Delegated Report - Code - Planning OPW26 0094 (As Published) · OPW26/0094
Treated material must undergo verification testing at the rate of one sample per 250m3
throughout the duration of the excavation phase of the development. The verification testing
must be undertaken by a qualified person in accordance with the Queensland Acid Sulfate
Soil Technical Manual: Soil Management Guidelines v4.0, and the results must be submitted
to Council for appraisal when requested during construction and prior to commencement of
use and must demonstrate that the material has been adequately neutralised.
Certification of the verification results for compliance with this condition must be provided by
a suitably qualified Geotechnical Engineer prior to the issuing of the certificate of
classification for the dwelling.
16. Fall protection must be provided to retaining walls that are over 1m high.
17. Slope and batters are a maximum grade of:
a. 1 in 6 where in proximity to waterbodies;
b. 1 in 4 for grassed areas;
c. 1 in 3 for planted areas; and
d. 1 in 2 for combined structural engineering and planting solutions.
Stormwater Drainage
18. Appropriate scour protection must be provided at the outlet of all stormwater pipes including
temporary outlets.
19. Works associated with this permit must not adversely impact on the existing drainage
conditions on other properties (e.g., by blocking or interfering with natural overland flows).
20. Prior to the completion of the development, all site surfaces must be effectively stabilised
using methods which have achieved effective short-term stabilisation and which will continue
to achieve effective stabilisation in the medium- to long-term (refer to E&SC Advisory Notes).
For the purpose of this condition, an effectively stabilised surface is defined as one that does
not, or is not likely to result in visible evidence of soil loss caused by sheet, rill or gully erosion
or lead to sedimentation, or lead to water contamination
Erosion and Sediment Control
21. Prescribed Water Contaminants (as defined in Schedule 10 of Environmental Protection
Regulation 2019) must not be released from the site or to waters within the site, or be likely
to be released should rainfall occur, unless all reasonable and practicable measures are
taken to prevent or minimise the release and concentration of contamination.
22. Sediment and erosion control measures must be in place prior to works commencing. If such
measures are not in place or are not satisfactory, “on the spot” fines may be issued. Such
fines can be issued if sediments from the site are found to enter or have the potential to enter
Council’s stormwater system, natural waterways, any downstream stormwater filtration
system or adversely impacting on other properties. The sediment and erosion control design
and measures have NOT been approved, it is the site's Supervising Engineer who is
responsible for ensuring that the sediment and erosion control measures have:
a. been duly designed by an RPEQ or CPESC and constructed in accordance with "best
practise" methods;
b. been revised by an RPEQ or CPESC to address the issues raised by changes in the
projected construction schedule and/or methods;
c. been revised to address predicted rainfall events; and
d. achieve the desired environmental outcomes.
Council may request further controls to be installed should thew implementation measures
be found inefficient.
Page 6 of 9
Document Set ID: 25154969
Version: 3, Version Date: 10/09/2026
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalUsed in these records
Delegated Report - Code - Planning OPW26 0094 (As Published).pdfRelated documentApplication case desk ↗
About this file
- File size
- 577 KB (small file)
- File type
No other editions are linked here.