Council archive · source document
response to information request · MCU19/0117
20. Clarify if the information presented in the report is accurate and forms part of
the assessment material for the development application.
21. Provide an Ecological Assessment Report, based on Planning Scheme Policy
18 Ecological Assessment Guidelines, which assesses the environmental
values of the development footprint and surrounds and the impact the
development will have on these values with the construction and on-going use
of the development.
An updated copy of each of the reports was sent back through to Council in October 2019.
No further requests were made by Council and it is considered the existing reports
appropriately address the environmental values of the development footprint.
---------------------------------------------------------------------------------------------------------------------
22. Clarify if the information presented in the report is accurate and forms part of
the assessment material for the development application.
23. Provide a plan showing the extent of clearing required to achieve a radiant heat
flux level at any point on the building or envelope that does not exceed 29
kW/m².
24. Provide a detailed plan which documents all the species of vegetation to be
cleared to facilitate the development.
25. Provide information regarding the purpose of clearing of vegetation outside the
footprint of the development.
The updated earthworks and pool plans included as Appendix 7 are overlaid on the
original tree survey for the site, describing the trees for removal. No further trees are to be
removed beyond the development footprint.
----------------------------------------------------------------------------------------------------------------------
Pursuant to the Development Assessment Rules, the applicant has given the assessment
manager the information requested. In accordance with the DARules, please forward
through the adjoining owners’ details to commence public notification.
If you have any further queries in relation to the above, please do not hesitate to contact
myself.
Regards,
Jack Lewis B.Sc Hons UNSW M.Plan Otago MPIA
Planner/Director
Pivotal Perspective Pty Ltd
0406 334 227
Page 9 of 9
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalUsed in these records
response to information request.pdfRelated documentApplication case desk ↗
About this file
- File size
- 2.6 MB (large file)
- File type
No other editions are linked here.
Original file
Log in to download the original file
The download may take up to a minute.