Attachment 7 - Stormwater Management Plan
Plans and drawings
This document appears to be plans or drawings. Its page text below holds only the words printed on the drawings, without the drawings themselves, so it may be jumbled or hard to follow. To see the plans as drawn, choose Original above or download the file (both need you to log in).
Log in to see the plans as drawnSTORMWATER MANAGEMENT PLAN Client: Devcon Capital 9 Location: 11 Leo Alley Road, Noosaville 3.3 Bioretention Basin Maintenance The proposed bioretention basins will require consideration and management during both the construction period and maintenance period of the development. In order to establish vegetation and treatment functions in the bioretention systems, the filter media will require protection from the common pollutants generated in the construction phases of the development. During the operational phase, regular maintenance is required to ensure a comprehensive vegetation establishment, a critical component in stormwater pollutant uptake. Below are details on the general maintenance periods and the requirements for the construction and maintenance periods. 3.3.1 ‘Construction Period’ Maintenance Erosion and sediment control devices will be installed at the commencement of the works to capture and treat runoff during construction works. The sediment control devices should be cleaned out as required and at the end of the works. During the construction stage, all sediment control devices are to be inspected weekly, after runoff generating rain events and prior and after prolonged site shut downs (e.g. holiday periods). Proposed bioretention basins may be excavated and used as a sediment basin. Any sediment basin will require regular, weekly inspection to prevent scour and sediment build up. Basins should be inspected regularly and cleaned out when 1/3rd full. At the completion of construction, the sediment basins will be removed. The bioretention basin will be installed at the end of the building construction phase when the site is stabilised. 3.3.2 ‘Maintenance Period’ Maintenance The bioretention basins will be temporarily turfed during the maintenance period. Once construction of 80% of the site in each catchment of the development is complete, the turf will be removed and the basins will be vegetated appropriately. 4.0 STORMWATER QUANTITY MANAGEMENT The majority of the existing site is considered to be hardstand as the current use of the site is for storing landscape supplies which are normally delivered and taken away from the site using heavy vehicles. Due to the proposed development the fraction impervious of the site increases slightly from 80% in the existing case to 83% in the developed case. The time of concentration in both cases is effectively the same as both sites have a similar fraction impervious. The subject site has an existing stormwater pit which is identified to be a lawful point of discharge. The existing underground stormwater network is currently connected to this pit. The stormwater pit is located in an easement which discharges to an existing 300mm RCP stormwater main. The existing stormwater network ultimately discharges to Eenie Creek located approximately 500m to the south. A stormwater drainage system is proposed for the development which incorporates a bioretention basin and an underground drainage network. The northern portion of the site will discharge stormwater to the east by connecting to the existing stormwater network within the easement. In the event that the stormwater pit over tops stormwater will discharge as overland flow to the grassed area located to the east as it does in the existing case. The southern portion of the site will discharge to the existing stormwater manhole located in Leo Alley Road to the south. In the event that the proposed network overtops stormwater will discharge as overland flow to the Leo Alley Road roadway and enter the existing stormwater network via the existing gully pits located downstream on Production Street as it does in the existing case. Covey Associates Pty Ltd 5 Project No: 192297 Consulting Engineers 26719Rpt, Issue D
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalLog in to download the original file
Large file: the download may take up to a minute.
Searchable page text hides email addresses. Original files are unchanged and may show email addresses.