Noosa Shire Council
Charges Resolution (No. 2) 2014
12.2 Application of section
Section 12 applies where:
(a) the development to which the trunk infrastructure relates has been
lawfully completed;
(b) the trunk infrastructure is planned under this document to service the
development of other premises and has been completed and handed
over to Council;
(c) the amount of the value of an infrastructure offset has not been fully
offset against a levied infrastructure charge to which the trunk
infrastructure relates.
12.3 Payment of a refund
(1) A refund will be paid by Council (as applicable) to the applicant in accordance
with the following:
(a) the refund will not exceed the value of the unused infrastructure offset
and is not subject to indexation;
(b) The amounts and timing of refund payments will be made as follows:
(i) for refund amounts up to $150,000, the payment will occur in the
December quarter in the financial year following completion of the
works and handover of the trunk infrastructure to Council; and
(ii) for remaining refund balance amounts over $150,000 up to
$500,000 the payment will occur in the December quarter in the
second financial year following completion of the works and
handover of the trunk infrastructure to Council; and
(iii) for any remaining refund balance amounts over $500,000, the
payment will occur in the December quarter in the third financial
year following completion of the works and handover of the trunk
infrastructure to Council.
13. CONVERSION APPLICATIONS
13.1 Purpose
Section 13 states the Council’s criteria for consideration and assessment of applications
to convert non-trunk infrastructure to trunk infrastructure.
13.2 Application of section
(1) This section applies if:
(a) a condition of a development approval requires non-trunk infrastructure
to be provided; and
(b) the construction of the non-trunk infrastructure has not started.
Council Resolution effective 16 February 2015
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalSearchable page text hides email addresses. Original files are unchanged and may show email addresses.