Decision Notice - Minor Change - 132007 12 9 [As Published]

of 18

Page text shows just the words. Original shows the document exactly as it was published.

               5.     Digital detailed designs including drawings, calculations, specifications and a schedule of
                      works, shall be submitted with any application for a Development Permit for Operational
                      Works in respect of roadworks and stormwater drainage works. In this regard a DXF/DWG
                      file on GDA94 zone 56 grid of the proposed cadastre layout is to be submitted in conjunction
                      with any application for Operational Works. The design shall be in accordance with Council’s
                      Planning Scheme Policy PSP05 – Engineering Design Standards – Roads, Drainage and
                      Earthworks.
               6.     To facilitate production of As Constructed drawings it is suggested that all design drawings
                      are submitted in the Asset Design and As Constructed (ADAC) digital format. (Guidelines on
                      the use of ADAC are available at www.adac.com.au).
               7.     Prior to the commencement of the development, a plumbing assessment must be obtained
                      from Noosa Council’s Plumbing Services Section in accordance with the Plumbing &
                      Drainage Act 2002 (as applicable).
               8.     The requirements of the Environmental Protection Amendment Regulation (No. 2) 1999 and
                      Local Law No. 12, prevents a builder or building contractor carrying out building work on a
                      building site in a way that makes or causes audible noise to be made from the building work:-
                      8.1. On a Sunday or public holiday, at any time; or
                      8.2. On a Saturday or a business day, before 7.00am or after 6.30pm.
                      A maximum penalty of $1,500 applies to an offence under this legislation.
               9.     Pursuant to the Building and Construction Industry (Portable Long Service Leave) 1991 Act
                      if the cost of operational works exceeds $150,000, then a portable long service leave levy is
                      required to be paid. In accordance with Section 77.(1) of the Act, Council is required to sight
                      the approved form issued by the Building and Construction Industry (Portable Long Service
                      Leave) Authority that confirms that the requirements of the Act have been satisfied. A
                      statutory declaration outlining the cost of the operational works must be submitted to Council
                      with the lodgement of any application for operational works over the site.
               10.    The plans for the proposed building work have not been assessed for compliance with the
                      requirements of the Building Code of Australia as they relate to people with disabilities. Your
                      attention is drawn to the matter that either or both the Disability Discrimination Act 1992
                      (commonwealth) and the Anti-Discrimination Act 1991(Queensland) may impact on the
                      proposed building work.
               11.    Noosa Council recommends that the following matters be considered to address equitable
                      access and facilities in the building:-
                      A.      The building and environs should be designed to meet the requirements of the Human
                              Rights and Equal Opportunity Commission “Advisory Notes on Access to Premises”
                              and AS1428.2;
                              1.       Applicants should be aware that a “Disability Standard on Access to Premises is
                                       being developed and most likely will result in changes to the Building Code of
                                       Australia;
                              2.       Any services and facilities in the building complex must allow independent,
                                       dignified and equitable use of the services and facilities for all people.
               12.    This proposal has not been assessed in relation to the spread of fire between properties /
                      buildings. It is the building certifiers responsibility to assess the requirements for fire services,
                      fire separation and appropriate methods of construction as part of the building works approval
                      process. Referral to the Queensland Fire and Rescue Service (QFRS) may be required as
                      part of the Building Approval process.




                                                                                                           Page 15 of 18
Document Set ID: 22465906
Version: 7, Version Date: 22/06/2023
Log in to download the original file

Decision Notice - Minor Change - 132007 12 9 [As Published].pdf · 339 KB (small file)

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.