Negotiated Decision Notice - 010.2008.00000890.001 [As Published] · 132008.890
2008/890
3 RELEVANT PERIOD OF APPROVAL
The relevant period for this Development Approval is identified in the Assessment Manager
conditions.
4 ASSESSMENT MANAGER CONDITIONS
1. Development undertaken in accordance with this approval must generally comply with the
approved plans of development. The approved plans are listed in the following table and as may
be amended by these conditions.
Plan / Rev. Plan / Document Name Date
Document No.
Plan of an Area to be Leased – Ken Hicks & 14/05/08
Associates
2. The development must be undertaken and operated in a manner that causes no detrimental
effect upon the amenity of the neighbourhood by reason of the creation of excessive noise,
lighting nuisance or other emissions.
3. Any advertising sign or device is to comply with Council's policies on advertising.
4. All goods are to be displayed on site within the property boundaries and/or on the premises
approved for the use.
5. Any new hot water systems installed shall be either solar systems; electric heat pump systems;
or gas systems (LPG or natural).
6. Any new kitchen, laundry and bathroom fittings shall comply with the AAA Water Conservation
Rating System as defined by the AS/NZS 6400 (Water Efficient Products - Rating and Labelling
2003) and AS/NZS 3500 (National Plumbing and Drainage Standard Part 1.2), with toilets to
comply with the AAAA Water Conservation Rating System. All tap ware and shower roses shall
not exceed a maximum flow of 9 litres per min. Dishwashers and washing machines are
excluded from this requirement.
7. The Development Permit for a material change of use of premises lapses if the use has not
happened by 20 August 2012, unless an application to extend the currency is approved by
Council.
Contributions Towards Council Infrastructure
8. Monetary contributions shall be paid to Noosa Council towards the cost of providing and/or
upgrading various infrastructure at the rates applicable at the time of payment. An estimate only
of the contribution amounts under the current Council policies and requirements is outlined in
the table below:
Contribution Required For: Amount:
PSP12 – Public Open Space Contributions (Park) $184
PSP16 – Sewerage Headworks Contributions $0
PSP17 – Water Supply Headworks Contributions $0
PSP20 – Pathway Trunk Network Contributions $185
TOTAL Contribution Amount = $ 369
Please note, that these amounts are all subject to variations in the Consumer Price Index, All
Groups Brisbane from March 2008 until the date of payment.
2 of 7
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalUsed in these records
Negotiated Decision Notice - 010.2008.00000890.001 [As Published]Related documentApplication case desk ↗
About this file
- File size
- 56 KB (small file)
- File type
No other editions are linked here.