Council archive · source document
Decision Notice - 010.2007.00002023.001 [As Published] · 132007.2023
NOOSA COUNCIL IDAS Development Application Decision Notice 3 of 6
Noosa Council Conditions
INTEGRATED PLANNING ACT 1997, IDAS DEVELOPMENT APPLICATION
General
1. Development undertaken in accordance with this approval must generally comply with the approved plans
of development. The approved plans are titled Basement Floor Plan, Ground Floor Plan, First Floor Plan,
Roof Plan, Elevations North & South, Elevations, East & West, Sections A & B, and Sections C & D & E
& F and numbered WD 01 A, WD 02 A, WD 03 A, WD 04 B, WD 05 B, WD 06 B, WD, 07 B and WD 08 B
prepared by Middap Ditchfield Pty Ltd and dated August 2007 and as may be amended by these
conditions and annotations on the plans.
2. The development must be undertaken and operated in a manner that causes no detrimental effect upon
the amenity of the neighbourhood by reason of the creation of excessive noise, lighting nuisance or other
emissions.
3. All hot water systems installed shall be either solar systems; electric heat pump systems; or gas systems
(LPG or natural).
4. A rainwater storage tank with a minimum capacity of 5000 litres shall be provided on site to service the
detached house. The tank is to be installed to ensure water from the tank can be used both:
4.1. for external use such as watering gardens, irrigation, ornamental ponds or water features, topping
up swimming pools, outdoor cleaning; and
4.2. for use in flushing of toilets internal to the building.
3
5. As the site is located below the 5m AHD, any excavation works consisting of 100m or greater and/or any
3
filling works consisting of 500m or greater and with an average depth of 0.5m or greater will need to be
carried out in accordance with the recommendations found in the Soil Surveys report entitled Acid Sulfate
Soil Investigation & Management Plan For a Proposed Development at 59 Wyuna Court, Noosa Heads,
Version 1.1, prepared for Middap Ditchfield Pty Ltd by Bio-Track Pty Ltd and dated 23 October 2007.
Easements
6. Buildings and structures (including swimming pools, sheds, tennis courts or outbuildings) are not
constructed under overhead electricity transmission lines, or within any easements.
Currency
7. The Development Permit for a material change of use lapses if the use has not happened by 30 October
2011, unless an application to extend the currency is approved by Council.
AOP2 c:\docume~1\aop2\locals~1\temp\bcl technologies\easypdf 5\@bcl@bc0593dd\@[email protected]
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalUsed in these records
Decision Notice - 010.2007.00002023.001 [As Published]Related documentApplication case desk ↗
About this file
- File size
- 26 KB (small file)
- File type
No other editions are linked here.