Concurrence and Advice Agency Response - Department of Environment & Resource Management · OPW11/0116

Attached to the e-mail Referral Agency Response - Department of Environment & Resource Management.

of 29

Text shows just the words. Original shows the document exactly as it was published.

Check the original when the exact wording matters.

 

B6.

DERM Permit number: SPCC01881911

During and following construction of the works, any areas disturbed by the works are to be
stabilised against wind erosion, rainwater run-off erosion and revegetated with endemic
native species commonly found on adjacent areas or present prior to disturbance.

END OF CONDITIONS FOR SCHEDULE B

Schedule C - Monitoring

C1.
C2.

C3.

C4.

C5.

C6.

The operator must implement a monitoring plan from the commencement of these works.

The monitoring plan must achieve the following outcomes, but not limited to:
(a) long-term ecological impacts associated with the works;
' (b) effectiveness of the erosion protection works;
(b) compliance with the conditions of this development permit;
(c) operations are adjusted in response to. monitoring results to ensure compliance
with development permit conditions ‘

Quarterly monitoring of the works must be undertaken and records kept of its performance

during the works and for the life of the works, or until otherwise advised by the administering
authority that such monitoring can cease.

Water quality monitoring must be undertaken daily and regularly (at fixed intervals or at evenly
spaced intervals) at suitable locations within the works area and records kept of all relevant
observations.

The holder of this development approval must notify the administering authority in writing
within 14 days of any monitoring result which indicates any failure of the works or exceedance
of any licence limit.

The operator of this development permit must monitor the visual impact of the operational
works area on the environment by undertaking the following when works are being carried out;
(a) Daily observations and recording of the extent of any turbidity plume caused by
the works; and
(b) Daily observations and recording of extent and period of time turbidity persists.

END OF CONDITIONS FOR SCHEDULE C

Schedule D - Water

Di.

D2.

D3.

D4,

All reasonable and practicable measures must be taken to minimise any increase in turbidity
of the waters or the release of contaminants as a result of these works to any waters.

In the event that the administering authority requires water quality sampling, all determinations
of the quality of the samples must be:
(a) made in accordance with methods prescribed in the latest edition of the Department
of Environment and Resource Management Water Quality Sampling Manual; and
(b) carried out on samples that are representative of the works area.

The works must not result in a change in water chemistry that will impact upon ecological
values on or off site.

The only contaminants permitted to be released to any waters (including the bed or banks

- of such waters) are sediments disturbed during the works.

 

Page 7 of 11°

091217 Department of Environment and Resource Management

 

 

Used in these records

About this file

File size
1.0 MB (small file)
File type
PDF

No other editions are linked here.

Original file

Log in to download the original file

Concurrence and Advice Agency Response - Department of Environment & Resource Management.pdf · 1.0 MB (small file)

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.