               FOLLOWING CONSTRUCTION / PRIOR TO COUNCIL SIGNING THE PLAN OF SURVEY
                      Certification
               76.    Upon completion of the work a certificate must be issued by an RPEQ certifying that the
                      works have been constructed in accordance with the Operational Works permit.
                      As Constructed Plans and ADAC XML Files (Council)
               77.    Prior to acceptance of civil works to become Council assets “On Maintenance”, satisfactory
                      “As-Constructed” records must be submitted to Council. The bundle of “As Constructed”
                      information shall include:
                      a.      As-Constructed Engineering Drawings. Data is to be submitted in an electronic drawing
                              file format (.dwg), with all plans clearly endorsed “As-Constructed”, along with the
                              accompanying hardcopies (PDFs of the As-Constructed .dwg drawing files), and;
                      b.      ADAC XML Digital File. ADAC File format (ADAC - Asset Design As Constructed)
                              prepared in accordance with industry standards and recorded in “MGA - UTM56 /
                              GDA94” projection.
                              Please Note: Further information and advice relating to the as-constructed drawing
                              presentation, as-constructed survey capture and associated guidelines for preparation
                              of a compliant ADAC XML digital file are available on the webpage titled “As-
                              Constructed Guidelines” and accessible at the Noosa Council Website: Planning &
                              Development / Development Tools & Guidelines / As-Constructed Guidelines.
                      c.      The “As-Constructed” drawings will require certification by a:
                              i.       Qualified experienced Civil Engineer (RPEQ) confirming design intent and
                                       conformance with applicable standards and specifications, along with the
                                       relevant descriptions of assets, services and structures and;
                              ii.      Licensed Surveyor in regard to the cadastral and locational information, levels
                                       and applicable survey datum.
                      d.      The data must be in accordance with Council’s “Planning Scheme Policy 5 –
                              Engineering Design Standards – Roads, Drainage and Earthworks”, and fully detail the
                              levels for all engineering works including but not limited to the drainage network and
                              structures, finished ground and pavement surface levels.
                      e.      Landscaping, including all assets and improvements within parks, open space and road
                              reserves areas are to be shown on an accompanying separate landscape plan
                              (prepared in .dwg file format with accompanying hardcopy PDFs) and include a
                              complaint ADAC XML file. Details of the landscaping and all associated assets and
                              improvements may be included in the ADAC XML digital file prepared for associated
                              civil infrastructure, or alternatively, be provided as a separate ADAC XML digital file
                              containing landscape and asset information only.
                      On Maintenance
               78.    All municipal works must be accepted ‘On Maintenance’ by Council in accordance with
                      Council’s relevant Planning Scheme Policy prior to survey plan sealing. To achieve ‘On
                      Maintenance’, the supervising RPEQ must submit to Council:
                      a.      certification that all works have been undertaken and completed in accordance with the
                              requirements of this Permit
                      b.      as Constructed details in accordance with Council’s Planning Scheme Policy
                      c.      maintenance and operational manuals for all proprietary or site specific devices




                                                                                                       Page 25 of 35
Document Set ID: 24395463
Version: 4, Version Date: 03/02/2026

Used in these records

About this file

File size
957 KB (small file)
File type
PDF

No other editions are linked here.

Original file

Log in to download the original file

Decision Notice OPW20 145 06 (As Published).pdf · 957 KB (small file)

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.