Delegated Report - Code - Planning RAL24 0014 - AS PUBLISHED · RAL24/0014
i. a Traffic Management Control Plan in accordance with the Manual of Uniform
Traffic Control Devices (MUTCD) detailing all temporary signage and traffic
control measures prior to construction.
ii. maintenance of safe vehicle and pedestrian access for the areas affected by the
works during and after daily construction has ceased.
iii. proposed fencing to the site during the construction phase of the development.
iv. approval of the Traffic Management Control Plan by the Department of Transport
and Main Roads (DTMR) for any works on State controlled roads.
v. provision for worker car parking.
b. maintenance and protection of water quality and existing drainage lines through the
construction site, through the implementation of appropriate erosion and sediment
control measures
c. works programme identifying key components of the works and their respective
durations
d. establishment of a communication protocol with the general public, adjoining owners,
emergency services and local businesses to advise of agreed construction times,
impacts on traffic, services and other relevant issues
e. Include a post out to the local residents and businesses advising of the proposed
development, the expected time frames and the site contact details.
f. Include signage in prominent locations on the boundaries of the site advising of the
proposed development, the expected time frames and the site contact details.
g. identification of complaint management procedures including:
i. contact details for the on-site manager
ii. dispute resolution procedures
h. details on the location of external fill/dump sites/sources, the haulage route, type of
vehicle to be utilised during filling operations and frequency of usage. NB any damage
to the existing road system as a result of haulage operations shall be fully repaired at
the applicant’s expense
i. it is acknowledged that the preliminary Construction Management Plan will be a draft
document requiring finalisation upon appointment of the Principal Contractor employed
to construct the works and a final document will be required to be submitted at the Pre-
Start Meeting for the project.
8. PROPERTY NOTES
The following property notes will be placed against the subject property in Council’s property record
system:
RAL24/0014 - Property Access
1. The following notation applies to approved Lot 2 and Lot 100:
Private Certifiers, owners and prospective purchasers are notified that access to the property
has not been constructed and special requirements apply to this parcel of land. Contact
Council's Planning Department for details.
RAL24/0014 - Services
2. The following notation applies to approved Lot 2 and Lot 100:
Private Certifiers, owners and prospective purchasers are notified that service connections
(water, sewer, electricity and telecommunications) to the property have not been constructed
and special requirements apply to this parcel of land. Contact Council's Planning Department
for details.
Page 11 of 12
Document Set ID: 23148031
Version: 5, Version Date: 29/08/2024
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalUsed in these records
Delegated Report - Code - Planning RAL24 0014 - AS PUBLISHEDRelated documentApplication case desk ↗
About this file
- File size
- 8.2 MB (large file)
- File type
No other editions are linked here.
Original file
Log in to download the original file
The download may take up to a minute.