RFI - Attachment 8 - Energex Netwrok Connection Contract
3044 09.10.2018
Page 11 of 11
Schedule 1 – Work Activities
ENERGEX WORK
1 Work at Premises
i Nil
2 Network Alteration / Extension Works
i Nil
CUSTOMER’S ACTIVITIES
3 The Customer must:
i Contact their Electricity Retailer and enter into a supply agreement with an electricity
retailer for NMI 31206756356;
ii contact its Electricity Retailer (or a Metering Coordinator, as appropriate) to arrange
for the appropriate Metering Equipment to be installed;
iii Engage an Electrical Contractor to facilitate the connection or upgrade to the premise.
Such duties required are but not limited to;
a. ensuring the premise complies with the relevant standards and distributor’s
requirements (AS/NZL3000, Queensland Electricity Connection Manual,
Queensland Electricity Metering Manual);
b. submit and link an EWR to Connect Application CX21LEO0705658A ;
iv Engage an electrical contractor to organise and connect a generator to the main
switchboard to avoid outages where practical;
The Customer must complete the above Customer Activities at least 1 week prior to the
estimated works completion date contained in Item 12 of Part 1. If the Customer fails to do
so, Energex may need to delay the completion of the work in accordance with clause 9 of
Part 2. The delays to rescheduling your Connection Services under the current Energex
Program will be up to a minimum of 2 weeks.
Energex Limited ⚫ GPO Box 1461 Brisbane Queensland 4001 ⚫ ABN 40 078 849 055
WR Reference: !Undefined Bookmark, WORKREQUE