23677 DA - Approved plans DECISION NOTICE - Planning Services Notice of Decision [As Published] · 132003.221199

of 59

Check the original when the exact wording matters.

Plans and drawings: the text below has words only, no drawings.

Log in to see the plans as drawn
52.

-li-

The Fire Management Plan shall incorporate ail the relevant requirements of, and be consistent
with, all the other management plans required by this approval.

Sediment and Erosion Control Plan

seqanenaog eee

53.

54.

55.

Detailed staged Sediment and Erosion Control Plans shall be prepared for the site and
imptemented by the applicant. The Plans shall be in accordance with the institution of Engineers
Australia ‘Engineering Guidelines for Queensland Soil and Sediment Control’ (June 1996) and
in particular using Checklist No. 3 from that document. The Sediment and Erosion Control
Plans shall cover all development on site (during the construction, establishment and
operational phases), ecological restoration and remediation works. All recommendations of the
Plans shall be implemented.

The Sediment and Erosion Control Plans shall also ensure the protection of the areas of
retained and enhanced vegetation and shall:

54.1. identify existing erosion problems, and
54.2. specify appropriate remedial actions.

All necessary erosion and sediment control devices shall be incorporated within the
development precincts. The applicant must ensure that any person acting on this permit shall
prevent erosion and sediment export from teaving the site or entering the creek. Site contro!
measures such as silt fencing, controlled gravel access to the site and controlled disposal of
waste, will be necessary.

In this regard plans detailing the methods of controlling erosion and sediment are required to be
submitted to the Council for approval prior to obtaining a Development Permit for Operationa!
Works.

Stormwater and Water Quality Management Plan

56.

57.

58.

59.

A Stormwater and Water Quality Management Plan for the site shall be prepared and
implemented by the applicant prior to the issue of a Development Permit for Operational Works.

The Stormwater and Water Quality Management Plan shall take into account matters specified
in section 19(4) of the Environmental Protection (Water) Policy 1997.

Key water quality objectives to be reflected in the Stormwater and Water Quality Management
Plan are for the protection of aquatic ecosystems in the waterways of the site, areas adjoining
the site, and the receiving waters of Noosa Inlet and the Noosa River. The low nutrient
environment of the site and areas adjoining the site are the key factors in determining
appropriate performance targets. Specifically, water quality objectives shall include the
following performance targets, subject to the constraints of the catchments external to the site:

58.1. Total nitrogen levels — 0.34 mg/l
58.2. Total phosphorous levels — 0.035 mg/l

The Stormwater and Water Quality Management Plan shall comply with and address the
following issues in relation to the construction, establishment and operation phases of the
development:

59.1. Identify all necessary stormwater treatment and water quality devices associated with the
development, which shal! be located within the approved boundaries of the development
areas.

59.2. During the construction phase, monthly water quality monitoring and monitoring after
significant rainfall events (at least two per year) shall be undertaken for:

59.2.1, suspended solids and turbidity,
59.2.2. temperature,

59.2.3. salinity,

59.2.4. total nitrogen,

59.2.5. total phosphorous,

59.2.6. pH,

59.2.7. trash and gross pollutants, and

Used in these records

About this file

File size
4.4 MB (large file)
File type
PDF

No other editions are linked here.

Original file

Log in to download the original file

23677 DA - Approved plans DECISION NOTICE - Planning Services Notice of Decision [As Published].pdf · 4.4 MB (large file)

The download may take up to a minute.

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.