RFI - Attachment 8 - Energex Netwrok Connection Contract

of 11

Page text shows just the words. Original shows the document exactly as it was published.

                                                                                                                   3044 09.10.2018
                                                                                                                       Page 6 of 11



  11. Energex Obtained Approvals                     Energex will obtain the following approvals (where applicable):
                                                     (i)   traffic control permits from the relevant road authority;
                                                     (ii)  any environmental/vegetation clearing permits for clearing of
                                                           vegetation contained on a public road; and
                                                     (iii) local government authority approvals for the installation of any
                                                           Energex works on land or roads controlled by that local
                                                           government authority.
  12. Program for Energex                            Commencement Date:
      Connection Services                            Within one business day after all of the following conditions have been
                                                     met or the formation of this contract (whichever is the later):
                                                     (i) payment of the Connection Charges is received by Energex;
                                                          and
                                                     (ii) you have complied with all applicable Customer obligations
                                                          under clauses 6 and 7 of Part 2.
                                                     Completion Date:
                                                     Estimated works Completion Date will be 2 weeks from the
                                                     Commencement Date.
                                                     Energisation Date:
                                                     If you require Energex to energise the Premises to allow the supply of
                                                     electricity in addition to the Energex Connection Services, Energex
                                                     shall complete this energisation within 5 business days (unless an
                                                     alternative timeframe has been agreed) of the last of the following to
                                                     occur:
                                                     (i) the completion of the Energex Connection Services;
                                                     (ii) Energex receiving a completed Electrical Works Request (EWR)
                                                           from your electrical contractor; and
                                                     (iii) Energex has received a completed service order from your
                                                           Electricity Retailer.
  13. Technical and Safety                           (i)    You, and any electrical contractor engaged by you, must comply
      Obligations                                           with the requirements set out in the Queensland Electricity
                                                            Connection and Metering Manual (‘the Manual’) relevant to the
                                                            Energex Connection Services. These requirements include,
                                                            but are not limited to, those set out in Chapters 5, 6 and 7 of the
                                                            Manual.
                                                            A copy of the Manual can be found in the Contractors and
                                                            Service Providers section of the Energex website:
                                                            www.energex.com.au
                                                      (ii) You must ensure that the Premises are wired by a qualified
                                                           electrician in accordance with Australian Standard AS3000 and
                                                           the requirements of the Electrical Safety Regulation 2002 (Qld)
                                                           (‘the Regulation’). Any work to be performed on or near
                                                           exposed electrical parts must be undertaken by ‘Authorised
                                                           Persons’ as defined under the Regulation and in accordance
                                                           with the requirements of the Regulation.




                                 Energex Limited ⚫ GPO Box 1461 Brisbane Queensland 4001 ⚫ ABN 40 078 849 055

WR Reference: !Undefined Bookmark, WORKREQUE
Log in to download the original file

RFI - Attachment 8 - Energex Netwrok Connection Contract.pdf · 302 KB (small file)

Searchable page text hides email addresses. Original files are unchanged and may show email addresses.

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.