               Preparation of a Preliminary Construction Management Plan
               7.     A preliminary Construction Management Plan must be submitted with the Operational Works
                      application and must address the following:
                      a.      traffic management during all aspects of the construction phase including:
                              i.       a Traffic Management Control Plan in accordance with the Manual of Uniform
                                       Traffic Control Devices (MUTCD) detailing all temporary signage and traffic
                                       control measures prior to construction;
                              i.       maintenance of safe pedestrian access for the areas affected by the works during
                                       and after daily construction has ceased;
                              ii.      proposed fencing to the site during the construction phase of the development;
                              iii.     provision for worker car parking.
                      b.      maintenance and protection of water quality and existing drainage lines through the
                              construction site, through the implementation of appropriate erosion and sediment
                              control measures;
                      c.      works programme identifying key components of the works and their respective
                              durations;
                      d.      establishment of a communication protocol with the general public, adjoining owners,
                              emergency services and local businesses to advise of agreed construction times,
                              impacts on traffic, services and other relevant issues.
                      e.      Include a post out to the local residents and businesses advising of the proposed
                              development, the expected time frames and the site contact details;
                      f.      Include signage in prominent locations on the boundaries of the site advising of the
                              proposed development, the expected time frames and the site contact details;
                      g.      identification of complaint management procedures including:
                              i.       contact details for the on-site manager;
                              ii.      dispute resolution procedures.
                      h.      t is acknowledged that the preliminary Construction Management Plan will be a draft
                              document requiring finalisation upon appointment of the Principal Contractor employed
                              to construct the works and a final document will be required to be submitted at the Pre-
                              Start Meeting for the project.
               Infrastructure Charges
               8.     All developments and/or changes to existing developments may require payment of
                      “Infrastructure Charges” (as applicable) in accordance with Council’s “Charges Resolution”
                      made pursuant to the planning legislation and regulations current at the time of issue. For
                      further       information,     please        refer to https://www.noosa.qld.gov.au/planning-
                      development/development-tools-guidelines/infrastructure-charges
               7.     PROPERTY NOTES

               Not applicable.
               8.     VARIATION APPROVAL DETAILS

               Not applicable.




                                                                                                          Page 9 of 11
Document Set ID: 21417355
Version: 6, Version Date: 18/03/2021                                                                  Print Date: 18 March 2021, 4:14 PM

Log in to download the original (210319_approval.pdf)

Searchable page text hides email addresses. Original files are unchanged and may show email addresses.

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.