                                                                                                                  ITEM 6 SEPTEMBER 2014 QUARTERLY BUDGET REVIEW

September Quarter Budget Review
September 2014


Supporting
Document                                                                                    Capital /
Reference    Cost Centre/Project            Financial Statement                      Amount Operating    Comment
OPERATING
CEO01        CEO                            Materials and Services             $ 45,184.00 Operating     LGAQ Online not in original budget
CEO02        CEO                            Materials and Services             -$ 13,446.33 Operating    Saving in Council of Mayors subscription
CEO03        CEO                            Materials and Services             $    1,472.73 Operating   LGMA subscription not in original budget
CS001        Noosa Leisure Centre           Materials and Services             -$ 12,000.00 Operating    PMI#58 Purchase of Table Tennis Tables Savings - project initiated in previous year
CS002        Community, Culture and Sport   Grants and Subsidies - Operating   -$ 25,000.00 Operating    Additional RADF grant received
CS002        Community, Culture and Sport   Materials and Services             $ 25,000.00 Operating     RADF grant expenditure
CS003        Animal Control                 Fees & Charges                     $ 31,416.00 Operating     Revenue from cat registrations removed - Council decision
CS004        Respite                        Grants and Subsidies - Operating   -$ 105,704.34 Operating   Indexation of Noosa Community Care grant
CS004        Respite                        Materials and Services             $ 72,298.12 Operating     Indexation of Noosa Community Care grant
CS006        Noosa Leisure Centre           Employee Benefits                  $ 80,000.00 Operating     Casual Leisure Centre Coordinator appointed as permanent
CS007        Cooroy Butter Factory          Sales and Recoverable Works        -$   9,414.96 Operating   Cooroy Butter Factory - Service review revenue reduction applied to one line in OB - now split
                                                                                                         based on forecast to 31 Dec
CS007        Cooroy Butter Factory          Fees & Charges                     $    9,414.96 Operating   Cooroy Butter Factory - Service review revenue reduction applied to one line in OB - now split
                                                                                                         based on forecast to 31 Dec
CS008        Pest Animal Control            Materials and Services             $ 18,967.50 Operating     Wild Dogs control program
CS010        Respite                        Materials and Services             $    8,600.00 Operating   Respite Centre - Extension to gardens to accommodate extra day of Horticulture Therapy
                                                                                                         service output
CS011        Noosa Leisure Centre           Materials and Services             -$ 30,000.00 Operating    Leisure Centre Contractor - replaced with casual employee
CS011        Noosa Leisure Centre           Employee Benefits                  $ 30,000.00 Operating     Leisure Centre Contractor - replaced with casual employee
CS012        Noosa Leisure Centre           Fees & Charges                     -$ 12,000.00 Operating    Leisure Centre New Yoga model - contractors now paying venue hire
CS012        Noosa Leisure Centre           Materials and Services             -$ 20,000.00 Operating    Leisure Centre New Yoga model (leased arrangement)
CS012        Noosa Leisure Centre           Fees & Charges                     $ 32,000.00 Operating     Leisure Centre New Yoga model (leased arrangement)
CS013        Sunshine Beach Skate Park      Materials and Services             -$   4,000.00 Operating   Aquatic Centre / Skate Park Contractor - replaced with casual employee
CS013        Sunshine Beach Skate Park      Employee Benefits                  $    4,000.00 Operating   Aquatic Centre / Skate Park Contractor - replaced with casual employee
CS015        Library Program & Services     Materials and Services             $    5,096.00 Operating   SCC Libraries literacy program
CS017        Community, Culture and Sport   Grants and Subsidies - Operating   -$ 21,705.45 Operating    Graffitti Stop Grant revenue received
CS017        Community, Culture and Sport   Materials and Services             $ 21,705.45 Operating     Graffitti Stop Grant related expenditure
CS018        Get Ready                      Grants and Subsidies - Operating   -$ 10,035.00 Operating    Get Ready Grant revenue


                                                                                        Page 1                                                                                Budget Review 2 -2014-15
Log in to download the original file

2014-11-11 Planning & Organisation Committee Updated Attachment 1 to Item 6(PDF, 473KB).pdf · 485 KB (small file)

Searchable page text hides email addresses. Original files are unchanged and may show email addresses.

Full text of the other 5 sections

Section 2

Supporting
Document                                                                                 Capital /
Reference    Cost Centre/Project                    Financial Statement          Amount Operating      Comment
CS018        Get Ready                              Materials and Services   $ 10,035.00 Operating     Get Ready Grant related expenditure
EO004        Tourism                                Other Expenses           -$   7,819.00 Operating   Savings in Noosa Triathlon budget


EO005        Noosa Junction Levy                    Other Expenses           $    9,539.25 Operating   Transfer 2013/14 remaining unspent levy balance to Noosa Junction Traders
EO006        Noosa Junction Levy                    Materials and Services   -$ 90,480.00 Operating    reallocate to correct natural account
EO006        Noosa Junction Levy                    Other Expenses           $ 90,480.00 Operating     reallocate to correct natural account
EO008        Risk Management and Insurances         Materials and Services   -$ 20,000.00 Operating    Insurance transferred to Fleet
EO008        Fleet Plant and Workshop Operations    Materials and Services   $ 20,000.00 Operating     Insurance transferred to Fleet
PI002        Environmental Services Co-ordination   Employee Benefits        -$ 118,691.36 Operating   Service review realised employment cost savings
PI002        Accounting Other                       Employee Benefits        $ 50,000.00 Operating     Unallocated savings applied to above
OS002        Boreen Point Town Water Network        Materials and Services   $    4,000.00 Operating   Boreen Point Town Water Network maintenance
OS003        Treasury                               Finance Costs            $    2,685.00 Operating   Bank fees reallocation
OS003        Cooroy Waste Transfer Facility         Finance Costs            -$    341.04 Operating    Bank fees reallocation
OS003        Pomona Waste Transfer Facility         Finance Costs            -$    342.00 Operating    Bank fees reallocation
OS003        Noosaville Landfill Eumundi Road       Finance Costs            -$   2,001.96 Operating   Bank fees reallocation

OS005        ICT Infrastructure                     Materials and Services   $ 131,520.00 Operating    Mobile phone charges reallocation to ICT.
OS005        Various                                Materials and Services   -$ 131,520.00 Operating   Mobile phone charges reallocation to ICT.
OS006        Pelican Place                          Materials and Services   -$    900.00 Operating    Building maintenance budget reallocation
OS006        Pelican Place                          Materials and Services   -$ 14,185.00 Operating    Building maintenance budget reallocation
OS006        Tewantin Admin Building                Materials and Services   $     900.00 Operating    Building maintenance budget reallocation
OS006        Pelican Place                          Materials and Services   $ 14,185.00 Operating     Building maintenance budget reallocation
PI006        Ringtail Quarry                        Internal Recoveries      -$ 47,150.00 Operating    Recognition of Internal Quarry charges.
PI006        Noosa River Caravan Park               Internal Charges         $     200.00 Operating    Recognition of Internal Quarry charges.
PI006        North Shore Campground                 Internal Charges         $    4,000.00 Operating   Recognition of Internal Quarry charges.
PI006        Gravel Roads                           Internal Charges         $    2,250.00 Operating   Recognition of Internal Quarry charges.
PI006        Bridges                                Internal Charges         $     400.00 Operating    Recognition of Internal Quarry charges.
PI006        Drainage                               Internal Charges         $ 20,000.00 Operating     Recognition of Internal Quarry charges.
PI006        Road Furniture                         Internal Charges         $     800.00 Operating    Recognition of Internal Quarry charges.
PI006        Vegetation                             Internal Charges         $     100.00 Operating    Recognition of Internal Quarry charges.
PI006        Pathways                               Internal Charges         $    2,000.00 Operating   Recognition of Internal Quarry charges.


                                                                                      Page 2                                                                            Budget Review 2 -2014-15

Section 3

Supporting
Document                                                                                       Capital /
Reference    Cost Centre/Project                   Financial Statement                 Amount Operating    Comment
PI006        Beach Management                      Internal Charges              $    9,000.00 Operating   Recognition of Internal Quarry charges.
PI006        Parks and Gardens                     Internal Charges              $    8,400.00 Operating   Recognition of Internal Quarry charges.
PI005        Retification Works - Bunnings Site    Recoverable Works             -$ 83,053.99 Operating    Reallocation from unearned revenue as at 30 June 14
PI005        Parks and Gardens                     Contract Services             $ 83,053.99 Operating     Reallocation from unearned revenue as at 30 June 14
OS008        Community Leases                      Sales and Recoverable Works   -$ 56,000.00 Operating    Recovery of Unity water charges from leased properties
OS008        Community Leases                      Sales and Recoverable Works   -$ 12,000.00 Operating    Electricity recovery from leased properties
OS009        Fleet Plant and Workshop Operations   Sales and Recoverable Works   $ 27,000.00 Operating     Budget reallocation of Beach Cleaner Noosa Main Beach
OS009        Fleet Plant and Workshop Operations   Internal Recoveries           -$ 27,000.00 Operating    Budget reallocation of Beach Cleaner Noosa Main Beach
OS009        Beach Management - Main Beach Noosa   Materials and Services        -$ 11,571.48 Operating    Budget reallocation of Beach Cleaner Noosa Main Beach
OS009        Beach Management - Main Beach Noosa   Internal Plant Charges        $ 11,571.48 Operating     Budget reallocation of Beach Cleaner Noosa Main Beach
OS009        Beach Management- General             Internal Plant Charges        $ 15,428.52 Operating     Budget reallocation of Beach Cleaner Noosa Main Beach
PI007        Sports Grounds                        Materials and Services        -$ 65,000.00 Operating    Maintenance of Girraween sportsfield now provided by clubs.
OS001        Various                               Other Expenses                -$ 21,885.72 Operating    Fire levy adjustment
OS001        Various                               Internal Charges              -$ 166,886.22 Operating   Natural Account tidy up - Individual amounts not substantial
OS001        Various                               Internal Recoveries           $ 166,886.22 Operating    Natural Account tidy up - Individual amounts not substantial
OS001        Various                               Internal Charges               $ 167,486.80 Operating   Natural Account tidy up - Individual amounts not substantial
OS001        Various                               Internal Recoveries           -$ 167,486.80 Operating   Natural Account tidy up - Individual amounts not substantial
OS004        ICT Applications                      Materials and Services        $ 40,488.27 Operating     Technology One HR licence costs
OS010        ICT Applications                      Materials and Services        $    2,050.00 Operating   Additional drafting software licence costs
OS010        ICT Applications                      Materials and Services        $ 29,688.59 Operating     Technology One Assets software licencing
OS010        ICT Applications                      Materials and Services        $    5,349.84 Operating   Technology One HRM WH&S and ELT software licence costs
OS010        ICT Applications                      Materials and Services        $    4,235.40 Operating   Black Mountain Tower Power Consumption
OS010        ICT Applications                      Materials and Services        $    5,495.50 Operating   Duncan AutoIssue and handset software maintenance
OS010        ICT Infrastructure                    Materials and Services        $    5,349.84 Operating   T1 Cloud fee ETL - GIS Integration
OS010        ICT Infrastructure                    Materials and Services        $    7,600.00 Operating   Sensis advertising (Whitepages)
OS010        ICT Spatial Information               Materials and Services        $    8,000.00 Operating   DERM Aerial Photos
OS011        Accounting Other                      Internal Recoveries           -$ 38,000.00 Operating    Recognise internal plant hire for capital projects
TOTAL OPERATING                                                                  -$    287.19




                                                                                          Page 3                                                                          Budget Review 2 -2014-15

Section 4

Supporting
Document                                                                                       Capital /
Reference    Cost Centre/Project                 Financial Statement                    Amount Operating   Comment
CAPITAL
CP003        Transport Infrastructure Planning   Grants and Subsidies - Capital   -$ 205,000.00 Capital    Bus Stop Program additional funding for 9 bus stops (50% funding).
CP003        Transport Infrastructure Planning   Materials and Services           $ 410,000.00 Capital     Bus Stop Program capital expenditure (Council to fund 50%)
CP003        Sealed Roads                        Materials and Services           -$ 205,000.00 Capital    NSC contribution reallocated from contingent renewals funds
CP001        Noosa Aquatic Centre                Materials and Services           $    7,710.00 Capital    Noosa Aquatic Centre Pool Blanket. Winch modifications
CP001        Sealed Roads                        Materials and Services           -$   7,710.00 Capital    Noosa Aquatic Centre Pool Blanket. Emergent Infrastructure Renewal. Reallocated from
                                                                                                           contingent funds.
CP004        Transport Infrastructure Planning   Grants and Subsidies - Capital   $ 57,600.00 Capital      Noosa Bus Stations Safer Program. Adjustment for reduced grant funding
CP004        Transport Infrastructure Planning   Materials and Services           -$ 57,600.00 Capital     Noosa Bus Stations Safer Program. Adjustment for reduced grant funding
CP005        Transport Infrastructure Planning   Materials and Services           -$ 15,019.00 Capital     Whole of Shire - On Road Cycle Network. Savings to purchase IT program.
CP005        ICT Applications                    Materials and Services           $ 15,019.00 Capital      Purchase of CAD engineering drafting IT program
CP002        Sealed Roads                        Materials and Services           $ 553,610.00 Capital     Additional Roads to Recovery Grant applied to Walter Hay Drive resealing
CP002        Sealed Roads                        Grants, subsidies - Capital      -$ 553,610.00 Capital    Recognition of additional Roads to Recovery grant
CP006        Sealed Roads                        Grants, subsidies - Capital      -$ 42,500.00 Capital     Grant Funding Eenie Creek Rd/Walter Hay Drive Intersection Safety Upgrade (50% funding)

CP006        Sealed Roads                        Materials and Services           $ 85,000.00 Capital      Eenie Creek Rd/Walter Hay Drive Intersection Safety Upgrade (Council funding 50%)
CP007        Transport Infrastructure Planning   Grants, subsidies - Capital      $ 10,000.00 Capital      Sunrise Beach - Ben Lexcen Dr school. Grant Reduction
CP007        Transport Infrastructure Planning   Materials and Services           $ 10,000.00 Capital      Sunrise Beach - Ben Lexcen Dr school. Grant Reduction
CP008        Transport Infrastructure Planning   Grants, subsidies - Capital      -$ 115,000.00 Capital    Grant Funding Cooroy Noosa Rd Corridor Improvement (50% funding)
CP008        Transport Infrastructure Planning   Materials and Services           $ 230,000.00 Capital     Cooroy Noosa Rd Corridor Improvement (Council funding 50%)
CP009        Pathways                            Grants, subsidies - Capital      -$ 20,000.00 Capital     Grant Funding Eenie Creek Pathway (Cycle Grant 50% funding)
CP009        Pathways                            Materials and Services           $ 40,000.00 Capital      Eenie Creek Pathway (Council funding 50%)
CP010        Pathways                            Grants, subsidies - Capital      -$ 200,000.00 Capital    Grant Funding Wallace Park Shared Pathway (Cycle Grant 50% funding)
CP010        Pathways                            Materials and Services           $ 400,000.00 Capital     Wallace Park Shared Pathway (Council funding 50%)
CP011        Cooroy Library                      Materials and Services           $    9,338.50 Capital    Cooroy Library Tactile Marker Replacement

CP011        Sealed Roads                        Materials and Services           -$ 9,338.50 Capital      Cooroy Library Tactile Marker. Emergent all Infrastructure Renewal. Reallocated from
CP012        Parks and Gardens                   Materials and Services            $ 24,500.00 Capital     Botanical Gardens Park Furniture Renewal
CP012        Sealed Roads                        Materials and Services           -$ 24,500.00 Capital     Botanical Gardens. Emergent all Infrastructure Renewal. Reallocated from contingent funds.
CP013        Drainage                            Materials and Services           $ 50,000.00 Capital      Noosa River Flood mitigation strategy
CP014        Transport Infrastructure Planning   Materials and Services           $ 50,000.00 Capital      New Noosa Bus Shelters - Design

CP014        Sealed Roads                        Materials and Services           -$ 50,000.00 Capital     New Noosa Bus Shelters - Design. Emergent all Infrastructure Renewal. Project cost
                                                                                                           reallocated from contingent funds.


                                                                                            Page 4                                                                              Budget Review 2 -2014-15

Section 5

Supporting
Document                                                                                       Capital /
Reference    Cost Centre/Project                    Financial Statement                Amount Operating    Comment
CP016        Environmental Services Co-ordination   Materials and Services        $ 300,000.00 Capital     Noosa River Hydraulic Model.
CP017        Community Leases                       Materials and Services        $ 10,000.00 Capital      Girraween Sports Complex Lighting

CP018        Sealed Roads                           Materials and Services        -$ 30,000.00 Capital     Borreen Point Tennis Court. Emergent all Infrastructure Renewal. Project cost reallocated from
                                                                                                           contingent funds.
CP018        Boreen Point Caravanpark               Materials and Services        $ 30,000.00 Capital      Borreen Point Tennis Court refurbishment
CP019        Canals and Waterways                   Materials and Services        $ 60,000.00 Capital      Munna Point Foreshore Stabilisation
CP020        Commercial Land & Property             Materials and Services        $ 750,000.00 Capital     Land Aquisition
CP021        Road Furniture                         Materials and Services        -$ 29,085.25 Capital     Eumundi Rd Corridor Improvement. Realloaction.
CP021        Transport Infrastructure Planning      Materials and Services        $ 29,085.25 Capital      Eumundi Rd Corridor Improvement. Realloaction.
CP022        Transport Infrastructure Planning      Materials and Services        $    5,100.00 Capital    Noosa Junction Disabled Parking. Original estimate excluded design and survey
CP023        Canals and Waterways                   Materials and Services        $ 20,000.00 Capital      Noosaville - Gympie Tce / Williams St. Increased design costs due to enhanced scope
CP024        Noosa Aquatic Centre                   Materials and Services        -$   6,648.18 Capital    Noosa Aquatic Centre - pool cleaner. Project completed below budget
CP025        Public Amenities                       Employee Benefits             -$ 20,000.00 Capital     Whole of Shire- public toilet / sewerage. Deferred Handover of STP from Unitywater on hold
CP026        Public Amenities                       Materials and Services        -$ 15,000.00 Capital     Whole of Shire- public toilet / sewerage. Deferred Handover of STP from Unitywater on hold
CP027        Environmental Services Co-ordination   Employee Benefits             -$ 200,000.00 Capital    Weyba Creek - bank erosion restoration. Deferred to 15/16 capital program
CP028        Parks and Gardens                      Employee Benefits             -$   6,000.00 Capital    Noosaville - Munna Pk basket ball court. Project completed below budget
CP029        Parks and Gardens                      Materials and Services        -$ 11,058.38 Capital     Noosaville -Gympie Tce Foreshore BBQs. Project completed below budget
CP029        Parks and Gardens                      Materials and Services        $ 60,000.00 Capital      Change scope to provide better structure Noosville Lions Park Pirate Playground.
CP029        Parks and Gardens                      Materials and Services        -$ 60,000.00 Capital     Emergent all Infrastructure Renewal. Project cost reallocated from contingent funds.
CP030        Parks and Gardens                      Materials and Services        $ 10,000.00 Capital      Whole of Shire - playground renewal program. Additional urgent repairs.

CP030        Parks and Gardens                      Materials and Services        -$ 10,000.00 Capital     Whole of Shire - playground renewal program. Emergent all Infrastructure Renewal. Project
                                                                                                           cost reallocated from contingent funds.
CP031        Parks and Gardens                      Materials and Services        $ 10,000.00 Capital      Tewantin - pathway upgrade and lighting. Additional urgent repairs.

CP031        Parks and Gardens                      Materials and Services        -$ 10,000.00 Capital     Tewantin - pathway upgrade and lighting. Emergent all Infrastructure Renewal. Project cost
                                                                                                           reallocated from contingent funds.
CP032        Pathways                               Grants, subsidies - Capital   $ 250,000.00 Capital     Noosa Heads - Main Beach boardwalk. Unsuccessful Grant application (grant revenue
                                                                                                           reduced)
CP032        Pathways                               Employee Benefits             -$ 500,000.00 Capital    Noosa Heads - Main Beach boardwalk. Unsuccessful Grant (expenditure reduced)

CP033        Pathways                               Grants, subsidies - Capital   $ 425,000.00 Capital     Noosa Heads - Park Rd boardwalk stage 3a. Unsuccessful Grant application (grant revenue
                                                                                                           reduced)
CP033        Pathways                               Employee Benefits             -$ 850,000.00 Capital    Noosa Heads - Park Rd boardwalk stage 3a. Unsuccesful Grant (expenditure reduced)
CP034        Sport and Community                    Employee Benefits             -$ 12,000.00 Capital     Girraween Sports Ground irrigation. Completed under budget
CP035        Pathways                               Materials and Services        -$ 43,400.00 Capital     Pomona State School Station Street Pathway improvements. Project to be redesigned


                                                                                            Page 5                                                                             Budget Review 2 -2014-15

Section 6

Supporting
Document                                                                                      Capital /
Reference     Cost Centre/Project                  Financial Statement                Amount Operating    Comment
CP036         Sealed Roads                         Materials and Services        -$ 2,797.00 Capital      Eenie Creek Road / Langura Street Intersection safety upgrade. Completed under budget
CP037         Sealed Roads                         Materials and Services         $ 30,000.00 Capital     Noosaville - Eumundi Noosa Road corridor additional works required

CP038         Transport Infrastructure Planning    Grants, subsidies - Capital   $ 62,500.00 Capital      Whole of Shire - On Road Cycle Network grant funding reduction. Cycle networks no
                                                                                                          improvements identified, green treatments to be done by reseal program
CP038         Transport Infrastructure Planning    Materials and Services        -$ 109,981.00 Capital    Whole of Shire - On Road Cycle Network expenditure reduction. Cycle networks no
                                                                                                          improvements identified, green treatments to be done by reseal program
CP039         Noosaville Landfill Eumundi Road     Employee Benefits             -$ 50,000.00 Capital     Noosaville Landfill - stormwater. Works not able to be undertaken

CP040         Noosa Waters Canal Management Levy   Materials and Services        $ 150,000.00 Capital     Noosa Waters - scour protection stage 2b. Addional due to extra section being completed in
                                                                                                          sequence.
CP041         ICT Infrastructure                   Materials and Services        -$ 35,000.00 Capital     Whole of Shire - Tech One HR module. Not purchasing all modules.
CP042         Transport Infrastructure Planning    Materials and Services        -$ 25,000.00 Capital     Standards Review - Standard Drawings. Scope changed to focus on old red book
TOTAL CAPITAL                                                                    $ 623,215.44

GRAND TOTAL                                                                      $ 622,928.25




                                                                                           Page 6                                                                            Budget Review 2 -2014-15

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.