*<.	park rd (12), noosa heads – minor change to development approval conditions (sewer & Stormwater line) – 23643 DA (kc)
	REPORT BY:	Senior Planning Officer – Kerri Coyle

FILE:	23643 DA

APPLICANT:	DesignInc Brisbane

OWNER:	Ron Ure

SITE:	12 Park Road, Noosa Heads described as Lot 54 RP 52918 Parish of Weyba

AREA:	798.5m²

DEVELOPMENT APPROVAL:	Development Permit for Material Change of Use of Premises (Dwelling House)

REFERRAL AGENCY:	Nil

PROPOSAL:	Minor change to development approval conditions (sewer land stormwater line)

DATE OF APPROVAL:	12 August 2004

ZONE:	Detached Housing

FEES PAID:	$685
Introduction
Background
On 12 August 2004 Council granted a Development Permit for a Dwelling House at 12 Park Road, Noosa Heads and decided the representations on 29 October 2004.  Access to the dwelling house is via an easement over an adjoining property from Allambi Rise.  An application for a minor change to the development approval to remove and replace a tree was approved on 9 February 2006.  A copy of the approved site plan is included as Attachment 1.
Proposed Change
This application seeks to change the development approval conditions to permit the sewer and stormwater lines to discharge to Park Road rather than Allambi Rise.  Conditions of the development approval currently require disposal to Allambi Rise to maintain the site’s vegetation and the green backdrop to Hasting Street, main beach.

Assessment
The applicant submits that a trench to accommodate the sewer and stormwater lines is proposed approximately 400mm(+-) deep x 300mm wide from the house down the slope to Park Road.  The applicant submits that the proposal to connect to Park Road is preferred due to the problems and risks associated with the operation of a sewerage pump station on site and a storage tank for stormwater retention.
The applicant has submitted a statement from a geotechnical engineer and an aborist’s report in support of the application.  The arborist’s report concludes that “considering the width and depth of the proposed trench the size of the pipes and that all work is to be carefully carried out manually very little disturbance to the site and vegetation is likely to occur”.  The applicant further submits that “…given the careful attention taken to route this service in a manner to avoid any conflict with the existing trees that this work will not negatively impact upon the continued health, safety or long-term viability of the trees on this site”.
Inspection of the site with Council’s environmental planner finds that the line can be accommodated through the site and along the Park Road frontage without impacting on any significant vegetation, providing the trench is hand dug and an arborist is on site at all times during works.  A line through the site is available clear of any significant trees.
Land Development
Slope Stability
The site is steeply sloped at an average of 35 degrees of a naturally vegetated sand dune formation.
The geotechnical engineers Morrison Geotechnic, have previously investigated the stability of the site in relation to the proposed dwelling and the associated stormwater disposal and sewer connection and made recommendations that were incorporated into the conditions of the current approved permit (Compiled Decision dated 9/02/2006).  These recommendations and conditions remain valid except for Land Development’s Conditions 18 and 20, which require some amendments.
However, it is considered that a Geotechnical Engineer should endorse the engineering plans to be submitted in association with the Development Permit for Operational Works for proposed changes to the sewer connection and the stormwater drainage disposal.  The internal works will be subject to a plumbing and drainage application.
Stormwater Drainage
An approval was given to have the stormwater runoff be collected from the roof in a 1 in 100 year capacity holding tank and piped to an array of perforated pipes suspended beneath the floor.  The discharge from the perforated pipes was to be released onto a filter or geo-textile fabric covered area under the house before dispersing on vegetation located downstream of the building site.
The proposed change is to have the roof stormwater runoff collected on site and discharged to the Park Road kerb line via a fusion welded polyethylene pipe generally accommodated within the same trench of the sewer polyethylene pipe as discussed below.  This manner of disposal is considered acceptable conditional that the trench excavation not exceed 500mm in depth, the filling be carried out using the excavated soil with disturbance to the existing vegetation and the integrity of the slope being kept to the absolute minimum.
Engineering plans showing the details of the proposed drainage system together with supporting calculations prepared by a qualified engineer shall be submitted to Council for approval prior to issuing the Development Permit for Operational Works. The relevant condition should be amended accordingly.
Sewerage Connection
The approval was given for the sewerage from the subject site be directed via a pump up connection to the existing sewerage reticulation main available on Lot 64 RP 52918 (No9 Allambi Rise).
The proposed change for the sewerage disposal system is that it be connected to the sewer system via a fusion welded polyethylene pipeline and a new sewer main constructed along the western boundary lines of Nos 10 and 12 Park Road which to be connected into an existing sewer manhole within Park Road.  This proposal has the advantages of eliminating the reliance on a pumping system, which can be susceptible to failure and require high and frequent maintenance.  Also, the proposed new sewer main along the western boundary of the site can be used to connect the future dwellings on adjoining properties No’s 10 and 14 Park Road.  Council’s Sewerage Section endorse this option and an inspection of the site indicates that the proposed construction of the pipelines (sewer and stormwater as discussed earlier) can be accommodated in a single trench and carried out in a manner that has very limited impact on the vegetation cover and the stability of the sand dune slope.  A conceptual plan of the sewer system is detailed on Attachment 2.
Land Development Conditions that Require Changes
Condition 18:
“Detailed engineering plans of the proposed drainage system together with supporting calculation prepared by a Registered Professional Engineer shall be submitted to Council for approval prior to obtaining a Development Permit for Operational Works.”
Land Development Comment
The condition needs a minor amendment to require the endorsement of a geotechnical engineer for the proposed stormwater disposal down the steep slope to Park Road.
Condition 20:
“The site shall be connected to Council’s existing sewerage reticulation systems over Lot 64 RP 52918 (No9 Allambi Rise) and be constructed in accordance with Council’s standards and requirements at no cost to Council.  Design plans showing the detail of the pumping system and any civil works and/or excavation work associated with it shall be submitted for Council approval and an Operational Works Permit shall be obtained for the proposed sewerage works.”
Land Development Comment
The condition should be amended to give the applicant additional choice of connecting the site to a new sewer line along the western boundary line of the property and to the existing sewer manhole located in Park Road as agreed with Council’s Water and Sewerage Capitol Works Manager.  The proposed works should be clearly outlined in the amended condition and a Development Permit for Operational Works should be required.
Land Development Conclusion
It is considered that the proposed changes to dispose of the sewerage and stormwater directly into the existing systems in Park Road, and the proposed manner of construction will not have any significant or detrimental impact on the stability of the steep slope. It is therefore recommended for approval subject to appropriate amendments to the relevant conditions.
conclusion
The applicant has satisfactorily demonstrated that sewer and stormwater connection to Park Road can be achieved without impacting on significant vegetation.  The application is therefore recommended for approval.
RECOMMENDATION
With regard to a change to development approval conditions of 23643 DA (DesignInc Brisbane) for a Dwelling House at 12 Park Road, Noosa Heads described as Lot 54 on RP 52918, Parish of Weyba, Council:
A.	Approve the change with amendment to Conditions 18 and 20 to read as follows:-
18.	The stormwater drainage disposal via a fusion welded polyethylene pipe shall be discharged into the existing kerb line in Park Road generally in accordance with Drawing no S-OW.02 Issue C dated October 2004 by Whaley Consulting Group.  Detailed engineering plans with supporting calculation prepared by a Registered Professional Engineer shall be submitted to Council for approval prior to obtaining a Development Permit for Operational Works.  The depth of the excavation for trench shall not exceed 500mm, with a maximum width of 300mm and be on an alignment that ensures the damage to the existing vegetation and its root systems is kept to the absolute minimum.  The excavated trench for the pipeline shall be backfilled and stabilised immediately by the excavated materials from the site.  All excavation and backfilling works shall be carried out by hand and be supervised and certified by a geotechnical engineer.
20.	The site shall be connected to Council’s existing sewerage reticulation systems over Lot 64 RP 52918 (No9 Allambi Rise) and be constructed in accordance with Council’s standards and requirements at no cost to Council.  Design plans showing the detail of the pumping system and any civil works and/or excavation work associated with it shall be submitted for Council approval and an Operational Works Permit shall be obtained for the proposed sewerage works.
Alternatively the site may be connected to the existing sewer main in Park Road generally in accordance with Drawing no S-OW.02 Issue C dated October 2004 by Whaley Consulting Group subject to the following requirements.:
20.1	A new sewer main shall be constructed along the western boundary lines of Nos 10 and 12 Park Road (Lots 54 and 55 RP 52918) and connected to the existing sewer manhole (NH01/02/13) in Park Road at no cost to Council and to specifications and an alignment approved by Council’s Water Sewerage Capitol Works Manager,
20.2	The new sewer main shall be provided with connections to future dwelling on the adjoining properties at 10 and 14 Park Road and written permission shall be obtained from the owners of these properties if the new sewer main or any proposed sewer works are to be located within these properties.
20.3	The sewer connection between the dwelling on this property (No 12 Park Road) and the new sewer main shall be constructed of fusion welded polyethylene pipe with the excavated trench for the pipeline being backfilled and stabilised immediately by the excavated materials from the site. The depth of the excavation shall not exceed 500mm, with a maximum width of 300mm and be on an alignment that ensures the damage to the existing vegetation and its root systems is kept to the absolute minimum.  All excavation and backfilling works shall be carried out by hand and be supervised and certified by a geotechnical engineer.
20.3	The sewer connection and stormwater disposal shall be accommodated in a single trench to minimise disturbance on the site.
20.4	A Development Permit for Operational Works shall be required and all submitted plans shall be prepared by a Registered Professional Engineer Queensland and certified by a Geotechnical Engineer in relation to the impact of the works on the stability of the sand dune slope.
B.	Include the following additional condition:-
1.	The stormwater disposal and sewer connection shall be undertaken in accordance with the Arborist’s Advice Report prepared by John Mullholland & Associates and dated March 2006 and the following requirements:
 1.1	The route for the service trench shall be a minimum of 1.5 metres clear of all trees and shrubs, unless otherwise agreed to by the Manager, Land Use.
1.2	An arborist shall be on site all times supervising the works being undertaken.
1.3	Prior to commencing any works, the route for the service trench shall be pegged and inspected by Council.
1.4	Prior to excavation existing mulch/leaf cover material over proposed trench shall be raked back and stockpiled for covering of trench area after completion.
1.5	Works shall be undertaken in a progressive manner and route reinstated as works progress.
1.6	Uphill anchor roots of trees shall not be disturbed.
1.7	All works shall be carried out by hand excavation other then the sewer trench under existing road pavement.
1.8	All excavated material shall be placed on a ‘tarpaulin’ or the like laid immediately adjacent to the proposed trench.
1.9	Excavated material shall be used as bedding and backfilling of trench.
2.0	Where works disturb the understorey vegetation, rehabilitation works shall be undertaken to the reasonable satisfaction of Manager, Land Use.
C.	Issue a Compiled Decision Notice.
(Index Application No. 23643 DA – (po2))
Directorates/Sections Consulted:
	Business
Corporate Services	X	Community Services	x	Environ & Planning

Aquatic Centre
Financial Services
Art Gallery
Building Services

Building Certific.Group
Information Services
Community Dev.
Environmental Services

Child Care Centre
Legal Services
Events	x	Land Development

Council Laboratory
Planning & Support
Environmental Health	x	Land Use

Leisure Centre
Revenue Services
Library
Plumbing Services

Water & Sewerage

Public Order & Safety
Strategic Planning

Recreational Services

Respite Centre

Youth

Works
Human Resources
Exec. & Secretariat

Design

Arts & Heritage Board

Works Administration

Economic Board

Works Operations

Environment Board

Works Planning

Social Board

Tourism Board

ATTACHMENT 1

ATTACHMENT 2

Environment & Planning Committee Reports 04/08/06 - Ordinary Meeting 17/08/06	1

Used in these records

About this file

File size
940 KB (small file)
File type
DOC

No other editions are linked here.

Original file

Log in to download the original file

2006-08-09 E&P - 23643 DA - Minor Change to sewer & stormwater - Park Rd, Noosa Heads.doc · 940 KB (small file)

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.