name Date
DA01 10 Cover Page, prepared by 04-08-25
Blackburne Jackson
DA02 10 Location Plan & Notes, prepared 04-08-25
by Blackburne Jackson
DA03 11 Site Plan – Level 1 & 2, prepared 14-08-25
by Blackburne Jackson
DA04 13 Floor Plan – Level 1, prepared by 17-12-25
Blackburne Jackson
Annotated by Council
DA05 10 Floor Plan – Level 2, prepared by 04-08-25
Blackburne Jackson
DA06 10 Roof Plan, prepared by Blackburne 04-08-25
Jackson
DA07 10 Elevations, prepared by Blackburne 04-08-25
Jackson
DA08 10 Elevations, prepared by Blackburne 04-08-25
Jackson
DA09 10 Sections, prepared by Blackburne 04/08/25
Jackson
DA14 10 Perspectives, prepared by 04-08-25
Blackburne Jackson
DA15 10 Perspectives, prepared by 04-08-25
Blackburne Jackson
DA17 06 Elevations - Boundary, prepared by 04-08-25
Blackburne Jackson
L01-01_I I Landscape Notes & Schedules, 08-08-25
prepared by Blackburne Jackson
L03-01_J J Landscape Planting Plan, 14-08-25
prepared by Blackburne Jackson
L03-02_J J Landscape Planting Plan, 14-08-25
prepared by Blackburne Jackson
Page 25 of 29
Document Set ID: 24138568
Version: 7, Version Date: 17/04/2026
Page 26
L07-01_I I Landscape Details, prepared by 08-08-25
Blackburne Jackson
L07-02_A A Landscape Details, prepared by 08-08-25
Blackburne Jackson
Condition 29
29. The development site must be landscaped. The works must be undertaken in accordance
with the Noosa Plan PSP 2 – Landscaping and generally in accordance with the approved
Landscaping Plans and in particular:
a) A dense 2m minimum landscaped setback to the full length of the site’s frontage to Pearl
Street (excluding access, fence and bin enclosure).
b) A dense 2m minimum landscaped setback to the full length of the site’s frontage to Elm
Street.
c) A dense 1m minimum landscaped setback to all side boundaries (excluding stormwater
infrastructure) except along the proposed driveway which adjoins Lot 1 RP153798 where
a 0.5m wide landscape setback must be provided.
d) The provision of 3 new street trees in accordance with PSP 2 – Landscaping.
e) All landscape works must be established and maintained in accordance with the
approved design for the life of the development, and in a manner that ensures healthy,
sustained and vigorous plant growth. All plant material must be allowed to grow to full
form and be refurbished when its life expectancy is reached.
Car Parking
32. A minimum of 20 car parking spaces must be provided and marked on the site. The works
must include in particular:
a) 16 covered parking spaces within the total;
b) Four visitor parking spaces within the total, which are clearly marked for that purpose
and accessible at all times for visitor use; and
e) Dimensions, crossfalls and gradients in accordance with Australian Standard AS2890:
Parking Facilities.
Stormwater Drainage
34. The site must be provided with a stormwater drainage system connecting to a lawful point of
discharge and be in accordance with the Queensland Urban Drainage Manual (QUDM). The
works must be undertaken in accordance with an Operational Works approval and include in
particular:
a) The works generally in accordance with the approved engineering operational works
plans as prepared by Morgan Consulting Engineers.
b) Collection and lawful discharge of stormwater to ensure that adjoining properties,
reserves and roads are protected from ponding or actionable nuisance from stormwater
as a result of any works undertaken.
c) The site stormwater system is to accommodate stormwater from Lot 1 RP153798
external to the site, including registration of drainage easements over the site drainage
system in favour of Lot 1 RP153798.
d) the use of gravity stormwater drainage and not surcharge pits
Page 26 of 29
Document Set ID: 24138568
Version: 7, Version Date: 17/04/2026
Page 27
35. A stormwater quality treatment system must be provided for the development. The works
must be undertaken in accordance with the Bioretention Technical Design Guidelines (Water
by Design, 2012), and must include in particular stormwater quality treatment devices of a
size and location generally in accordance with the approved engineering operational works
plans as prepared by Morgan Consulting Engineers.
RECOMMENDATION
With regard to Application No. OPW21/0199.02, to make a minor change to an existing approval
situated at 5 Pearl St Cooroy Qld 456354 Elm St Cooroy Qld 4563 described Lot 2 RP 64750, Lot
2 RP 153798, Council on 10 April 2026 decided to:
A. Approve the change to Development Permit for Operational Works.- Roadwork, Drainage
work, Landscaping, Stormwater & Earthworks
B Amend Conditions 48,63 & 97of the Development Permit for Operational Works to read as
follows:
APPROVED PLANS
48. Development undertaken in accordance with this approval must generally comply with the
approved plans of development. The approved plans are listed in the following table unless
otherwise amended by these conditions.
Plan No. Rev. Plan/Document Name Date
L01-01_I I Landscape Notes & Schedules, prepared by 08-08-25
Blackburne Jackson
L03-01_J J Landscape Planting Plan, prepared by 14-08-25
Blackburne Jackson
L03-02_J J Landscape Planting Plan, prepared by 14-08-25
Blackburne Jackson
L07-01_I I Landscape Details, prepared by Blackburne 08-08-25
Jackson
L07-02_A A Landscape Details, prepared by Blackburne 08-08-25
Jackson
23098/C00 F Cover Sheet and Drawing Index, prepared 07.08.25
by Morgan Consulting Engineers
23098/C01 B Bulk Earthworks Layout Plan, prepared by 07.08.25
Morgan Consulting Engineers
Page 27 of 29
Document Set ID: 24138568
Version: 7, Version Date: 17/04/2026
Page 28
23098/C02 A Bulk Earthworks Sections, prepared by 07.08.25
Morgan Consulting Engineers
23098/C10 I Site Works and Drainage Plan Layout Plan, 19.08.25
prepared by Morgan Consulting Engineers
23098/C11 H Site Works and Drainage Plan – Sheet 1, 19.08.25
prepared by Morgan Consulting Engineers
23098/C12 H Site Works and Drainage Plan – Sheet 2, 19.08.25
prepared by Morgan Consulting Engineers
23098/C13 G Site Works and Drainage Details – Sheet 1, 19.08.25
prepared by Morgan Consulting Engineers
23098/C14 F Site Works and Drainage Details – Sheet 2, 19.08.25
prepared by Morgan Consulting Engineers
23098/C15 C Site Works and Drainage Details – Sheet 3, 19.08.25
prepared by Morgan Consulting Engineers
23098/C20 F Stormwater Drainage Catchment Plan, 19.08.25
prepared by Morgan Consulting Engineers
23098/C21 F Stormwater Drainage Long Sections, 19.08.25
prepared by Morgan Consulting Engineers
23098/C22 F Stormwater Drainage Calculations, 19.08.25
prepared by Morgan Consulting Engineers
23098/C30 F External Roadworks Plan, prepared by 19.08.25
Morgan Consulting Engineers
23098/C60 B Pavement Jointing Plan, prepared by 07.08.25
Morgan Consulting Engineers
23098/C61 B Pavement Jointing Details, prepared by 08.08.25
Morgan Consulting Engineers
63. All works must be constructed and work procedure undertaken in accordance with:
a) The approved plans/documents and conditions detailed in this Decision Notice;
b) The relevant conditions of the higher order Material Change of Use approval viz.
MCU21/0117.02 to which this approval relates;
Page 28 of 29
Document Set ID: 24138568
Version: 7, Version Date: 17/04/2026
Page 29
c) All relevant Noosa Council Planning Scheme Policies, standard drawings, standard
specifications and guidelines;
d) The latest version of the Healthy Waterways document “Water Sensitive Urban Design
Technical Design Guidelines for South East Queensland” for all water quality devices
to be constructed on site..
Landscaping
97. The development site must be landscaped. The works must be undertaken in accordance
Noosa Plan PSP 2 – Landscaping and generally in accordance with the approved
Landscaping Plans and in particular:
a) A dense 2m minimum landscaped setback to the full length of the site’s frontage to
Pearl Street (excluding access, fence and bin enclosure).
b) A dense 2m minimum landscaped setback to the full length of the site’s frontage to Elm
Street.
c) A dense 1m minimum landscaped setback to all side boundaries (excluding stormwater
infrastructure) except along the proposed driveway which adjoins Lot 1 RP153798
where a 0.5m wide landscape setback must be provided.
d) The provision of 3 new street trees in accordance with PSP 2 – Landscaping.
e) All landscape works must be established and maintained in accordance with the
approved design for the life of the development, and in a manner that ensures healthy,
sustained and vigorous plant growth. All plant material must be allowed to grow to full
form and be refurbished when its life expectancy is reached.
C. Delete Part 9 Reference Documents and insert, Not applicable.
Page 29 of 29
Document Set ID: 24138568
Version: 7, Version Date: 17/04/2026
Used in these records
Minor Change Report MCU21 0117 02 (As Published).pdfRelated documentApplication case desk ↗
Minor Change Report MCU21 0117 02 (As Published).pdfRelated documentApplication case desk ↗
About this file
- File size
- 1.7 MB (small file)
- File type
No other editions are linked here.