FIGURE 11: Indicative Open Forest Planting Module
Reconstruction planting works are to occur immediately following completion of the initial weed
management works. To obtain optimum results all plantings are to be implemented in
accordance with the methodology described below:
Native plantings must be healthy with tree species of a single, straight trunk, free of
pests and disease. All tree/small tree/shrub/groundcover specimens must not be pot-
bound or root-girdled;
For each new plant, dig a steep-sided hole 1.5 times the depth (~400mm) and 3 times
the width of the stock container, leaving loose soil in its base for roots to bind with;
Position plant upright in the hole and back-fill soil with moderate pressure to form a
‘well’ around the stem for water retention (soil must be level with top of root-ball);
Hand-soak each plant with approximately 3 – 5 litres of water;
Spread forest mulch around each plant to a depth of 100mm and radius of 1m, avoiding
direct contact of any mulch with the stem/trunk (soil and mulch must also not be mixed).
Such will ensure native vegetation structure and diversity/composition is progressively restored
to its natural state.
5.3 Maintenance/Monitoring
The designated rehabilitation areas must be maintained/monitored in an ongoing capacity to
achieve the performance criteria detailed within SECTION 6.0 following.
Maintenance/monitoring is to occur at routine intervals concurrently with those previously
specified for weed management works (i.e. monthly for an establishment phase of three (3)
months then quarterly thereafter until such time as cover/structure provided by native
vegetation satisfactorily inhibits further weed invasion/edge-effects).
It is recommended that photographs of the reconstruction planting area be taken at each
maintenance interval from permanent monitoring points (refer APPENDIX 2 and PLATES 10
& 11 following) per the following GPS references:
Rehabilitation Management Plan
Page 16 434 Lake Cooroibah Rd, Cooroibah
Franz Enterprises Pty Ltd
Document Set ID: 24816703
Version: 1, Version Date: 25/05/2026
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalUsed in these records
Reference Document - RAL26 0015 - Rehabilitation Management Plan (As Published).pdfRelated documentApplication case desk ↗
About this file
- File size
- 4.9 MB (large file)
- File type
No other editions are linked here.
Original file
Log in to download the original file
The download may take up to a minute.