Appendix A - SDAP - State Code 1 - Development in a state controlled road environment response template
Performance outcomes Acceptable outcomes Response
PO29 Development does not impede delivery of No acceptable outcome is prescribed. Complies – The proposed development will not
planned upgrades of state-controlled roads. impede any planned upgrades of state-controlled
roads.
PO30 Development does not impede delivery of No acceptable outcome is prescribed. Complies – The proposed development will not
corridor improvements located entirely within impede delivery of any corridor improvements and
the state-controlled road corridor. is removed from the frontage.
Table 1.4 Filling, excavation, building foundations and retaining structures
Performance outcomes Acceptable outcomes Response
PO31 Development does not create a safety No acceptable outcome is prescribed. Complies – All earthworks are internal to the site,
hazard for users of the state-controlled road or with the majority of fill material to be sourced from
road transport infrastructure. within the landfill site.
PO32 Development does not adversely impact the No acceptable outcome is prescribed. Complies – The proposed earthworks for the
operating performance of the state-controlled development is not likely to impact the operating
road. performance of the state-controlled road, with the
majority of the fill required to be sourced from
within the landfill site.
PO33 Development does not undermine, damage No acceptable outcome is prescribed. Complies – Refer above.
or cause subsidence of a state-controlled road.
PO34 Development does not cause ground water No acceptable outcome is prescribed. Complies – The proposed development will not
disturbance in a state-controlled road. affect ground water within a state-controlled road.
PO35 Excavation, boring, piling, blasting and fill No acceptable outcome is prescribed. Complies – The proposed excavation and filling
compaction do not adversely impact the physical works will not adversely impact a state-controlled
condition or structural integrity of a state- road.
controlled road or road transport
infrastructure.
PO36 Filling and excavation associated with the No acceptable outcome is prescribed. Complies – The existing access is to remain
construction of new or changed access do not unchanged with the filling and excavation works
compromise the operation or capacity of existing proposed being well removed from the state-
drainage infrastructure for a state-controlled controlled road.
road.
Table 1.5 Environmental emissions
State Development Assessment Provisions v3.0
State code 1: Development in a state-controlled road environment Page 7 of 17
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalSearchable page text hides email addresses. Original files are unchanged and may show email addresses.