Original source · versioned page text
2022-07-18 General Committee Meeting Agenda
Text sections have not been matched to the original PDF pages. Use the original document to check page numbers.
GENERAL COMMITTEE MEETING AGENDA 18 JULY 2022
Category Summary Comments
Fees and $8.9 million (107.4%) Property and Facility fees $240k above FY budget
Charges of the $8.3 million (158.7% or $648k of $408k annual budget earned)
annual budget has Plumbing application fees $162k above FY budget
been earned (112.4% or $1.46 million of $1.3 million annual budget
earned)
Development assessment fees $75k above FY budget
(103.1% or $2.5 million of $2.4 million annual budget
earned)
Local Laws fees $57k above FY budget (103.7% or
$1.6 million of $1.6 million annual budget earned)
Building application fees $41k above FY budget
(104.8% or $898k of $857k annual budget earned)
Sale of Goods $12.9 million (117%) Holiday Park sales $706k above FY budget (123% or
and Services of the $11.1 million $3.8 million of $3.1 million annual budget earned) –
annual budget has offset in part by additional variable operating costs
been received Waste management sale of recoverable materials
$595k above FY budget (152.4% or $1.7 million of $1.1
million annual budget earned)
Waste disposal fees $250k above FY budget (106.2%
or $4.2 million of $4.0 million annual budget earned)
Noosa Aquatic Centre revenue $150k above FY
budget (108.7% or $1.87 million of $1.71 million annual
budget earned)
Interest $795k (119%) of the Interest revenues on cash invested will need ongoing
Received $670k annual budget monitoring to ensure returns on surplus funds are
has been earned maximised as investment rates begin to increase.
Other Revenue $2.8m (90%) of the Waste kerbside waste bin recoveries from Cleanaway
$3.1 million annual below FY budget $123k (45.4% or $102k of $226k
budget has been annual budget earned) – correlates with lower kerbside
earned bin purchases
Holiday Park electricity recoupment below FY budget
$118k. No revenue recouped FY due to supplier delays
from COVID. Works have now commenced, and
project is in implementation phase.
Unbudgeted insurance proceeds received $52k
Operating $8.4 million (142%) of $1.4 million in Community resilience and disaster
Grants, the $5.9 million annual management grants have been received in respect to
Subsidies budget has been the recent flood event. These funds have been
received recorded as operational grants until the program of
works has been finalised.
Council received $392k from the Black Summer
Bushfire Recovery Grant program for building bushfire
resilience through technology innovation with $167k
allocated for operational projects.
75% of the 2023 financial assistance grant was prepaid
in April 2022. Historically only 50% of this grant is
prepaid in June so this may impact on Council’s
2022/23 final operating position if the prepayment
approach is discontinued by the Australian
government.
Unitywater On track Unitywater distributions are fixed each year so little
Distributions budget variance risk
Page 19 of 45
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalSearchable page text hides email addresses. Original files are unchanged and may show email addresses.