INTRODUCTION 1-1
1 INTRODUCTION
For the Doonella Noosa project, stages A, Band D have been approved and are in differing phases
of construction. The process which has been utilised in obtaining these approvals (in respect of
stormwater management) for these earlier stages has included a process of review and checking.
Generally, Stockland’s civil designer would firstly integrate the requirements of the approved
’Doonella Noosa Stormwater and Water Quality Management Plan’ (Final Report), R.B14640.001.04
(September2005), into their civil design drawings for the respective stages. At this stage, BMT WBM
would review the designs for consistency with the Doonella Noosa Storm water and Water Quality
Management Plan (WBM, 2005). Any shortcomings would be addressed prior to issue of final
designs for approval by Council.
BMT WBM commenced review work of Stage C designs in August 2009, however due to external
factors Stockland Developments postponed the completion of the designs. In August of 2010, BMT
WBM recommenced assessment of Stage C, but with the inclusion of the "Link Road" which was
added within the Stockland owned portions of the site after discussions with Sunshine Coast
Regional Council (SCRC). The effect of the addition of the Link Road within the Stockland owned
portions of the site was that several hundred square metres of dedicated storm water treatment land
was lost to accommodate road and related infrastructure.
The effect of the loss was critical to stormwater management of the Stage C site, in that the lost area
for stormwater treatment meant that the previously established water quality objectives (discussed
further below) were unable to be met. This matter was discussed at length with SCRC, and as a
result of specific statements included within the court order which provides for development approval,
SCRC were unable to accept any of the options presented to them in respect of stormwater
management.
As such, Stockland Development has proposed to make amendments to the court order to address
these issues relating to stormwater management.
G:\ADMINIB15573.G.BAD’R.B15573.002.00.DOC
(f!. BMTWBM
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalUsed in these records
Further information re Request to Change Approval MCU 132003.221132.8Related documentApplication case desk ↗
About this file
- File size
- 39.0 MB (very large file)
- File type
No other editions are linked here.
Original file
Log in to download the original file
The download may take a few minutes. On mobile data, it is best to wait for Wi-Fi.