N70-T63-s376 Change decision notice responsible entity
Attached to the e-mail MCU12/0041 DAFF amended response to applicant's change request (Removal of condition 20).
SPD-0215-015204
(ii)
if a decision notice was not previously given and the negotiated decision
notice relates to a deemed approval—the standard conditions applying to
the deemed approval.
(5) If the assessment manager does not agree with any of the representations, the
assessment manager must, within 5 business days after the day the assessment
manager decides not to agree with any of the representations, give written notice to
the applicant stating the decision about the representations.
364 Giving new notice about charges for infrastructure
(1) This section applies if the development approved by the negotiated decision notice is
different from the development approved in the decision notice or deemed approval in
a way that affects the amount of an infrastructure charge, regulated infrastructure
charge or adopted infrastructure charge.
(2) The local government may give the applicant a new infrastructure charges notice
under section 633, regulated infrastructure charges notice under section 643 or
adopted infrastructure charges notice under section 648F to replace the original
notice.
366 Applicant may suspend applicant’s appeal period
(1) If the applicant needs more time to make the representations, the applicant may, by
written notice given to the assessment manager, suspend the applicant’s appeal
period.
(2) The applicant may act under subsection (1) only once.
(3) If the representations are not made within 20 business days after the day written
notice was given to the assessment manager, the balance of the applicant’s appeal
period restarts.
(4) If the representations are made within 20 business days after the day written notice
was given to the assessment manager—
(a) if the applicant gives the assessment manager a notice withdrawing the notice
under subsection (1)—the balance of the applicant’s appeal period restarts the
day after the assessment manager receives the notice of withdrawal; or
(b) if the assessment manager gives the applicant a notice under section 363(5)—
the balance of the applicant’s appeal period restarts the day after the applicant
receives the notice; or
(c) if the assessment manager gives the applicant a negotiated decision notice—the
applicant’s appeal.
Chapter 7 Appeals, offences and enforcement
Part 1 Planning and Environment Court
Division 8 Appeals to court relating to development applications and approvals
461 Appeals by applicants
(1) An applicant for a development application may appeal to the court against any of the
following—
(a) the refusal, or the refusal in part, of the development application;
(b) any condition of a development approval, another matter stated in a
development approval and the identification or inclusion of a code under section
242;
(c) the decision to give a preliminary approval when a development permit was
applied for;
(d) the length of a period mentioned in section 341;
(e) a deemed refusal of the development application.
(2) An appeal under subsection (1)(a), (b), (c) or (d) must be started within 20 business
days (the applicant’s appeal period) after—
Department of State Development, Infrastructure and Planning Page 7
See the original
The page text is free to read. Viewing or downloading an original file needs an account.