OPERATIONAL MANAGEMENT
AND MAINTENANCE PLAN




Noosa Medihub
Eenie Creek Road Noosaville




                                           Prepared By:
                              MPN CONSULTING PTY LTD
                                               Level 5
                                     39 Sherwood Road
                                             Toowong
                                           Queensland
                                      4066 • Australia
Log in to download the original file

25-11-22 Operational Management and Maintenance Plan_Issue A.pdf · 3.5 MB (large file)

The download may take up to a minute.

Full text of the other 24 pages

Page 2

25 November 2022



REVISION STATUS

MPN Reference No:                              8662

Client:                                        Stockwell Developments Pty Ltd

Site Address:                                  28 Eenie Creek Road Noosaville

Report Title:                                  Operational Management & Maintenance Plan




DOCUMENT CONTROL

Version          Date                 Author                       Reviewer              Approved   RPEQ
Issue A          25/11/2022           Lachlan                      Lachlan Stephenson               16903
                                      Stephenson




Excellence with Economy in Engineering                                                                      1
https://mpncnetau.sharepoint.com/sites/administration/shared documents/8000-8999/8600-
8699/8662/reports/25-11-22 operational management and maintenance plan_issue a.docx`

Page 3

 25 November 2022


Table of Contents

1         INTRODUCTION                                                                                                                                                 3
2         CONSTRUCTION PHASE                                                                                                                                           3
3         OPERATIONAL PHASE                                                                                                                                            3
      3.1.1          General ............................................................................................................................................................ 3
      3.1.2          Maintenance Program ............................................................................................................................... 4
      3.1.3          Watering ......................................................................................................................................................... 5




Table of Tables
Table 1 - General recommended program of inspection and maintenance – Bioretention Basin                                                                                                5

Table of Appendices
Appendix 1 MPN Plans                                                                                                                                                                    6
Appendix 2 Bioretention Basin Construction Checklists and Forms                                                                                                                         7
Appendix 3 Bioretention Basin Maintenance Checklist                                                                                                                                     8




 Excellence with Economy in Engineering                                                                                                                                                       2
 https://mpncnetau.sharepoint.com/sites/administration/shared documents/8000-8999/8600-
 8699/8662/reports/25-11-22 operational management and maintenance plan_issue a.docx`

Page 4

 25 November 2022



1 INTRODUCTION
The following Maintenance Plan addresses the inspection and maintenance procedures to be
undertaken for the on-site stormwater quality improvement devices during the construction and
operational phases of the project. During the construction phase and maintenance period, the
Developer shall be responsible for the monitoring and maintenance of the bioretention basin on
site. Thereafter, the site manager shall be responsible for ongoing monitoring and maintenance.

All maintenance and amendments necessary to achieve and/or maintain the required treatment
performance must be recorded and appropriate steps taken to inform those responsible of any
required actions.

Layout plans and details of the proposed stormwater quality treatment devices are attached in
Appendix 1.

For further details of the development’s stormwater quality treatment devices, refer to the
Stormwater Management Plan prepared by MPN Consulting.

2 CONSTRUCTION PHASE
Bioretention basin construction shall be undertaken in accordance with the Healthy Waterways
Construction and Establishment Guidelines: Swales, Bioretention Systems and Wetlands Version
1.1 April 2010.

Filter media in the bioretention basin is only to be installed once the “Construction” Stage involving
the Civil Works required to create the land forms associated with the development and installation
of the services. Once this has been completed, the construction of the functional elements of the
bioretention basin can be commenced as part of the early landscaping works prior to the “Building
Phase” of the development.

During the “Building Phase” of the development, a protective layer shall be placed over the filter
media. This protective layer consists of a geofabric layer with 25mm topsoil and a turf layer, with
silt fences around the boundary of the basin. After completion of the “Building Phase”, the
geofabric and turf are to be removed with the filter media reprofiled and planted in accordance
with the proposed landscape design. The above protection method is consistent with Option 1
detailed in the Construction and Establishment Guidelines.

Bioretention basin construction inspection checklists and sign off forms from the Construction and
Establishment Guidelines are attached in Appendix 2.



3 OPERATIONAL PHASE
3.1.1 General

Vegetation in the bioretention basin plays a key role in maintaining the porosity of the filter media
and a strong healthy growth of vegetation is critical to its performance. The establishment of
plants after the construction phase and ongoing maintenance is therefore a fundamental part of
the operation of the entire device.


 Excellence with Economy in Engineering                                                                  3
 https://mpncnetau.sharepoint.com/sites/administration/shared documents/8000-8999/8600-
 8699/8662/reports/25-11-22 operational management and maintenance plan_issue a.docx`

Page 5

 25 November 2022



Overflow pits require careful monitoring, as these are prone to scour and a build-up of sediment,
debris and gross pollutants. Debris can block outlets and can be unsightly. Inspection and removal
of debris should be undertaken regularly and debris should be removed whenever it is observed
on-site.

3.1.2 Maintenance Program

Maintenance of the bioretention basin would involve the following activities:

     •    Removal of sediment where it is smothering the bioretention basin vegetation;
     •    Manual removal and management of invasive seeds. Note herbicides should not be used as
          they would contaminate the downstream receiving waters;
     •    Debris removal in the bioretention basin and adjoining areas;
     •    Repair any damage to the profile as a result of scour, rill erosion or vehicle damage by
          replacement of appropriate fill (to match onsite soil) and revegetation;
     •    Till the bioretention basin surface, or remove the surface layer, if there is evidence of
          clogging;
     •    Regularly water the basin vegetation until plants are established and actively growing;
     •    Fertilising of plants with environmentally friendly products;
     •    Removal of plants that have died and replacement with plants of equivalent size and
          species as detailed in the Landscape Architect’s planting schedule;
     •    Pruning to remove dead or diseased vegetation material and to stimulate growth;
     •    Vegetation pest monitoring and control; and
     •    Inspection and repair of the subsoil drainage system.

Table 1 below sets out the recommended frequency for inspections and maintenance of
bioretention basins during the Operational Phase. Note the Schedule is a guideline only. Routine
clean out and maintenance should be scheduled based on the outcome of routine inspections.




 Excellence with Economy in Engineering                                                               4
 https://mpncnetau.sharepoint.com/sites/administration/shared documents/8000-8999/8600-
 8699/8662/reports/25-11-22 operational management and maintenance plan_issue a.docx`

Page 6

 25 November 2022




 Schedule of Site Visits
 Purpose of Visit                               Frequency                    J     F      M A M J         J   A   S   O N D
 Routine Inspection                             Monthly                      √    √       √   √   √   √   √   √   √   √   √   √
 Annual Inspection                              Yearly                                        √
 Routine Maintenance                            Twice Yearly                                  √                       √
 Routine Clean-Out of
                              Every Two Years                √
 Sediment
  Table 1 - General recommended program of inspection and maintenance – Bioretention Basin

For additional information and guidance on how to undertake maintenance activities, refer to the
Healthy Waterways: Maintaining Vegetated Stormwater Assets Version 1 February 2012.

A bioretention basin inspection and maintenance checklist from the Maintaining Vegetated Assets
Guideline is attached in Appendix 3.


3.1.3 Watering

Time of year and the climate will determine the frequency of watering. However, during
establishment, regular watering is essential for plants. Successfully establishing plants is
dependent on the frequency of watering, which in turn is dependent on rainfall, the maturity of the
plant stock and the water-holding capacity of the soil. The following watering program is generally
adequate but should be adjusted to suit site conditions:

     •    Week 1 – 6   5 visits per week
     •    Week 7 – 10 3 visits per week
     •    Week 11 – 12 2 visits per week

In the absence of rain, it is recommended that each plant receives 2.5 – 5.0 litres of water per week
during the first six weeks (40mm of watering per week during establishment).

After the initial four-month period, watering may still be required, particularly during the first
winter or dry period. Watering requirements for healthy vegetation can be determined by ongoing
inspections.




 Excellence with Economy in Engineering                                                                                           5
 https://mpncnetau.sharepoint.com/sites/administration/shared documents/8000-8999/8600-
 8699/8662/reports/25-11-22 operational management and maintenance plan_issue a.docx`

Page 7

25 November 2022


                                                                                         Appendix 1
                                                                                         MPN Plans




Excellence with Economy in Engineering                                                                6
https://mpncnetau.sharepoint.com/sites/administration/shared documents/8000-8999/8600-
8699/8662/reports/25-11-22 operational management and maintenance plan_issue a.docx`

Page 8

25 November 2022


                                                                                                    Appendix 2
                                                          Bioretention Basin Construction Checklists and Forms




Excellence with Economy in Engineering                                                                           7
https://mpncnetau.sharepoint.com/sites/administration/shared documents/8000-8999/8600-
8699/8662/reports/25-11-22 operational management and maintenance plan_issue a.docx`

Page 9

BIORETENTION SYSTEM CONSTRUCTION & ESTABLISHMENT SIGN-OFF FORMS

Asset |.D.

System location:

DANo.

ee

 

Civil drawing no.

Landscape drawing no.

Area: Catchment Area (ha):

 

Bioretention Area (ha):

 

ROLE/STAKEHOLDER COMPANY

 

CONTACT NAME CONTACT DETAILS

 

 

Developer

Site superintendent (civil)

 

 

Site superintendent
(landscape)

 

Bioretention designer

 

Civil engineer

 

Landscape architect

 

Civil contractor

 

Landscape contractor

 

Council compliance officer

CHECKLIST OF SIGN-OFF FORMS

SIGN-OFF FORM DATE COMPLETED

NAME OF
SIGNATORY & ROLE SIGNATURE
(E.G. SUPERINTENDENT)

 

Pre-Start Meeting

 

Form A — Earthworks &
Functional Structures

 

Form B — Under-Drainage

Form C — Bioretention Media

Form D — Finished Levels

Form E — Coarse Sediment
Forebay

Form F — Protective
Measures

Form G — Landscape
Installation

Form H — Landscape
Establishment

 

 

 

elines € Walel bygesign 109

 

Page 10

PRE-START MEETING

List pre-start meeting attendees who are to sign indicating they have attended the meeting and understand the design intent,

construction and establishment process.

Location

Date

 

ROLE/STAKEHOLDER COMPANY CONTACT NAME

CONTACT DETAILS

 

Developer

 

Site superintendent (civil)

 

Site
superintendent(landscape)

 

Bioretention designer

 

Civil engineer

 

Landscape architect

 

Civil contractor

 

Landscape contractor

 

Other

 

Other

 

Other

 

 

 

 

Comments (attach and refer to additional pages if necessary)

Actions (attach and refer to additional pages if necessary)

 

io woterbyd

 

ON Construction and Establishment Guidelines

Page 11

FORM A — EARTHWORKS AND FUNCTIONAL (HYDRAULIC) STRUCTURES

Purpose: To ensure earthworks bulking out, trimming and profiling and the key levels of functional (hydraulic) structures are in

accordance with design drawings and specifications. The earthworks and structures dictate the movement of stormwater

through the bioretention system and are a critical element in the function of the system.

ITEMS

CHECKED

As constructed survey completed and |

attached to this form

Photos taken and attached to this form |

Set-out of system is correct

Base levels are at correct elevation

(£50 mm)

Base at correct grading (0.5%)

fe

SATISFACTORY

es

ACTION (IF
UNSATISFACTORY)

INITIAL

 

Punch out holes in overflow pit are
correct size, correct level and above

invert level of outlet pipe (+25 mm)

Overflow pit is correct size and crest and
invert is at correct level (25 mm)

 

Outlet pipe invert levels are correct
(upstream and downstream) (£25 mm)

 

Outlet pipe is free dra

 

Overflow weir (if required) is correct
length and at correct level +25 mm) |

 

Overflow weir (if required) is keyed |

into bund

 

Bunds/embankments surrounding the

system are at correct levels or above |

 

 

 

HOLD POINT: Superintendent and bioretention designer inspection and sign-off before proceeding.

Comments (attach and refer to additional pages if necessary)

NB: As constructed survey and drawings and photos attached.

Signed by superintendent:
Print name:

Date:

Signed by bioretention designer:

Print name:

Date:

 

Page 12

FORM B — UNDER-DRAINAGE

Purpose: To ensure under-drainage is installed correctly before the bioretention media is installed.

ITEMS

Base of system free from debris
Liner (typically filter cloth) correctly
installed

There is no fabric ‘sock’ around the under-

drainage

Correct under-drainage has been

supplied and slotted at 2 mm or smaller

Under-drainage pipes are laid at the
correct spacing (small bioretention
system 1.5 m, large system 2 m)

Required grade (verified using level or
string line)

Under-drainage pipes laid at required

grade (verified using level or string line to
achieve design level 25 mm and 0.5%
grade)

CHECKED

SATISFACTORY

 

Alljunctions and connections have been
appropriately sealed

Top of clean out points at design level (i.e.
approximately 50-150 mm above filter
media surface )

 

 

 

ACTION (IF
UNSATISFACTORY)

 

HOLD POINT: Superintendent and bioretention designer inspection and sign-off before proceeding.

Comments (attach and refer to additional pages if necessary)

NB; As constructed survey and drawings and photos attached

Signed by superintendent:
Print name:

Date:

Signed by bioretention designer:

Print name:

Date:

INITIAL

Page 13

FORM C — BIORETENTION MEDIA

Purpose: To ensure that the media placed in the system meets the required specifications and that there is a record of the
media being delivered to site.

To ensure media layers are installed correctly and meet the design and specification requirements.

SOURCING, TESTING AND SUPPLYING BIORETENTION MEDIA

ACTION (IF

DRAINAGE LAYER CHECKED SATISFACTORY, UNSATISFACTORY)

INITIAL

Meets the specifications |

Meets the required hydraulic
conductivity (4,000 mm/hr)

Delivery supply docket certifies that the

 

material delivered is the material tested
(delivery docket attached)

TRANSITION LAYER SUPPLY

Meets the specifications

 

Supplier certification provided
(certification attached)

 

 

Delivery supply docket certifies that the
material delivered is the material tested |
(delivery docket attached) |

 

 

 

FILTER MEDIA SUPPLY

Meets the FAWB's Guideline
Specifications for Soil Media in
Bioretention Systems (2008)

Meets the required hydraulic
conductivity (100-500 mm/hr, 750 mm/hr
maximum)

Frequency of laboratory testing
completed in accordance with Section 3.5
(results of testing attached)

Supplier certification provided
(certification attached)

Delivery supply docket certifies that the
material delivered is the material tested
(delivery docket attached)

HOLD POINT: Superintendent or bioretention designer inspection and review of test results and certifications before proceeding.

Comments (attach and refer to additional pages if necessary)

Page 14

FORM C — BIORETENTION MEDIA (CONT.)

INSTALLATION OF BIORETENTION MEDIA

Base of system free from debris

Drainage layer (fine gravel) installed to
correct depth (+25 mm)

Transition layer (coarse sand) installed to
correct depth (+25 mm)

Placement of filter media completed to
avoid compaction of media and using at
least two lifts

Filter media installed to correct depth

ACTION (IF

SATISERCTORY, UNSATISFACTORY)

INITIAL

 

Light, even compaction applied to
remove air gaps (e.g. light roller or single
pass with a ‘pozitrack’ bobcat)

Spreader bar used to flatten surface of
filter media

 

 

Sediment fences in place

 

 

INSPECTION: Superintendent and bioretention designer inspection and sign-off to occur while installation of media is

occurring. Photos must be taken by the superintendent, the bioretention designer or the contractor.

Comments (attach and refer to additional pages if necessary)

NB: Laboratory test results, certification, delivery dockets and photos attached

Signed by superintendent:
Print name:

Date:

Signed by bioretention designer:
Print name:

Date:

 

Page 15

FORM D — FINISHED LEVELS

Purpose: To ensure finished levels of system surface and bunds are correct and meet the design.

ACTION (IF

ITEMS CHECKED SATISFACTORY UNSATISFACTORY)

INITIAL

|
Landscaping topsoil applied to |
surrounding bunds to achieve design
levels

As-constructed survey of system surface |

 

and surrounding bunds completed

Final constructed levels are consistent
with design levels

Under-drainage clean-outs extended 50-
150 mm above filter media

Under-drainage pipes flushed to remove

initial ingress of material

HOLD POINT: Superintendent and bioretention designer inspection and sign-off before proceeding.

Comments (attach and refer to additional pages if necessary)

 

NB: As constructed survey and drawings and photos attached

Signed by superintendent: Signed by bioretention designer:
Print name: Print name:

Date: Date:

Page 16

FORM E — COARSE SEDIMENT FOREBAY
Purpose: To ensure the coarse sediment forebay is constructed correctly.

ACTION (IF
ITEMS CHECKED SATISFACTORY UNSATISFACTORY) INITIAL

Extent of coarse sediment forebay

correctly set out

Rocks to be used to line base of forebay

are correct size and shape | |

 

Base of constructed forebayisflatand | |
set at the correct level below the surface |
of the filter media

Rocks placed for energy dissipation are

location

 

Interface between forebay and filter
media is structurally sound and not prone

 

 

|
|
|
of appropriate size and are in correct |
|

to collapse

HOLD POINT: Superintendent or bioretention designer inspection and sign-off before proceeding.

Comments (attach and refer to additional pages if necessary)

 

NB: As constructed survey and drawings and photos attached

Signed by superintendent: Signed by bioretention designer:
Print name: Print name:

Date: Date:

Page 17

FORM F — PROTECTIVE MEASURES

Purpose: To ensure protective measures are correctly installed to protect the bioretention system while building is occurring in the catchment

Protection option adopted (Option 1, 2 or 3)

OPTION 1 — SURFACE PROTECTION DURING
BUILDING PHASE

Continuous sediment fences installed around
perimeter of filter media and top of batter.

Where landscape works are not to commence
immediately then cover batters with filter cloth.

Protective covering (filter cloth + 25 mm topsoil +
turf) installed across entire filter media area of
system.

OPTION 2 — BYPASS AND EARLY
ESTABLISHMENT

Continuous sediment fences installed around
perimeter of filter media and top of batter.

CHECKED

CHECKED

SATISFACTORY

SATISFACTORY

ACTION (IF
UNSATISFACTORY)

ACTION (IF
UNSATISFACTORY)

INITIAL

INITIAL

 

Where landscape works are not to commence
immediately then cover batters with filter cloth.

 

Temporary bund installed (where required) to
prevent stormwater runoff from entering bulk of
system. Bund keyed into batters of bioretention
and crest level higher than pits and weirs.

 

Temporary protective covering (filter cloth + 25
mm topsoil + turf) installed within bunded area.

OPTION 3 - SEDIMENT BASIN AND
BIORETENTION FUNCTION

Continuous sediment fences installed around
perimeter of filter media and top of batter

Sediment basin installed upstream of bioretention
in accordance with either (including hydraulic
structures):

* WSUD Technical Design Guidelines for SEQ
(SEQHWP)

+ Local erosion and sediment control guidelines or
Best Practice Erosion and Sediment Control
(IECA, 2008)

Suitable access provided to sediment basin for
clean out

Bioretention system installed downstream of
sediment basin

 

Protective covering (filter cloth + 25mm topsoil + |
turf) installed across entire filter media areaof =|

basin.

 

CHECKED

SATISFACTORY

 

 

HOLD POINT: Superintendent and bioretention designer inspection and sign-off before proceeding.

Comments (attach and refer to additional pages if necessary)

NB: Photos attached.

Signed by superintendent:
Print name:

Date:

ACTION (IF
UNSATISFACTORY)

Signed by bioretention designer:

Print name:

Date:

INITIAL

 

 

Page 18

FORM G — LANDSCAPE INSTALLATION

Purpose: To ensure the correct plants are supplied, installed and established.

ITEMS

Correct mulch has been supplied
Mulch applied to correct depth and
secured

Supplied plants are correct species

 

Supplied plants are in correct pot sizes
and maturity (300 mm min)

Plants have been installed at correct
planting density (min 6 plants/m?)

As constructed drawings marked up with
final plant species and densities

CHECKED

SATISFACTORY

ACTION (IF
UNSATISFACTORY)

INITIAL

 

Mulch is clear of plant stems by
approximately 50 mm

 

 

 

HOLD POINT: Superintendent AND bioretention designer inspection and sign-off before proceeding.

Comments (attach and refer to additional pages if necessary)

 

NB: As constructed drawings and photos attached

Signed by superintendent:
Print name:

Date:

Signed by bioretention designer:

Print name:

Date:

 

Page 19

FORM H — LANDSCAPE ESTABLISHMENT

Purpose: To ensure the correct plants are supplied, installed and established.

ITEMS CHECKED

PLANT ESTABLISHMENT

Weeds being removed as required |
— —t—_ - -

Watering occurring as required

Replanting occurred as required to
replace failed plants

Plants successfully established plants
propagation is occurring.

Measure of successful establishment

1. Survivorship greater than 90%

2.80% coverage of system

3. Preferably more than one species per
macrophyte zone

4. At least 5 plants/m2 (preferably 6-10
plants/m2)

5. Plant height of at least 50%. This can
be measures through the use of
marker or stakes through the
bioretention

6. Propagation is occurring (more than
2-3 stems, seeding)

7.No weeds.

Growth and maturity should be recorded

through three-monthly photo logs every
500 m2.

 

ACTION (IF

BAST ACTORY. UNSATISFACTORY)

 

 

HOLD POINT: Superintendent AND bioretention designer inspection and sign-off.

Comments (attach and refer to additional pages if necessary)

NB: As constructed drawings and photos attached.

Signed by superintendent:
Print name:

Date:

Signed by bioretention designer:
Print name:

Date:

 

INITIAL

Page 20

4.3 Inspection and maintenance checklist for bioretention systems

ASSET TYPE Bioretention ASSET ID
Location

Date

Date of last rainfall Weather

Officer's name

Bioretention plan

Insert diagram or plan of the asset showing key features e.g. locations of inlet, outlet, and overflow

Additional information
Time taken to complete inspection or maintenance

Photos of site 1.
(explanatory notes)

General comments and sketches

Officer's signature

Maintaining Vegetated Stormwater Assets Vers on | waterbudesign 41

Page 21

papeeu yom jeuornppy

ajqeaijdde you - yyy ‘pa}2adsu) jou - jx ‘papaau aq Aew uo}jed1J1}9ay - p ‘papaau adueUajUlew |eUOIjppy - E!uayeyJapun AjAljIe aDUeUA}UIEW Jayje JW! |q-Z ‘JAW |g-Ly

#9UyeWapun a2ueuazuEyW

Paaowa: 18}}1) 10 JUBWIpas Jo JuNOWe “B'a ajqissod asaym AjueNy ,.

48}}1] ou pue jn

%GL> Aeqgasoj JUBWIPAaS asieo>,

Papuazjeun 348) J) Uasiom

OU pjnom pue ApZaquI jeunjan4ys
do Ayajyes 31)qGnd 0} ys11 e asod

OU Sap 3e4) Ajo UO}sOJa JOU)

a8ey20)q ON

Ayusaqur
Jesnjonsys Jo Ajajes a1qgnd

0} ys11 e sasod yey} adewep on

juawa)}}as/aquapisqns
4O UOISOJa JO SIUSPIAS OU S] B4ay}

pue punos Ajjeinjanijs Ss! ja]uy

Aya8aqu
yeunqani}s 10 Ayajyes a1)Gnd

0} ys} e sasod jey} adewep on

28u}}21 UON}}puc) (Id) 403e2:puy a2uewojseg

juaunpas

uoisol3

(LN3S3ud J)
AV@3404 LNAWIGAS ISUVOD

Siqgap 40 442331) ‘}uaUNpas

sa}eJ8 Jo spi) id Ba

$81N}2NJ3s paAowias Jo paseweg

uo1s013

L31NI

spse}joqg d144e4) ‘Ba
$ain}2nJ3s padowia, 40 paseweg

sannouuns

404 YOO) 03 E4AR

42 waterbydesign Maintaining Vegetated Stormwater Assets Version|

Page 22

Papaau 410m jeuolppy

a)qe2)\dde you - yn ‘pa}2adsu) jou - jN ‘papaau aq Aew u0}}e3151}9ay - p ‘(papaau adueuAyUleWw jeuOI}Ippy - €‘uayeyJapuN AjIA1}De adUeUaJUIEW Ja}Je JAW |q-Z “JAW |q-1,

##U@4eVapuN sueUa MEW

Parowas 4233!) Jo JUaWIpas jo JuNOWe “Ba ajqissod a1aym AyiqueNH 4x

Www 00S < jyZiay Jue}d aBesaay

aseo

 

wo aa4j pue Ayyjeay sjue}q

(sayajeq aseq jewiuiw)

4BA0I UOI}EJIBIA %GG wu |p|

pa}djajap auoy,

2W pad

48}})| adaid | wnwixeyy

aed uy Ajainaas sde pua

pue paSewep jou sjulod yno uea})

xx1PAW J9}]1J 9Y} UO adeyNS
ay)|-Ae] 10 ajqeawadun snoiago
OU S} ajay} pue jeyuIes Jaye
sanoy Z| UeY} aJOW Joy adejNs ayy
uo papuod jou s} ayem Aqaiaym

‘Ajaas4 Bujuieip si eipaw 1a})14

WW OOL<
SpunowW JO suolssaidap a2ejins oN

8ul}SNJ2 adeyINS ON

Papuaz}eun 4a] 41 UaSJOM
OU pjNom pue Ajp1IBaqu) eunyaN4ys
jo Ayajes 31)qGnd 0} ys!) e asod

OU Sap ey} AjuO UO}SOJa JOU)

#3unje1 uonj1puo) (Id) 403e2)puy a2uewsojieg

uojjze3a3ap,

(aseai8 pue }10 “*B'a) sasueysqns

40 ‘sino}09 ‘sinopo jensnuy

32331]

s3ujod 3no uea}2/suespsapur,

Ayqeaued
40 A}1A132Npuo? 2)nespAY

Spunow Jo suoissaidag

quaunpas aul Jo sn}

uoiso1y

LUAANI
3SV@ GNV SadO1s YaLlva

40J 400) 03 3e4

Maintaining Vegetated Stormwater Assets Version | waterbydesign 43

Page 23

papaau ¥J0m jeuor1ppy

e1paus Ja3}14 Buiulesp Ajs00d yo Joxe31pul ue s} OYdAy yo aIUBSAI yyy

Parowas 13}}!) Jo JUaWIpas Jo juNOWe “B'a ajqissod a1aym AjiUeND 4x

ajqeaidde jou - yx ‘pajaadsw) jou - jy ‘papaau aq Aew u0lje91}1}9ay - p {papaau adueua}UIeW jeuO)Ippy - €/Uaye}JapuN AjIAI}De BDUUAJUIEWW Ja}Je JBW |q-Z ‘JW |g-L

#,UaeVapuN adueuazWMEW

(payejnuina3ze

juaullpas anissaaxa ‘3'a)
Uo!}3UNJ]ewW Jo adUAapAa OU pue
‘gin}onsjs }]2J3NO ay} 0} aBewep
JO UO1SO1a OU ‘1a}eM JO aSea|a! ay}

0} sjuawpadu) Wees}sumop ON
a8e420)q ON

AyuBaqui
yesnjanizs Jo Ayajes aGnd

0} yS11 e sasod yey} adewep oy

swa}shs a8Je] JO} 118M JO a0}

40 U01}3a}0.1d 4301 Jo saBpa punose
Bupnjoui ‘}uawa}}3as/aauapisqns
40 UOISOJa JO aIUAPIAA OU S! aay}
pue punos Ajjesnjanijs si 3a}3nQ

yymoi8 ssow oN

aegje ul

PasaA09 adejINs JO %OL WNwIXe|Y

#93U)32/ UO}}!pUuo} (Id) 403e2:puy a2uewsojiag

Aemiayem 10 aBeuleip
Bulaiadai 0} Sumueup Ajaa.y 393NQ

Slqgap Jo 4833) ‘uaunpas

$a}eJ8 Jo spy pid Ba

$31N}3N1}S PaAOwWsl JO padgeweg

uo}sos3

(1Wv4LNO YO
‘Adid ‘MlI3M MO14Y3A0)
1a11n0

y3moi3 ssow Jo )e3;y

404 YOO) 03 324A

44 Wwaterbydesign Maintaining Vegetated Stormwater Assets Version|

Page 24

25 November 2022


                                                                                                          Appendix 3
                                                                             Bioretention Basin Maintenance Checklist




Excellence with Economy in Engineering                                                                                  8
https://mpncnetau.sharepoint.com/sites/administration/shared documents/8000-8999/8600-
8699/8662/reports/25-11-22 operational management and maintenance plan_issue a.docx`

Page 25

25 November 2022




                              BIORETENTION BASIN MAINTENANCE CHECKLIST


Inspection Frequency 1 to 6 Monthly                           Date of Inspection
Location
Description
Asset ID
Site Visit by

Inspection Items                                                         Y     N     Actions Required (Details)
Sediment accumulation at inflow points?

Litter within basin?

Erosion at inlet or other key structures?

Traffic damage present?

Evidence of waste dumping?

Vegetation condition satisfactory (health,
weeds etc)?
Watering of vegetation required?

Replanting required?

Mowing required?

Clogging of drainage points (sediment or
debris)?
Evidence of ponding?

Damage/Vandalism to structures present?

Surface clogging visible?

Filling of surface required?

Drainage System inspected?

Resetting of system required?




Excellence with Economy in Engineering                                                                            9
https://mpncnetau.sharepoint.com/sites/administration/shared documents/8000-8999/8600-
8699/8662/reports/25-11-22 operational management and maintenance plan_issue a.docx`

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.