GENERAL COMMITTEE MEETING                                                           17 MARCH 2025


8.4     POMONA PLACE PLAN


Author            Principal Strategic Planner, Michelle Tucker
                  Strategy & Sustainability | Strategy and Environment
Index             Subject 41.14 Place Making
Attachments       1.   ATTACHMENT 1 Pomona Place Plan_Final
                  2.   ATTACHMENT 2 Response Table Draft Pomona Place Plan
                       Submissions


EXECUTIVE SUMMARY
The Pomona Place Program commenced in June 2023 after Pomona village was endorsed by
Council as the location for a Placemaking pilot in February 2023. This report presents the final
Pomona Place Plan (Attachment 1) for endorsement by Council. The Pomona Place Plan (Place
Plan) has been prepared in partnership with the Pomona community and is the result of three rounds
of community engagement.

The first round of engagement was undertaken from 6 August till 9 October 2023 to determine the
vison and values of the community as well as asking the community what made Pomona a great
place to live and how we could make it even better. Over 500 people participated in the engagement
through a range of activities with 250 people completing the community survey identifying a diverse
range of ideas for potential actions in the Pomona Place Plan. Two workshops were also held with
community organisations and participated in a walk on country with Kabi Kabi Peoples Aboriginal
Corporation (KKPAC). The Pomona Place Plan Engagement Summary Report was endorsed by
Council at its meeting in December 2023.

A second round of community engagement was undertaken from 13 May until 23 June, where the
community were asked to prioritise actions from round one engagement and to confirm the vision
statement. Over 240 survey responses were received and approximately 60 participants attended
pop-ups. Separate workshops were also undertaken with KKPAC and Pomona community
organisations.

The draft Pomona Place Plan plan was then prepared and underwent a third round of community
engagement from October 18 until November 17 for a period of four weeks. The purpose of this
round of engagement was to present the Draft Pomona Place Plan to the community to confirm the
vison and actions reflected their aspirations, and to enable community members to nominate to be
involved in specific community led actions. Council received 40 online survey submissions and an
additional 12 submissions via email. A workshop was also held with community organisations to
discuss implementation approaches.

The final Pomona Place Plan (Attachment 1) has been developed based on community input and
responses from all three rounds of community consultation and has been amended considering
submissions. The majority of changes focus on providing further clarity, detail, functionality and
readability of the plan and strengthening the issue of quarry trucks moving through the village.

The purpose and benefit of the pilot was to test ideas and processes both within the organisation as
well as develop a collaborative community based Place Plan in partnership with the community for
the village of Pomona. An Evaluation report is currently being prepared with input from the project
team, community and within the organisation, and will provide useful insight for future place planning
processes for the organisation moving forward should Council choose to continue the Noosa Place
Program into the future. This includes an assessment against the key aims of the pilot as well as
Full text of the other 11 pages

Page 2

GENERAL COMMITTEE MEETING                                                           17 MARCH 2025


lessons learnt within the organisation and with the community. This will continue to be developed as
we move into implementation and reported back to council in the coming months.

RECOMMENDATION
That Council note the report by the Principal Strategic Planner to the General Committee meeting
dated 17 March 2025 regarding the Pomona Place Plan Pilot; and
A. Approve the final Pomona Place Plan in Attachment 1;
B. Note the changes to the Draft Pomona Place Plan as a result of submissions in Attachment 2;
C. Approve the preparation of an Implementation Plan for actions designated as short term in the
   Pomona Place Plan; and
D. Note an Evaluation report will be provided to Council in the coming months once the Place plan
   has been endorsed and implementation has commenced with community.


REPORT
Place-based programs seek to deliver sustainable social, economic and environmental benefits
through place-based partnerships and program interventions customised to a specific location and
the needs of its different communities. It is critical that a placed based approach truly reflects the
uniqueness of different localities and communities, and in order to achieve this, it involves multiple
stakeholders and takes a wholistic approach. A place-based approach involves looking at, listening
to, and asking questions of the people who live, work and play in a particular place to discover the
needs and aspirations of those people and create a common vision.

Placemaking Pilot
The Noosa Place Program and place making pilot was endorsed by Council to commence in Pomona
on 13 February 2023. Consultants Cred and Archipelago were engaged in June 2023 to assist the
project team to design and deliver the Pomona Place pilot. The purpose and role of the pilot was to
undertake an place based approach in one of our towns or villages to prove the viability and
effectiveness of a place based approach. The pilot enables Council to manage the risk of a new
approach and identify opportunities and improvements prior to undertaking further place-based
programs across the Shire.

One of the key aspects of the pilot is to evolve the organisation to be able to deliver place-based
initiatives and service delivery which requires increasing skills, knowledge and understanding of
placemaking by staff across the organisation. The pilot location was therefore a place with key
strengths but had some aspects that could benefit from a place-based approach. This allowed staff
to increase their skills, the organisation to adapt, and community to realise benefits.

The Pomona Place Plan

The Pomona Place Plan:
•   Identifies the characteristics and values that make Pomona special
•   Establishes a shared vision
•   Outlines actions for delivery by Council, community and other stakeholders over the next 10 plus
    years.

The final Plan is at Attachment 1 and comprises the following components:
•   Introduction
•   Part A - Background

Page 3

GENERAL COMMITTEE MEETING                                                            17 MARCH 2025


•   Part B - Vision + Actions
•   Part C - Implementation Plan
•   Appendix A - Actions by Timeframe
•   Appendix B - List of all community actions
Part A - Background
This part of the plan includes the background information to provide the local context about the
village and people of Pomona. It also includes information about the placemaking process, how the
plan was developed including community engagement and key findings that have helped shape the
Plan.

Part B - Vison and Actions.
This section of the plan presents the vision for Pomona, as well as the themed community actions
for how to achieve it. The vision, themes and actions were derived from community and stakeholder
input. There is also a list of advocacy actions where the community and council can work together
with other stakeholders such as the state government.

Part B also includes a map indicating where some actions are located across the village. The
mapping of actions shows focal points for future initiatives in key locations within Pomona, for
example, Stan Topper Park, Cooroora Creek Park, Station Street, Factory Street, etc. Some actions
also relate to multiple areas throughout town including on the edges of the village (for example,
Reserve Street and Summit Road), and connections to neighbouring areas like Cooran and Cooroy.

Part C - Implementation
The implementation of the Place Actions in Part B of the Plan will occur over many years aligned
with the priority timeframes listed against each action. A list of all the actions in Part B are ordered
in timeframe delivery (Short, Medium and Long Term) located in Appendix A and will help form the
basis of the Implementation Plan. Delivery of these actions will be dependent on potential funding,
ongoing resources from both the community and Council as well as other stakeholders. This part of
the Plan also considers ongoing monitoring and evaluation processes as the plan is implemented.

Community and Stakeholder Engagement
Placemaking is a collaborative process working in partnership with the community and is focused on
building community capacity. It is about delivering social, economic and environmental benefits
aligned with community values to meet its unique needs and aspirations. To develop a place plan in
partnership with the community it is essential to acknowledge they are experts of their 'place' and
we need to engage and listen to gain an understanding of what they value about where they live,
what they hope for the future, and how they want to make their place an even better place to live.
Partnering with the community along the journey is imperative to ensuring the placemaking process
is successful and sustainable in the longer term as placemaking is an ongoing process that evolves
overtime.

In line with the above three rounds of community engagement were undertaken in the preparation
of the Pomona Place Plan.

An Engagement Summary Report was presented to Council in December 2023 and detailed the
outcomes of the first round of consultation which included a program of broad community
consultation undertaken to support the preparation of the Pomona Place Plan. From the results of
round one over 110 potential actions and a vision statement were drafted.

Round two engagement was undertaken from 13 May until 23 June 2024 where the community were
asked to test the vision statement and select their top three actions across 12 themes to help
prioritise actions for inclusion in the draft Pomona Place Plan. Over 240 responses were received
on the survey as well approximately 60 participants attended pop-ups. Workshops were also held
with KKPAC and key community organisations on the draft vision and actions.

Page 4

GENERAL COMMITTEE MEETING                                                         17 MARCH 2025



The Draft Pomona Place plan was then drafted based on community responses from both rounds of
engagement. It was presented to Council on 14 October 2024 for the third and final round of
engagement. The purpose of round three engagement was to confirm with the community we have
understood them and confirm the vison and the actions reflect their aspirations. It also opened
discussion with the community about who would be interested in community led actions and the best
process for community led implementation of the Place Plan once finalised and endorsed by
Council.

Round three engagement included a range of activities including a post card mail out, online survey,
community pop-up and a community organisation workshop. Further details of all the activities
undertaken are described under the "external Consultation" section of this report. Council received
40 online survey submissions and an additional 12 submissions via email giving a total of 52
submissions and spoke to approximately 50 people at the pop-up at Jo Bazzo Park. Responses to
comments raised in the submissions are in Attachment 2 of this report, some of which have resulted
in changes to the Place Plan.

Survey results
Of the participants, 62.9 % lived in Pomona, with 11.4 % living in nearby Pinbarren and 5.7% in Kin
Kin. The majority (over 85 %) where resident ratepayers, followed by Business owners and workers.




The Survey asked the following four questions and responses are below.

Question 1 - Asked the community to what extent they agreed with the following questions about
the Draft Pomona pace Plan. As can be seen from the results below the majority of people who
participated in the survey agree or somewhat agree with the community vision in the plan; that the
draft actions align with what the community said was important to them and that the plan clearly
showed where the community can lead and where council may assist.

The community vison for the future of Pomona reflects what I want to see for my community.

Page 5

GENERAL COMMITTEE MEETING                                                       17 MARCH 2025




The draft actions align well with what our community said is important to them.




The draft actions clearly show what the community can lead on and where Council may
assist.




Question 2 - The next question was an open question, Noting the draft Place Plan in based on
community input, would you like to say anything specific about the actions? Do you think anything
has been missed, misinterpreted or needs to be changed? The responses to this question along with
the additional emailed submissions are in Attachment 2 and have been considered with some
recommended amendments to the draft plan. Amendments to the plan are discussed under
Summary of Changes to the Draft Pomona Place Plan section of this report.

Page 6

GENERAL COMMITTEE MEETING                                                             17 MARCH 2025



Question 3 - Asked Would you like to get involved in bringing these actions to life, together with
other people in your community? If so, please provide your name and preferred contact email below
for us to get in contact with you. We received 19 responses from community members interested in
being involved in implementing the plan which is very encouraging. These people will be contacted
as part of the implementation process in conjunction with community groups to consider the most
appropriate structure for community delivering actions in the plan.

Question 4 - Asked for feedback about the process given it was the first Place Plan for Noosa and
a pilot. As this is the first Place Plan developed for the Shire, we would love to know if you think this
was a good process and, where we might improve in future. Please select the emoji below and
provide more details in the next question, if you wish to. As can be seen below the majority of people
who completed the survey were very happy or happy with the process, with approximately 6 people
unhappy or very unhappy. This information and feedback will assist in developing the Evaluation
report.




Question 5 - Asked: If you would like to provide more detailed feedback on the Place Plan process,
please let us know here or provide your contact details and we would be delighted to get in touch
with you to find out more. 16 responses were received and will be used to inform the Place Pilot
Evaluation Report. Some examples of comments included good process but lengthy, needing to
consider Pomona's connections to other places and broader socio-economic issues, wider
promotion of the engagement activities, happy the plan is happening, supportive of the community
involvement in the process, need to capture all parts of the community in engagement, providing
more information about placemaking to the community up front, the process relies on community
heavily to get key messaging out.

Summary of changes to the Draft Pomona Place Plan
As a result of submissions, a number of changes have been made to the Pomona Place Plan. The
changes respond to community feedback and provide more clarity and functionality to the plan. Key
changes include:
•   Strengthening the linkages between actions related to heavy vehicle movement through town
    such as quarry trucks and providing further representation of this issue throughout the plan.

Page 7

GENERAL COMMITTEE MEETING                                                             17 MARCH 2025


•   Providing further clarity around what a Place Plan includes and what it doesn't in the
    introduction.
•   Amending the vision statement to include the word "Character".
•   Including more community actions captured in Appendix B for future consideration.
•   Amending various actions to provide more clarity and/or direction.
•   Amending the Action map to include an additional pedestrian crossing on Hill Street at the
    entrance to Cooroora Creek Park and extended the dedicated cycle and walkway linkages
    through to Songbird estate.
•   Improving overall readability and clarification of the plan and what is within the scope and outside
    the scope of a Place Plan. eg The plan should not replicate other council plans and strategies
    but rather compliment them.
•   Providing more details and clarity in Part C - Implementation of the Plan.
Implementation
Submissions provided constructive advice in relation to the future implementation of the plan. Council
officers will prepare a more detailed implementation plan for the next 2 years (Short term Actions),
which will include consideration of key performance indicators where relevant to help track and
monitor the implementation of the plan. Appendix A provides a list of the Actions based on timing
and will form the basis of this monitoring program. The implementation plan will be prepared with
community who have committed to delivering actions in the plan and will be reported annually to
monitor progress over the lifetime of the plan. The Place Plan will be reviewed every 5 years with
the community to ensure priority actions still remain relevant over the life of the Plan. Part C of the
Place Plan has been amended to provide further clarity and detail on the future implementation of
the Plan.

Council Officers will continue to work with community and community organisations to support the
implementation of the actions in the Place Plan.

Options for a Town Team have been provided as part of the community consultation, a Town team
is a community led initiative, further information is outlined in the Place Plan. The establishment of
town teams needs to be a decision for the community. Pomona has a number of well run community
organisations which already provide a range of programs, services and events in the village. The
Place Plan builds upon these with actions that have been identified by the community to make it an
even better place to live.

As part of the implementation process opportunities for the delivery of some more quick win projects
to celebrate the launch of the Plan will be identified. Ideas for quick wins will be taken from community
ideas that have been provided throughout the engagement process and/or documented in the Place
Plan with opportunities to work in collaboration with community as part of the process.

The first round of Quick wins were undertaken early 2024. These included:
•   installing new park furniture and replacing old park with timber top chairs and tables more in
    keeping with the character of the village in parks throughout the village;
•   restoring and cleaning the BBQ area in Stan Topper Park; and
•   installing sandstone block seating and fixing the light at the basketball half court to make it more
    usable for the community.
Below is a list of the short term actions (1-2 years) that are currently being actioned or can be
actioned now by community, as well as Council proposed actions awaiting external funding
approvals and/or are subject to councils upcoming budget considerations for 25/26 financial year.
These are listed in Table 2 below against the relevant action in the Place Plan:

Page 8

GENERAL COMMITTEE MEETING                                                        17 MARCH 2025



Table 2 :Short Term Actions
PLACE PLAN ACTION                          IMPLENTATION RESPONSE
                                           Pomona and District Community House have a
1.4 Community Garden and Bush Tucker
                                           community and Bush tucker garden. Community can
Garden
                                           volunteer at the community garden.
                                           Consideration of the location of and the installation of
                                           new outdoor exercise equipment. *
                                           Undertake an audit/review of Stan Topper Park
1.3 Undertake improvements to key parks    focused on understanding the condition and
                                           functionality of the existing spaces and street
                                           furniture and identify current and future needs.
                                           *Subject to consideration in 25/26 Council Budget
                                           Community members are able to install a verge
1.5 Install a garden on your verge
                                           garden in accordance with Council's Verge policy.
                                           Council is proceeding with the missing links
                                           pedestrian links between Noosa District High School
                                           (Pomona campus) and the village centre in its
                                           2024/25 budget. This will provide a link to the village
                                           via Page Court and Pavilion Street. Council is also
2.1 Dedicated cycle and walkways
                                           seeking a grant under the QLD government walking
                                           program to revise the walking network maps for
                                           Pomona and provide a gateway for future State
                                           Government funding. Council is yet to receive any
                                           information on the outcome of this.
                                           Continue working with existing community groups to
3.1 Waterway Protection                    help with weed management and revegetation along
                                           Cooroora Creek.
                                           Council has community grants available (Climate
                                           Change Response Grants) that would enable
                                           community members to lead this action. In addition,
                                           council's Land for Wildlife and Private Land
3.3 Environmental Education                Conservation programs in this area has resulted in
                                           good uptake to larger land parcels. Council can ramp
                                           up the focus on the urban program to have these
                                           programs reach further into the community within
                                           existing budgets.
                                           Promote local information guide for new residents
                                           “Community Compass” developed by Pomona and
                                           District Community House
4.1 Promote Community Organisations        Provide support and training for community
                                           organisations to adapt to changing patterns in
                                           volunteering via community development
                                           programming.
                                           Council currently provides support and opportunities
4.4 Financial support for not-for-profit
                                           for non-profit organisations to better access financial
community groups
                                           support and grants.

Page 9

GENERAL COMMITTEE MEETING                                                            17 MARCH 2025


                                              Council’s Public Art Policy is soon to be considered
5.3 Public Art                                by council and will include funding through major
                                              capital works where the project qualifies.
                                              Economic Development Grants are available to fund
6.2 Diverse shops and services                the preparation of a business audit of the village to
                                              assess the diversity and mix of business.
                                              Strategy and sustainability Branch to commence a
A1 Character and Heritage Policy              Heritage and Character Amendment to the Noosa
                                              Plan 2020 once current amendments finalised.
                                              Council will continue to monitor the issues
A2 Truck Movements through town
                                              surrounding heavy vehicles.
                                              Successful lobbying by community secured funding
A4 Pedestrian Crossings
                                              for pedestrian crossing on Factory Street.
                                              Council currently have a very strong partnership with
                                              QPWS and Kabi Kabi Land and Sea Rangers to
A5 Land care and management                   incorporate traditional custodian practices into our
                                              management. This has included shared programs for
                                              cool burning and collaborating on ecological burning.
                                              Council are currently working with TMR on the
A8 Public Transport Improvements              Northern Sunshine Coast Public Transport Strategy
                                              which is expected to be completed this year.

Additional quick win projects are also being considered as part of the final endorsement and launch
of the Place Plan with additional funds being sort for consideration through the 25/26 council budget
for implementation.

The Shire-wide Liveability survey will also form part of the monitoring and evaluation process and
will be conducted every 4-5 years. The results of the Liveability Survey will provide high level data
into over 50 attributes that contribute to liveability across individual towns and villages across the
Shire and provide a Liveability Index rating for each location.

Pilot Evaluation Report
As stated previously, the purpose of having a pilot project is to help develop learnings and
understanding about how we can improve the process moving forward. The project team have been
collating learnings along the way as part of this process both externally with community and internally
within the organisation. As part of the community survey on the Draft Place Plan, we asked the
community to provide some evaluation feedback on the process so far with an option to follow up
further to gain further understanding and learnings to incorporate into a final evaluation report
(Question 5 above). The Evaluation Report is currently being developed and will be reported back
to council in the coming months once the plan commences implementation phase to capture any
additional learnings.

Next Steps
With the endorsement of the final Pomona Place Plan the following steps will be undertaken:
1. Prepare an implementation plan for the Short term actions and continue to engage and work with
   community and other key stakeholders to implement actions in the Place Plan including quick
   win projects.
2. Finalise the Pilot Evaluation Report and report back to Council.

Page 10

GENERAL COMMITTEE MEETING                                                           17 MARCH 2025


3. Continue with embedding the place based approach organisational policy and framework to build
   understanding, knowledge and skills around place planning and delivering a place approach
   across the organisation.

Link to Corporate Plan

Theme No. 4 - Future
This theme is focused on our future, strengthening our relationship with First Nations peoples and to
ensure our community is prepared and resilient to change. A focus on youth, climate resilience and
adaptation, sense of place and destination management.
Objective 4.5
Implement a place-based approach to working with individual towns/villages and address their
specific needs within a whole-of-Council framework.
Signature Project
Implement Noosa Place making Program


Previous Council Consideration
Ordinary Meeting Minutes, 17 October 2024, Item 6.2, Page 11
That Council note the report by the Principal Strategic Planner to the General Committee
meeting dated 14 October 2024 regarding Draft Pomona Place Plan; and
A. Endorse the Draft Pomona Place Plan in Attachment 1 for its third and final round of
   community consultation with following amendments to the Draft Pomona Place Plan under Item
   3 Environment conservation and sustainable living theme (page 28):
1. Under Action 3.1 "Waterway protection" amend to read: "Develop a program of
   volunteer events to support waterway health and restoration. This can include
   extending rehabilitation planting along the Cooroora Creek riparian area along
   Rifle Street to improve the area and to enhance the linkage through to the Tuchekoi
   National Park"; and
2. Under Action 3.1 "Who is involved" amend Council's role to: "Deliver and Facilitate"
B. Commence community consultation from the 18 October until the 17 November 2024.

Ordinary Meeting Minutes, 14 December 2023, Item 8.2, Page 9
That Council note the report by the Principal Strategic Planner to the Planning & Environment
Committee Meeting dated 5 December 2023 regarding the Pomona Place Pilot community
engagement outcomes and next steps and:
A. Endorse the Pomona Place Plan Engagement Summary Report 2023 as attached to this report;
B. Make this engagement summary report available to the public via Your Say webpage;
C. Note the proposed next steps and timing for the preparation of the Pomona Place Plan in 2024.

Ordinary Meeting Minutes, 16 February 2023, Item 3, Page 15
That Council note the report by the Principal Strategic Planner to the General Committee Meeting
dated 13 February 2023 and
A. Approve Pomona to be the location for the first Place Program pilot and;
B. Approve Kin Kin then Tewantin as the next two priorities for the Placemaking program.

Finance
The purpose of the pilot is to test the viability of the place program both within the organisation as
well as in the community. The success of the pilot will determine the future roll out of the program
across the Shire over a 10 year period. This will have financial implications for Council over the
longer term but will be factored into future planning and budget cycles. The current project budget

Page 11

GENERAL COMMITTEE MEETING                                                          17 MARCH 2025


includes the potential for some early win projects as part of the Pomona pilot project. The future
capital projects that Council has responsibility for will be included in the forward capital works
program and the review of the Local Government Infrastructure Plan for future consideration. Other
actions will be incorporated into operational/business planning for responsible departments and
branches for implementation.

Risk & Opportunities
The Place Program aligns with several key Council Strategies and Plans including the Corporate
and Operational Plan, Cultural plan and the Noosa Plan 2020. Key risks identified as part of the
place program include community expectations in terms of what ultimately will be the outcomes of a
place program. Other risks include participation, resourcing and capacity for Council in partnership
with the community and key stakeholders to deliver an integrated Place Program. Key to managing
these risks is effective and clear communication, consultation, and program management.

Human Rights
Human Rights Compatibility Statement
In developing this Report, the subject matter has been considered in accordance with the
requirements of the Queensland Human Rights Act 2019. It is considered that the subject matter
does not conflict with any human rights and supports a human rights approach to decision making
by Council. Council representatives will endeavour to act and make decisions under this report in a
manner that is compatible with human rights. This report should be read in conjunction with
Council’s Human Rights Policy.


Consultation
External Consultation - Community & Stakeholder
As detailed in the above report, extensive community and stakeholder consultation was undertaken
as part of the Pomona Place pilot over three rounds. Round one included a diverse range of activities
and stakeholder workshops, walk shops, pop-ups, on line and hard copy surveys, love letters and
urban sketching which have provided different perspectives and multi layered responses to give a
very in depth understanding of the issues, opportunities and challenges for the community of
Pomona. Round two engagement included an additional survey, pop-ups in community and
community stakeholder workshops to prioritise the actions as a result of round one as well as test
the draft vision for inclusion in the Draft Pomona Pace Plan.

Round three engagement was to present the Draft Pomona Place Plan to the community; to make
sure we understood the community and the actions reflect their aspirations based on the previous
consultation results and to enable those in the community to nominate to be involved in any specific
community led actions. Engagement also sought to discuss with community the best process for
community led implementation of the Place Plan once endorsed.

Round three engagement was undertaken from Friday 18 October to Sunday November 17, 2024
for a period of four weeks. Activities for round three included the following:
• Survey, a copy of the Draft Plan and supporting information on YourSay Noosa
• Postcard mail out to residents in Pomona with QR code to access the survey on YourSay Noosa.
• Posters at key locations around the village.
• Community Pop-up in Joe Bazzo park Saturday 2 November
• Social and print media
• Press release
• Emails to community members that have identified to be kept up to date with the project.
• Stakeholder Engagement including Community Organisations

The results of round three consultation are provided in the above report and Attachment 2.

Page 12

GENERAL COMMITTEE MEETING                                                                17 MARCH 2025



Internal Consultation
Effective communication and collaboration are key to the success of the Place Program. The
development of the Place Program has involved multiple departments across Council, particularly in
the establishment of and representation on the Place internal working group and a Project Steering
Committee. This group provides guidance and helps to develop and foster a good understanding of
the Place Program across the organisation. Staff and Councillors have also been involved and
participated in a range of community engagement activities throughout the consultation process.
Councillors were also briefed on the detail outcomes of the final consultation and contents of the
Pomona Place Plan in a workshop.

An organisational Place Based Approach Policy with supporting Guidelines and Embedding Action
Plan has been developed to provide direction and clear understanding across the organisation. The
Embedding action plan also includes tailored training opportunities for staff to building understanding
across the organisation.

Departments consulted:
     Office of the CEO, Mayor &             Community Services               Corporate Services
             Councillors
 x    Mayor & Councillors             x    Director                        Director
      Chief Executive Officer              Community Development           Financial Services
      Executive Officers              x    Sport & Active Lifestyles       Fleet
 x    Community Engagement            x    Arts & Culture                  Revenue Services
      People & Culture                     Community Connection            ICT
 x    Governance                           Customer Experience             Procurement

                                                                           Commercial Property

      Strategy & Environment              Development & Regulation         Infrastructure Services
 x    Director                             Director                    x   Director
 x    Strategy & Sustainability            Development Assessment      x   Infrastructure Planning, Design
                                                                           and Delivery
 x    Economic Development        &        Local Laws                  x   Civil and Asset operations
      Destination Management
 x    Environmental Services               Environmental Health            Waste
      Innovation & Digital Hub             Building & Plumbing             Building & Facilities
                                      x    Property / Permits          x   Disaster Management

Used in these records

About this file

File size
415 KB (small file)
File type
PDF

No other editions are linked here.

Original file

Log in to download the original file

Report.pdf · 415 KB (small file)

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.