5.     Digital detailed designs including drawings, calculations, specifications and a schedule of works, shall be
       submitted with any application for a Development Permit for Operational Works in respect of roadworks
       and stormwater drainage works. In this regard a DXF/DWG file on GDA94 zone 56 grid of the proposed
       cadastre layout is to be submitted in conjunction with any application for Operational Works. The design
       shall be in accordance with Council’s Planning Scheme Policy PSP05 – Engineering Design Standards –
       Roads, Drainage and Earthworks.

6.     To facilitate production of As Constructed drawings it is suggested that all design drawings are submitted
       in the Asset Design and As Constructed (ADAC) digital format. (Guidelines on the use of ADAC are
       available at www.adac.com.au).

7.     Prior to the commencement of the development, a plumbing assessment must be obtained from Noosa
       Council’s Plumbing Services Section in accordance with the Plumbing & Drainage Act 2002 (as
       applicable).

8.     The requirements of the Environmental Protection Amendment Regulation (No. 2) 1999 and Local Law
       No. 12, prevents a builder or building contractor carrying out building work on a building site in a way that
       makes or causes audible noise to be made from the building work:-

       8.1.   On a Sunday or public holiday, at any time; or

       8.2.   On a Saturday or a business day, before 7.00am or after 6.30pm.
       A maximum penalty of $1,500 applies to an offence under this legislation.
9.     Pursuant to the Building and Construction Industry (Portable Long Service Leave) 1991 Act if the cost of
       operational works exceeds $80,000, then a portable long service leave levy is required to be paid. In
       accordance with Section 77.(1) of the Act, Council is required to sight the approved form issued by the
       Building and Construction Industry (Portable Long Service Leave) Authority that confirms that the
       requirements of the Act have been satisfied. A statutory declaration outlining the cost of the operational
       works must be submitted to Council with the lodgement of any application for operational works over the
       site.

10.    The plans for the proposed building work have not been assessed for compliance with the requirements of
       the Building Code of Australia as they relate to people with disabilities. Your attention is drawn to the
       matter that either or both the Disability Discrimination Act 1992 (commonwealth) and the Anti-
       Discrimination Act 1991(Queensland) may impact on the proposed building work.

11.    Noosa Council recommends that the following matters be considered to address equitable access and
       facilities in the building:-
       A.     The building and environs should be designed to meet the requirements of the Human Rights and
              Equal Opportunity Commission “Advisory Notes on Access to Premises” and AS1428.2;

              Applicants should be aware that a “Disability Standard on Access to Premises is being developed
              and most likely will result in changes to the Building Code of Australia;

              Any services and facilities in the building complex must allow independent, dignified and equitable
              use of the services and facilities for all people.


12.    This proposal has not been assessed in relation to the spread of fire between properties / buildings. It is
       the building certifiers responsibility to assess the requirements for fire services, fire separation and
       appropriate methods of construction as part of the building works approval process. Referral to the
       Queensland Fire and Rescue Service (QFRS) may be required as part of the Building Approval process.

13.    The development should be undertaken and operated in a manner that causes no detrimental effect upon
       the amenity of the neighbourhood by reason of the creation of excessive noise, lighting, air-borne
       hazards, atmospheric pollutants (including dust or odours) nuisance or any other emissions in accordance
       with the nuisance provisions of the Environmental Protection Regulation 1998 or Council’s Local Law No.
       12 – Control of Nuisances.

14.    Noise from building works associated with commercial and or industrial development should comply with
       the following –

       14.1. Limited to between 7:00am to 6:30pm Monday to Saturday.




MSOffice c:\docume~1\shesse\locals~1\temp\bcl technologies\easypdf 5\@bcl@b00795bc\@[email protected]

Used in these records

About this file

File size
61 KB (small file)
File type
PDF

No other editions are linked here.

Original file

Log in to download the original file

SUPERSEDED Decision Notice - 010.2007.00000012.001 [As Published].pdf · 61 KB (small file)

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.