The applicant has requested existing Condition 63 be amended and replaced with the following
amended condition:
63. All works must be constructed and work procedure undertaken in accordance with:
a) The approved plans/documents and conditions detailed in this Decision Notice;
b) The relevant conditions of the higher order Material Change of Use approval viz.
MCU21/0117.02 to which this approval relates;
c) All relevant Noosa Council Planning Scheme Policies, standard drawings, standard
specifications and guidelines;
d) The latest version of the Healthy Waterways document “Water Sensitive Urban Design
Technical Design Guidelines for South East Queensland” for all water quality devices
to be constructed on site..
Assessment of Request
Agree.
The condition is required to be amended to reflect the current application number.
Recommendation
It is recommended existing condition 63 be amended to read as follows:
63. All works must be constructed and work procedure undertaken in accordance with:
a) The approved plans/documents and conditions detailed in this Decision Notice;
b) The relevant conditions of the higher order Material Change of Use approval viz.
MCU21/0117.01 MCU21/0117.02 to which this approval relates;
c) All relevant Noosa Council Planning Scheme Policies, standard drawings, standard
specifications and guidelines;
d) The latest version of the Healthy Waterways document “Water Sensitive Urban Design
Technical Design Guidelines for South East Queensland” for all water quality devices
to be constructed on site.
Existing Condition 97 (OPW approval)
Landscaping
97. The development site must be landscaped. The works must be undertaken in accordance
Noosa Plan PSP 2 – Landscaping and generally in accordance with the approved
Landscaping Plans and in particular:
a) A dense 2m minimum landscaped setback to the full length of the site’s frontage to
Pearl Street (excluding access, fence and bin enclosure).
b) A dense 2m minimum landscaped setback to the full length of the site’s frontage to Elm
Street.
c) A dense 1m minimum landscaped setback to all side boundaries (excluding stormwater
infrastructure).
d) Retention of all existing street trees.
Page 22 of 29
Document Set ID: 24138568
Version: 7, Version Date: 17/04/2026
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalUsed in these records
Minor Change Report MCU21 0117 02 (As Published).pdfRelated documentApplication case desk ↗
Minor Change Report MCU21 0117 02 (As Published).pdfRelated documentApplication case desk ↗
About this file
- File size
- 1.7 MB (small file)
- File type
No other editions are linked here.