RFI - ADG1451.22 Dewatering Management Plan_Rev0_28.02.23

of 34

Page text read automatically using OCR, there may be inaccuracies

Plans and drawings: the text below has words only, no drawings.

Log in to see the plans as drawn
                                                                  ADG Consulting Pty Ltd          All Correspondence
                                                                  ACN: 630 555 225                PO Box 6405
                                                                  ABN: 98 630 555 225             Yatala DC QLD 4207


                                                                  P 07 3801 1564
                                                                  E [email protected]
                                                                  W adgconsulting.com.au




  Dewatering Management Plan
  Proposed Residential Development:
  Lots 2 & 3 on MCH3881, 130‐132 Gympie Terrace, Noosaville, Queensland




  February 2023




  Prepared for:
  Craig & Nathan Francis
  c/‐ SCG Consulting Engineers



Acid Sulfate Soil Assessment      On‐site Wastewater Management      Contaminated Land Assessment & Remediation
Dewatering Management          Environmental Management Plans     Surface & Groundwater Investigation & Monitoring
Log in to download the original file

RFI - ADG1451.22 Dewatering Management Plan_Rev0_28.02.23.pdf · 6.3 MB (large file)

The download may take up to a minute.

Full text of the other 33 pages

Page 2

                                                                                               ADG Consulting Pty Ltd


                                                     Report details



     Project ref:                    ADG1451.22
     ADG Project Contact:            Michael Campbell
     Report title:                   Dewatering Management Plan
                                     Proposed Residential Development:
                                     Lots 2 & 3 on MCH3881, 130‐132 Gympie Terrace, Noosaville, Queensland


     Version:                        Rev0
     Author(s):                      ADG
     Reviewer:                       Michael Campbell


     Client:                         Craig & Nathan Francis
                                     c/‐ SCG Consulting Engineers


     Client contact:                 Tom Harrington – SCG Consulting Engineers


     Distribution date:              28 February 2023
     Distributed to:                 SCG Consulting Engineers
     Copies:                         1 PDF



     ADG Consulting Pty Ltd




     Michael Campbell BEnvSc, BSc[Hons],
     DipProjMgt, DipOHS, DipBusMgt, DipBus(Quality Auditing)
     MEIANZ, MALGA, MASSI
     Director & Principal Environmental Scientist

     Date: 28 February 2023


     This document and all its content is copyright. Apart from fair dealing for the purposes of study, research, criticism
     and/or review as permitted under the Copyright Act 1968, no part of the content may be reproduced, reused or
     redistributed without the prior written permission of ADG Consulting Pty Ltd.




ADG1451.22 Dewatering Management Plan_Rev0_28.02.23                                                                 Page ii

Page 3

                                                                              ADG Consulting Pty Ltd


                                                       Table of Contents
1        INTRODUCTION                                                                            1
1.1      PROPOSED DEVELOPMENT                                                                    1
1.2      RELEVANT GUIDELINES                                                                     1
1.3      GENERAL ENVIRONMENTAL DUTY                                                              1
1.4      DMP OBJECTIVES                                                                          2
1.5      SCOPE OF WORK                                                                           2
2        SITE CHARACTERISTICS                                                                    3
2.1      PROPERTY DESCRIPTION                                                                    3
2.2      SURROUNDING ENVIRONMENT                                                                 3
2.3      TOPOGRAPHY                                                                              3
2.4      GEOLOGY & SOILS                                                                         3
2.5      HYDROGEOLOGY                                                                            3
3        PREVIOUS INVESTIGATIONS                                                                 4
3.1      PACIFIC GEOTECH PTY LTD 2022                                                            4
3.1.1    SOILS                                                                                   4
3.1.2    GROUNDWATER                                                                             4
3.2      GROUNDWATER QUALITY                                                                     4
4        WATER QUALITY OBJECTIVES                                                                6
4.1      RECEIVING ENVIRONMENT                                                                   6
4.2      DEVELOPMENT OF WATER QUALITY OBJECTIVES                                                 6
4.3      PROPOSED WATER QUALITY OBJECTIVES                                                       7
5        DEWATERING METHODOLOGY                                                                  9
5.1      BASEMENT EXCAVATION AND SHORING                                                         9
5.2      GROUNDWATER EXTRACTION                                                                  9
5.3      EXTRACTION/DISCHARGE RATES AND VOLUME                                                   9
5.3.1    DEWATERING EXTRACTION CALCULATION BASED ON SUBSURFACE SOIL PROFILE                      9
5.4      DEWATERING DURATION                                                                     10
5.5      GROUNDWATER DRAWDOWN                                                                    10
5.6      GROUNDWATER TREATMENT                                                                   11
5.7      NOMINATED HOLD POINTS                                                                   11
6        WATER QUALITY MANAGEMENT                                                                12
6.1      RESPONSIBILITY                                                                          12
6.2      OPERATIONAL POLICY                                                                      12
6.3      PERFORMANCE CRITERIA                                                                    12
6.4      IMPLEMENTATION STRATEGY                                                                 12
6.4.1    GROUNDWATER TREATMENT SYSTEMS                                                           12
6.4.2    DEWATERING STRATEGY                                                                     13
6.4.3    INITIAL PUMP‐OUT                                                                        13
6.5      MONITORING                                                                              13
6.5.1    VISUAL MONITORING                                                                       13
6.5.2    WATER QUALITY MONITORING                                                                13
6.5.3    MONITORING RESPONSIBILITIES                                                             14
6.6      MAINTENANCE                                                                             15
6.7      REPORTING                                                                               15
6.8      CONTINGENCIES                                                                           15
7        NOISE & ODOUR MANAGEMENT                                                                17
7.1      RESPONSIBILITY                                                                          17
7.2      OPERATIONAL POLICY                                                                      17
7.3      PERFORMANCE CRITERIA                                                                    17
7.4      IMPLEMENTATION STRATEGY                                                                 17
7.4.1    NOISE                                                                                   17
7.4.2    ODOUR                                                                                   17
7.5      MONITORING                                                                              17


    ADG1451.22 Dewatering Management Plan_Rev0_28.02.23                                       Page iii

Page 4

                                                          ADG Consulting Pty Ltd


7.6      REPORTING                                                           18
7.7      CONTINGENCIES                                                       18
8        LIMITATIONS                                                         19
9        REFERENCES                                                          20
APPENDIX A: FIGURES
APPENDIX B: DRDMW LICENCED BORE SEARCH
APPENDIX C: BASEMENT INSTALLATION PLAN (DRAFT)
APPENDIX D: DEWATERING CALCULATION OUTPUT




    ADG1451.22 Dewatering Management Plan_Rev0_28.02.23                   Page iv

Page 5

                                                                                          ADG Consulting Pty Ltd


1    Introduction
     ADG Consulting Pty Ltd (ADG) was engaged by Craig & Nathan Francis care of SCG Consulting Engineers
     (SCG) to prepare a Dewatering Management Plan (DMP) for the proposed residential development within
     property described as Lots 2 & 3 on MCH3881, situated at 130‐132 Gympie Terrace, Noosaville,
     Queensland.
1.1 Proposed development
     The proposed development comprises the construction of four two‐storey residential dwellings (2x
     duplex pairs) overlying two single level in‐ground basements on the 1,581 m2 site. Supplied information
     indicates that excavations to facilitate the basement construction will extend to a maximum of
     approximately 2.3 m below ground level (bgl) to approximately ‐0.7 m Australian Height Datum (AHD).
     Localised deeper excavations may be required for the construction of other structural elements (i.e.
     footings and pile caps), where required.

     Groundwater seepage was recorded at depths pf between 1.0 to 1.1 mbgl (equating to an approximate
     elevation of 0.6 m AHD), during preliminary geotechnical works (drilling) on the site by Pacific Geotech in
     October 2022. Given the sites proximity to the Noosa River and the presence of groundwater within the
     excavation extent, dewatering will be necessary to allow the basement to be constructed in dry
     conditions.
1.2 Relevant guidelines
     The DMP was prepared with reference to the following documents:


          Australian and New Zealand Guidelines for Fresh and Marine Water Quality. 2018. Australian and
           New Zealand Governments and Australian state and territory governments (ANZG), Canberra ACT,
           Australia.
          Australian and New Zealand Guidelines for Fresh and Marine Water Quality. 2000. Australian and
           New Zealand Environment and Conservation Council and Agriculture and Resource Management
           Council of Australia and New Zealand (ANZECC/ARMCANZ).
          Environmental Protection (Water & Wetland Biodiversity) Policy 2019. Department of Environment
           and Science (DES), Queensland Government.
          Noosa River environmental values and water quality objectives. 2022. Department of Environment
           and Science (DES), Queensland Government.
          Guidelines for Managing Risks in Recreational Water. 2018. Australian Government, National Health
           and Medical Research Council (NHMRC).
          Monitoring and Sampling Manual 2018, Version 2 June 2018. 2018. Department of Environment and
           Science (DES).
          Queensland Water Quality Guidelines 2009, Version 3. 2013. The Department of Environment and
           Heritage Protection (DEHP).
1.3 General environmental duty
     The Environmental Protection Act 1994 describes that all persons in Queensland have a “General
     Environmental Duty” and that “a person must not carry out an activity that causes, or is likely to cause
     environmental harm unless the person takes all reasonable and practicable measures to prevent or
     minimise the harm”.

     The Act requires that appropriate action be taken to report that environmental harm is occurring or has
     the potential to occur, unless the harm is authorised under an environmental protection policy, an
     environmental management program, a development approval, or an environmental protection order.
     This is known as the “Duty to Notify”. Failure to fulfil this duty is an offence and may result in prosecution.




ADG1451.22 Dewatering Management Plan_Rev0_28.02.23                                                           Page 1

Page 6

                                                                                    ADG Consulting Pty Ltd


1.4 DMP objectives
     The objectives of the DMP are to:
          Describe the dewatering methodology, groundwater treatment, monitoring and reporting
           procedures to be employed at the site during dewatering activities.
          Provide effective management procedures to prevent environmental harm resulting from the
           discharge of extracted groundwater from the site.
1.5 Scope of work
     To achieve the investigation objectives, the following scope of work was undertaken:


          A desktop study including:
           1. Review of the development proposal and proposed shoring/dewatering designs.
           2. Review of geology and soil maps for the area.
           3. Search of groundwater bores licensed by the Department of Regional Development,
              Manufacturing and Water (DRDMW) within a 200 m radius of the site.
           4. Review of relevant existing reports and groundwater data from the local area.
           5. Review of current aerial photographs of the site and surrounds.




ADG1451.22 Dewatering Management Plan_Rev0_28.02.23                                                  Page 2

Page 7

                                                                                                 ADG Consulting Pty Ltd


2    Site characteristics
2.1 Property description
     The site is described as Lots 2 & 3 on MCH3881, and is situated at 130‐132 Gympie Terrace, Noosaville,
     Queensland. From most recent available aerial mapping dated 24 November 2022 (Nearmap), the site
     has been cleared of aboveground infrastructure (circa June‐July 2022) and is generally square to
     trapezoidal in shape. The site has a combined area of 1,581 m2. The site locality is shown in Figure 1,
     Appendix A.
2.2 Surrounding environment
     The surrounding environment and land use is described briefly in Table 1.

     Table 1 Surrounding land use and environment

              Direction                                                Environment

                North             Chaplin Park, then Noosa River.

                 East             2‐ storey residential lots, then canal network associated with Noosa River.

                South             Gympie Terrace, then multiple residential lots.

                West              Cleared vacant land, then residential lot, then Mill Street.


2.3 Topography
     The site and surrounding land is considered to be generally level (PG, 2022), with the site surface
     elevations ranging between approximately 1.3 m to 1.8 m AHD from the southern boundary toward the
     north of the site (refer SCG earthworks and piling plan).
2.4 Geology & soils
     The surface geology at the site is mapped as being Pleistocene aged sandy mud, muddy sand and minor
     gravel: estuarine channels and banks. The dominant rock type is identified as miscellaneous
     unconsolidated sediments as referenced through detailed surface geology (accessed via Queensland
     Globe online, 28 February 2023).

     The Acid Sulfate Soils (ASS) map 1:100,000 scale categorises the site as ‘SEA’ or ‘Disturbed Land with
     probability of ASS’, indicating that the site is likely to contain acid sulfate soils but the type and depth to
     ASS has not been defined (accessed via Queensland Globe online, 28 February 2023).
2.5 Hydrogeology
     A search of groundwater bores licensed by DRDMW was conducted by ADG on 28 February 2023. The
     search identified no licensed bores within a 200 m radius of the site. A map showing the bore search area
     is provided in Appendix B.

     Based on the local geology and topography, and the site’s proximity to the Noosa River, the inferred
     groundwater flow is to the north and/or east. Groundwater beneath the site is likely to be hydraulically
     connected to the river and/or canal network, therefore saline groundwater conditions are anticipated,
     and additional saltwater intrusion is likely to occur during dewatering.




ADG1451.22 Dewatering Management Plan_Rev0_28.02.23                                                               Page 3

Page 8

                                                                                       ADG Consulting Pty Ltd


3    Previous investigations
     This DMP is based on site specific information sourced from the following, provided to ADG by
     SCG Consulting Engineers:
             Acid Sulfate Soil Investigation, Proposed Residential Development, 128 – 132 Gympie Terrace,
              Noosaville. November 2022. Pacific Geotech Pty Ltd. Ref: PG‐9236, 2022‐10‐31, ASR VER 1.
             Geotechnical Investigation, Proposed 128 – 132 Gympie Terrace, Noosaville. November 2022. Pacific
              Geotech Pty Ltd. Ref: PG‐9236, 2022‐11‐08, GR VER 1.
             Operational Works: Earthworks & Piling – 130 – 132 Gympie Terrace, Noosaville. Drawing No. 32225‐
              OW3.1. September 2022. SCG Consulting Engineers Pty Ltd.
     It is noted that dilapidation reports for surrounding structures and services are proposed to be
     undertaken prior to commencement of construction and dewatering, however are to be provided to
     Council separately from this DMP.

     A brief discussion of relevant soil and groundwater conditions is provided below.
3.1 Pacific Geotech Pty Ltd 2022
     A Geotechnical Investigation and concurrent Acid Sulfate Soils Investigation was undertaken at the site
     in October 2022 (reported November 2022) by Pacific Geotech Pty Ltd (PG).
3.1.1 Soils
     A total of four (4) boreholes (BH01 to BH04) were drilled on the proposed development footprint to
     between 4.0 and 9.0 mbgl.

     The subsurface profile encountered is generally described as clay and sand fill material at the ground
     surface, extending to depths ranging between 1.0 m and 1.1 m. Fill material is underlain by natural sand
     and silty sand which is initially medium dense, becoming loose with depth, extending to depths ranging
     between 2.5 m and 2.9 m. The upper‐level sand is underlain by very dense, indurated sand which extends
     to depths ranging between 2.8 m and 3.2 m. This indurated sand is underlain by stiff to hard, silty and
     sandy clay, which extends to the borehole termination depths.

     Alongside the Geotechnical Investigation (2021), Acid Sulfate Soil (ASS) samples were collected at 0.5 m
     intervals in BH01 & BH02 to 4.0 m depth. A total of sixteen (16) samples were collected for ASS screening
     and eight (8) samples were selected for further analysis by the Chromium Reducible Sulfur suite (CRS).

     ADG notes that the testing was limited to two boreholes with ASS testing to 4.0 m depth, and PG reports
     that within part of this depth profile the natural sands are considered to contain potential ASS requiring
     liming at rates of up to 8 kg/tonne. All excavated spoil from depths between 1.5 to 2.5 mbgl within the
     excavation footprint will be appropriately neutralised with lime and validated in accordance with
     recommendations by PG in the ASS Investigation Report (PG, 2022).
3.1.2 Groundwater
     During drilling activities for the Preliminary Geotechnical Investigation, groundwater seepage/inflow was
     encountered at 1.0 to 1.1 m depth below the ground surface (approx. 0.6 m AHD)(PG, 2022).

     It should be noted however, that groundwater depths and ground moisture conditions are affected by
     weather and climatic conditions, tidal variations, surface and subsurface drainage/permeability
     conditions, and human influence and will therefore vary with time. Groundwater levels are expected to
     be similar to the water level in the canal to the east and river to the north, albeit somewhat a dampened
     response to tidal variations.
3.2 Groundwater quality
     No groundwater quality data was obtained by PG as part of the preliminary geotechnical investigation.
     However, based on numerous groundwater investigations and dewatering monitoring projects that have


ADG1451.22 Dewatering Management Plan_Rev0_28.02.23                                                      Page 4

Page 9

                                                                                         ADG Consulting Pty Ltd


     been undertaken by ADG throughout the Noosa Coast Region in recent years, our understanding of the
     groundwater quality in the region is provided below:
          Groundwater is generally mildly acidic to neutral, with pH levels ranging from approximately 5.5 to
           6.5 and electrical conductivity ranging from brackish to saline between 2,000 µS/cm to
           48,000 µS/cm. Groundwater pH has the potential to reduce (become more acidic) following
           oxidisation of PASS as dewatering progresses, particularly if re‐wetting of the soils occurs.
          Dissolved oxygen levels in static groundwater typically range from approximately 35 – 40 %
           saturation.
          The groundwater associated with indurated sand strata is moderately to highly turbid as a result of
           staining and organic content.
          Concentrations of dissolved metals are typically below the available marine water trigger values
           (MWTV’s) provided in ANZECC/ARMCANZ (2000) for the receiving waters, however elevated levels
           of aluminium and particularly iron are expected in the untreated groundwater and have the
           potential to increase following oxidisation of PASS as dewatering progresses or as a result of existing
           acidic groundwater conditions.
          Given the location and previous use of the site, groundwater impacts resulting from site
           contamination are not anticipated.
     A groundwater investigation will be undertaken at the commencement of dewatering as described in
     Section 6.5.2 of this report. This assessment will be representative of the groundwater being extracted
     and treated from the entire site, as opposed to localised monitoring well data which is often misleading.
     Based on previous experience with dewatering in the area, ADG expects the groundwater to require
     treatment to increase pH and dissolved oxygen levels, as well as reduce turbidity, suspended sediments
     and dissolved metal concentrations prior to being discharged to the Noosa River.




ADG1451.22 Dewatering Management Plan_Rev0_28.02.23                                                         Page 5

Page 10

                                                                                       ADG Consulting Pty Ltd


4    Water quality objectives
4.1 Receiving environment
     It is proposed to discharge extracted groundwater to the stormwater network via gully pit on Gympie
     Terrace (adjacent the bus stop) which discharges to the canal network associated with the Noosa River
     located approximately 60 m east of the site. The exact location of the receiving waters/environment will
     be confirmed on commencement of dewatering.

     The receiving environment in this location identifies as a moderately disturbed, marine canal
     environment. The following section establishes water quality objectives (WQOs) to ensure that the
     environmental values of the receiving waters are protected and maintained.
4.2 Development of water quality objectives
     WQOs have been developed to support and protect the designated environmental values (EVs) for the
     receiving environment. The WQOs have been developed with reference to the following guideline
     documents:
          Australian and New Zealand Guidelines for Fresh and Marine Water Quality 2018. (ANZG 2018) The
           selected trigger values apply to moderately disturbed systems to provide a 95% level of species
           protection for marine waters.
          Environmental Protection (Water & Wetland Biodiversity) Policy 2019. 2019. Queensland
           Government.
          Noosa River environmental values and water quality objectives. 2022. DES.
          Queensland Water Quality Guidelines, Version 3, September 2009. 2013. DEHP.


     The Australian and New Zealand Guidelines for Fresh and Marine Water Quality by the Australian and
     New Zealand Environment and Conservation Council and Agriculture and Resource Management Council
     of Australia and New Zealand (ANZECC/ARMCANZ, 2000), has undergone review, with the publication of
     the 2018 version. The revised Australian and New Zealand Guidelines for Fresh and Marine Water Quality
     2018 is a joint initiative between the Australian and New Zealand Governments and Australian state and
     territory governments (ANZG, 2018) and supersedes the ANZECC/ARMCANZ 2000 publication. Where
     ANZECC/ARMCANZ (2000) is referenced, the relevant sections are still relevant and consistent with the
     updated ANZG 2018 publication, as referenced in the ANZG 2018 publication.

     The Queensland Water Quality Guidelines 2009 (DEHP, 2013) was made pursuant to the provisions of the
     Environmental Protection (Water) Policy 1999, now the Environmental Protection (Water & Wetland
     Biodiversity) Policy 2019 (the EPP(Water)), which is a subordinate legislation under the Environmental
     Protection Act 1994 and was developed as the State response to the ANZECC/ARMCANZ (2000)
     Guidelines. The EPP(Water) provides a framework for:


          Identifying environmental values for Queensland waters, and deciding the water quality objectives
           to protect or enhance those environmental values.
          Including the identified environmental values and water quality objectives under Schedule 1 of the
           EPP (Water).
     WQOs are long term goals for surface water quality management. They are indicators established for
     receiving waters to support and protect the designated Environmental Values (EVs) for those waters. DES
     (2022) describes that for slightly to moderately disturbed waters, the guideline values should be
     compared with the median of values at a test site, whilst ANZG (2018) stresses that the aquatic ecosystem
     guideline values are triggers to further action, are inherently conservative, and that the response to non‐
     compliance should match the magnitude and impacts (if any) of the exceedance.




ADG1451.22 Dewatering Management Plan_Rev0_28.02.23                                                       Page 6

Page 11

                                                                                                         ADG Consulting Pty Ltd


     Regardless of the WQOs adopted in this DMP, the General Environmental Duty set out in the EP Act is
     paramount, which requires that “a person must not carry out an activity that causes or is likely to cause
     environmental harm unless the person takes all reasonable and practicable measures to prevent or
     minimise the harm”.
4.3 Proposed water quality objectives
     The proposed water quality objectives that have been developed for the discharge of extracted
     groundwater from the site are provided in the Tables below. All water discharged from the site must
     comply with the discharge criteria provided in Table 2. In addition, the receiving water quality within a
     20 m radius of the discharge point entry to the receiving water shall comply with the receiving water
     criteria provided in Table 3. Receiving waters data will be assessed against background monitoring data
     if non‐compliant results are obtained at the receiving waters monitoring location.

     Table 2 Discharge criteria

                              Parameter                                                        Criteria

       Physico‐chemical
       pH (pH units)                                                                          6.5 – 8.51
       Dissolved oxygen (% saturation)                                                           ≥802
       Suspended solids (mg/L)                                                                  ≤501,2
       Turbidity (NTU)                                                                           ≤502
       Litter                                                                               None visible
       Totals metals (µg/L)
       Aluminium                                                                        No ANZG criteria / 2003

       Iron                                                                             No ANZG criteria / 3003

     Table notes:
     1. QWQG 2009 (2013) Refer to Table 8.2.1. Summary of design objectives for management of stormwater quality and flow –
        construction phase of development in Queensland.
     2. Typical discharge criteria recognised throughout Queensland & NSW.
     3. Criteria subject to anticipated Development Application (DA) notice and conditions by Noosa Shire Council.




     Table 3 Receiving waters criteria

                              Parameter                                                        Criteria

       Physico‐chemical
       pH (pH units)                                                                          7.8 – 8.31
       Dissolved oxygen (% saturation)                                                        85 – 1051
       Suspended solids (mg/L)                                                                   ≤141
       Turbidity (NTU)                                                                            ≤81
       Dissolved metals (µg/L)
       Aluminium                                                                   No relevant ANZG criteria available

       Arsenic                                                                                   2.32*
       Cadmium                                                                                   5.52
       Chromium                                                                                  4.42
       Copper                                                                                    1.32
       Iron                                                                        No relevant ANZG criteria available

       Lead                                                                                      4.42
       Nickel                                                                                     702




ADG1451.22 Dewatering Management Plan_Rev0_28.02.23                                                                       Page 7

Page 12

                                                                                                            ADG Consulting Pty Ltd



                               Parameter                                                           Criteria

       Zinc                                                                                           82
       Mercury                                                                                       0.42
       Totals metals (µg/L)
       Aluminium                                                                            No ANZG criteria / 2003

       Iron                                                                                 No ANZG criteria / 3003

     Table notes:
     1. DES (2022). Noosa River environmental values and water quality objectives (canal).
     2. ANZG (2018). Supersedes ANZECC/ARMCANZ (2000) ‐ Marine water trigger values for 95% species protection.
     3. Criteria subject to expected condition in Development Application (DA) notice by Noosa Shire Council.
     * = Insufficient data to derive a reliable trigger value. Low reliability value adopted (refer ANZECC/ARMCANZ (2000) Section
     8.3.7.

     Although ADG has not been provided a copy of the DA notice and conditions for the proposed
     development, based on previous dewatering projects in the Sunshine/Noosa Coast Region it is expected
     that total iron and aluminium concentrations as listed in Table 3 (above) are likely to be conditioned by
     Noosa Shire Council for compliance. It should be noted that these concentrations are considered to be
     onerous with respect to the risk‐based (worst‐case) bioavailable trigger value criteria contained in ANZG
     2018 & ANZECC/ARMCANZ (2000) for marine water (moderately disturbed) 95% species protection, and
     are likely to be difficult to achieve given the groundwater conditions encountered in the locality on
     previous dewatering projects on the Sunshine/Noosa Coast.

     Prior to discharge to the stormwater system or any waterway, discharges are to be tested to meet the
     requirements of the ANZG 2018 & ANZECC/ARMCANZ (2000) Guidelines for Fresh and Marine Water
     Quality. There is currently no chemical toxicant trigger value criteria available for total or dissolved (i.e.
     bioavailable) concentrations of aluminium or iron for marine or estuarine waters under the Australian
     and New Zealand Guidelines for Fresh and Marine Water Quality Guidelines (ANZG 2018 &
     ANZECC/ARMCANZ 2000 – i.e. ANZECC Guidelines) or the Guidelines for Managing Risks in Recreational
     Waters (NHMRC 2008), with regards to managing environmental impacts to the waterway.

     In addition, Section 5 (Guidelines for recreational water quality and aesthetics) of the ANZECC/ARMCANZ
     (2000) Guidelines (per section 5.2 thereof) was superseded by the Guidelines for Managing Risks in
     Recreational Water in 2008 (NHMRC, 2008). Therefore, a reference to the ANZECC/ARMCANZ (2000)
     Guidelines is by association and extension a reference to the current 2008 NHMRC Guidelines. The 2008
     NHMRC Guidelines contain no criteria for aluminium, and only includes an aesthetic criterion for iron –
     noting this is an aesthetic criterion derived from the Australian Drinking Water Guidelines on the basis of
     ingesting 2L of the recreational water solution per day. ANZECC/ARMCANZ (2000) Section 5.2.3.3, notes
     that as a general guideline, under Toxic Chemicals, ‘Higher concentrations of toxicants may be tolerated
     occasionally if it assumed that no person will ingest more than a maximum of 100 mL water during a
     normal swimming session (NHMRC 1990) compared with 2L/d for potable water’, and Section 3.1.1.3,
     under Risk based approach of the guidelines, ‘The guideline trigger values are based on bioavailable
     concentrations, and hence are relatively conservative when compared with total concentrations in the
     field, so the use of the decision frameworks will increase guideline concentrations in most cases’.
     Therefore, any chemical toxicant trigger values would require reassessment and likely increase upwards
     of any ANZG 2018 &/or ANZECC/ARMCANZ (2000) Guideline trigger values due to the slightly to
     moderately disturbed nature (and thereby reduced sensitivity) of the receiving waters.

     In conditioning more onerous criteria, rather than the available marine chemical toxicant trigger value
     criteria contained within the ANZG/ANZECC Guidelines, an unachievable constraint may be placed on the
     development. This DMP has allowed for contingency measures to be incorporated into the treatment
     and discharge system if required, including silt curtains to be installed within the receiving waterway
     surrounding the discharge location, or further onsite treatment measures such as filtration, to prevent
     and/or minimise as far as reasonably practicable the potential for release of suspended solid loads into
     the broader receiving waterway.


ADG1451.22 Dewatering Management Plan_Rev0_28.02.23                                                                                 Page 8

Page 13

                                                                                      ADG Consulting Pty Ltd


5    Dewatering methodology
5.1 Basement excavation and shoring
     It is understood that the excavation/basement perimeter will be stabilised along the perimeter of the
     basement excavations using a contiguous secant pile wall (refer to supplied indicative basement design
     at Appendix C). Excavations to facilitate the construction of the basement will extend to approximately
     2.3 m below ground level, which corresponds to a maximum elevation of ‐0.7 m AHD. Localised deeper
     excavations may be required for construction of other structural elements (i.e. footings & pile caps).

     All excavated spoil from depths between 1.5 to 2.5 mbgl within the excavation footprint will be
     appropriately neutralised with lime and validated in accordance with recommendations by PG in the ASS
     Investigation Report (PG, 2022).

     It is expected that the development will include a ‘tanked’ basement to prevent the requirement for a
     permanent dewatering facility at the site.
5.2 Groundwater extraction
     Dewatering is anticipated to be undertaken using a series of 6.0 m length, 40 mm diameter PVC spears
     installed to below maximum excavation depth at 1.5 m intervals around the internal
     perimeter of the basement excavation (refer to supplied indicative shoring design at Appendix C).

     The basement excavation must be dewatered to a minimum of approximately 1.0 m below the deepest
     point of excavation to allow construction to be undertaken in dry conditions. The water table is therefore
     expected to be lowered by a minimum of approximately 2.3 m to around ‐1.7 m AHD. It is expected that
     the cone of depression in the standing groundwater table will be predominantly limited to within the site
     boundaries.

     It is proposed that the development will include a ‘tanked’ basement to prevent the requirement for a
     permanent dewatering facility at the site. Similarly, no permanent groundwater dewatering is proposed
     or likely to occur as a result of the development, with all services and pipework proposed to be situated
     above standing groundwater elevations (that is, at elevations above 0.6 mAHD) and subject to the
     nominated hold points at Section 5.7. Where any deviation is proposed from this arrangement, all
     pipework within the saturated zone, that outlets direct to waterways must be fitted with buried
     headstocks at suitable intervals to prevent ongoing dewatering of groundwater along pipework bedding.
5.3 Extraction/discharge rates and volume
5.3.1 Dewatering extraction calculation based on subsurface soil profile
     The dewatering extraction rate, area of influence and cone of depression has been estimated using the
     Western Australian Department of Water and Environmental Regulation Cone of Depression Calculator.

     The calculation results are based on the following parameters (as provided by SCG) and known site‐
     specific conditions. The following is applicable to the basement excavations spanning across the lot:

           Approximate length of excavation = 35 m
           Approximate width of excavation = 30 m
           Reduction in depth of groundwater across the basement footprint/excavation = 2.3 m
           Approximate depth of saturated aquifer = 10 m (standardised conservative value applied)

     The soil profile of comprised predominantly of fine to medium grained silty sands, which has a hydraulic
     conductivity of 8.2 m/day, or equivalent 0.0000949 L/sec (WA Calculator). The results of the calculation
     are shown in Table 4 below, and a copy of the output is provided in Appendix D.




ADG1451.22 Dewatering Management Plan_Rev0_28.02.23                                                      Page 9

Page 14

                                                                                            ADG Consulting Pty Ltd



     Table 4 Dewatering extraction rate results

                               Output                                                Result

      Effective radius of dewatering spears (m)                                        18
      Dewatering radius of influence (m)                                               67
      Discharge rate (L/sec)                                                            9
      Discharge rate (L/hr)                                                          32,400
      Establishment of cone of depression (hours)                                      76


     Based on the above inputs, a groundwater flow rate of approximately 9 L/sec or 540 L/min or 32,400 L/hr
     has been predicted for the development, with the estimated cone of depression radius to be
     predominantly limited to within 3 m of the secant pile shoring wall. Flow rates are predicted to be highest
     during initial drawdown of the groundwater table within the basement excavation footprint, and
     reducing to approximately 6 L/sec following establishment of the cone of depression within the
     excavation. Flow rates may fluctuate due to tidal variations, generally approximately ± 0.5 m, and will
     also be influenced by rainfall and surface water collection within the basement excavation footprint
     noting the underlying predominantly sand profile encountered during geotechnical investigations.

     Regardless of the contractor employed, groundwater treatment systems should be installed with
     capability for treating flow rates of up to 10 to 12 L/sec, as a contingency against higher than anticipated
     flow rates exceeding the estimated 6 to 9 L/sec as a result of varying ground conditions across the extent
     of excavation.

     However, it should be noted that the WA Calculator provides a conservative assessment of inflows to an
     excavation footprint based on area and depth, but does not take account of the method of perimeter
     piling i.e. steel sheet pile, which will inhibit lateral inflows. Also note that the cone of depression radius
     measure includes water table depressions of 1 mm depth or more, so any significant depression of the
     water table is limited to much closer to the spear point dewatering spears (generally within 3 to 10 m
     from the shoring wall in fine‐medium grained sands, depending on density of the strata).
5.4 Dewatering duration
     Dewatering will be necessary throughout the basement construction phase, which is expected to require
     dewatering for approximately 10 to 12 weeks. To minimise the potential impacts during construction of
     short‐term dewatering, periods of active dewatering will be minimised as much as possible. However,
     ADG notes that once active dewatering has commenced, dewatering will not be able to be ceased until
     both: a) the basement hydrostatic uplift forces have been compensated to the satisfaction of the
     consulting RPEQ engineer; and b) potential hydraulic loading on the external face of the sheet pile shoring
     system has been compensated to the satisfaction of the consulting RPEQ engineer and shoring
     contractor.
5.5 Groundwater drawdown
     Groundwater drawdown caused by dewatering has the potential to create settlement in unconsolidated
     sediments and loose sands. It is noted that dilapidation reports for surrounding structures and services
     have been undertaken which were not supplied to ADG for the purposes of preparing this DMP, and are
     to be provided to Council separately from this DMP.

     Groundwater drawdown may also oxidise potential acid sulfate soils within the cone of depression,
     subsequently producing acidic groundwater conditions and mobilising heavy metals. Monitoring of the
     extracted untreated groundwater will be undertaken to detect potential in‐situ oxidation, as required
     and at the frequencies stated in Section 6.5.2. Groundwater monitoring bores for groundwater level
     gauging external to the excavation footprint are unable to be established and monitored prior to and
     during construction on the site, due to limited space (SCG Consulting Engineers).


ADG1451.22 Dewatering Management Plan_Rev0_28.02.23                                                         Page 10

Page 15

                                                                                      ADG Consulting Pty Ltd



     A plan showing the proposed shoring and dewatering system is provided at Appendix C.
5.6 Groundwater treatment
     All extracted groundwater will be treated on‐site using available technologies prior to discharge to the
     stormwater network. The following treatment measures will be adopted, and will be installed and
     operational prior to the commencement of dewatering:

     1.    A groundwater pH buffering treatment system (primary treatment)
     2.    A sedimentation tank to provide additional residence time and sedimentation (secondary
           treatment).
     3.    Installation of fine media filtration to retain suspended sediments and/or heavy metals (tertiary
           treatment), if required.

     Details of the treatment systems and methodologies are provided in Section 6 of this report.

     Note: Consideration should be taken, regarding placement of treatment gear on site to enable easy
     cleaning and maintenance throughout the dewatering phase for the project. Consider the potential
     requirement for regular de‐sludging of sedimentation tank/s to suitable area onsite, if available (cost
     minimisation).
5.7 Nominated Hold Points
     In accordance with anticipated DA Conditions, nominated hold points to be enacted during construction
     have been proposed to facilitate for certification by the suitably qualified person experienced with Acid
     Sulfate Soils, as well as Council Development Engineer to ensure all possible avenues for continual
     dewatering below permanent groundwater level, including around pipework bedding that outlet to
     waterways, are appropriately sealed. The nominated hold points regarding dewatering for this project
     are:
     1. Prior to commencement of dewatering/initial pump out
     2. At finished excavation level, prior to blinding layer application
     3. External to basement service installation trench opening/s prior to backfilling.

     The above nominated hold points are subject to confirmation by the consulting engineer, and liaison with
     council representatives and the Site Manager.




ADG1451.22 Dewatering Management Plan_Rev0_28.02.23                                                    Page 11

Page 16

                                                                                         ADG Consulting Pty Ltd


6    Water quality management
6.1 Responsibility
     The Site Manager is ultimately responsible for implementing the water quality management procedures
     described in this DMP.
6.2 Operational policy
     To prevent impacts on the receiving waters by effectively treating all extracted groundwater prior to
     discharge from the site.
6.3 Performance criteria
     The performance criteria for the discharge of extracted groundwater are the water quality objectives
     provided in Table 2 and Table 3 in Section 4 of this report. Both the discharge and receiving waters (within
     a 20 m radius of the stormwater discharge point) will be assessed against the WQOs to ensure that the
     environmental values of the waterway are maintained. Receiving waters data will also be assessed
     against background monitoring data if non‐compliant results are obtained at the receiving waters
     monitoring location.
6.4 Implementation strategy
     All extracted groundwater will be treated on‐site using available technologies prior to discharge to the
     stormwater network. The treatment system described in Section 6.4.1 will be adopted, installed and
     operational prior to the commencement of dewatering.
6.4.1 Groundwater treatment systems
     Subject to final appointment of shoring and dewatering contractors (who all generally have different
     treatment systems), the following treatment systems are generally proposed for dewatered groundwater
     treatment prior to discharge. Regardless of the contractor employed, groundwater treatment systems
     should be installed with capability for treating flow rates of up to 10 to 12 L/sec, as a contingency against
     higher than anticipated flow rates exceeding the estimated 6 to 9 L/sec as a result of varying ground
     conditions across the extent of excavation.

     Primary treatment
     A groundwater treatment system will be installed to provide primary treatment of the extracted
     groundwater. The system will provide the following capabilities:

     1.    A baffled treatment tank with 5 kL minimum capacity
     2.    Automated in‐line chemical dosing systems for the addition of buffering solutions and coagulants
     3.    A filtration system to reduce fine particulates (if required)
     4.    Emergency response alarms for non‐routine situations.

     Based on the estimated extraction rate, this system will provide approximately nine minutes contact time
     during the initial chemical dosing, prior to secondary treatment using a sedimentation tank. Primary
     treatment tank will be vertically stacked on the secondary treatment tank wherever practicable to
     minimise site area required for groundwater treatment equipment.
     Secondary treatment
     A 23 kL sedimentation tank will be utilised to provide the necessary residence time for secondary
     treatment of the groundwater prior to discharge to the stormwater system. Based on the estimated
     groundwater extraction rate of approximately 32,400 L/hr (equivalent 540 L/min) from Section 5.3.1 of
     this Report, one sedimentation tank will provide approximately forty‐two minutes retention time
     following primary treatment of the extracted groundwater. This is considered to be sufficient secondary
     settling / retention time based on extensive prior experience on other sites in similar ground conditions.




ADG1451.22 Dewatering Management Plan_Rev0_28.02.23                                                        Page 12

Page 17

                                                                                          ADG Consulting Pty Ltd


     Tertiary treatment – may be required following initial testing of extracted groundwater.
     A filtration treatment system with specialised fine filtration media and chlorine dosing will be utilised to
     provide the required heavy metal removal (specifically for total and dissolved iron) where not
     precipitated and retained within the sedimentation tank/s (secondary treatment). This treatment system
     will provide tertiary treatment of the groundwater prior to offsite discharge. This type of fine media
     filtration treatment system is a forced‐flow system under pressure, and generally capable of treating flow
     rates of up to 20 L/sec per filtration unit (therefore residence time is inconsequential to treatment quality
     achieved).

     Tertiary treatment will only be required if the required water quality is unable to be achieved following
     primary and secondary stages of treatment. Subject to the results of field and laboratory testing during
     the pre‐discharge monitoring event.
6.4.2 Dewatering strategy
     The Site Manager, Dewatering Contractor and ADG Consulting must formulate a dewatering strategy to
     ensure that the dewatering treatment system is sufficient to meet the requirements of the project and
     that the necessary equipment can be accommodated within the site prior to the commencement of
     dewatering.

     Where the construction of the proposed development requires occupation of the road reserve (verge
     area and/or road formation) for either short term or long term, a road reserve permit must be obtained
     from Council prior to any occupation of the road reserve.
6.4.3 Initial pump‐out
     Prior to discharge of any extracted groundwater to the canal system, the following pre‐dewatering
     procedure will be undertaken:

     1. The basement area will be excavated down to the standing groundwater level.
     2. The initial dewatering discharge will be directed (via the treatment systems) into the excavation and
        allowed to infiltrate/recharge the aquifer. This process will provide initial clarification of the extracted
        groundwater as disturbed sediment loads are typically reduced following the initial pump‐out.
     3. Samples of the treated groundwater will be recovered and analysed for the parameters detailed in
        Table 2 and Table 3.
     4. The extracted groundwater will be directed into the canal system following confirmation that the
        water quality complies with the discharge criteria.
6.5 Monitoring
6.5.1 Visual monitoring
     Visual inspections of the site and dewatering equipment shall be undertaken daily by the Site Manager
     to identify the following:
          Quantity of chemical product within the dosing system
          Effective operation of all dewatering treatment equipment
          Short circuiting of water around baffles and filter media in sediment tanks, where required to be
           installed.
          Visible hydrocarbon sheens and odours
          Green blue or extremely clear water indicating high levels of dissolved aluminium.
6.5.2 Water quality monitoring
     Water quality monitoring will be undertaken for the duration of dewatering activities at the site by a
     suitably qualified and independent person. The monitoring will include analysis of the extracted
     groundwater, treated discharge water and off‐site monitoring in the receiving waters (in the mixing zone
     within a 20 m radius of the discharge point). The exact location within the receiving waterway (Noosa


ADG1451.22 Dewatering Management Plan_Rev0_28.02.23                                                          Page 13

Page 18

                                                                                       ADG Consulting Pty Ltd


     River) is to be confirmed, however it is anticipated to be directly north of the site. Background water
     quality monitoring of field parameters will also be conducted during each sampling event, if applicable.
     Background samples will be recovered from the river, either upstream or downstream from the receiving
     water location (tide dependant).

     The proposed monitoring locations are shown in Figure 1, Appendix A are a subject to confirmation
     following mobilisation of dewatering gear to site.

     Monitoring will be undertaken at the following frequencies:


          Daily monitoring of field parameters (pH, electrical conductivity, dissolved oxygen, temperature and
           turbidity) in the treated discharge water and pH of the untreated extracted groundwater (to
           determine potential acidification). Daily monitoring will be undertaken by a suitably trained site
           employee under the supervision of the Site Manager.
          Weekly monitoring of field parameters (pH, electrical conductivity, dissolved oxygen, temperature
           and turbidity) in the untreated extracted groundwater, treated discharge water, receiving waters
           and background waters by ADG Consulting.
          Weekly laboratory analysis of treated discharge water and receiving waters for suspended solids
           and dissolved 0.45µm filterable metals (aluminium, arsenic, cadmium, chromium, copper, iron, lead,
           nickel, zinc and mercury). Total aluminium and iron will also be analysed for, if required.
          Pre‐discharge/initial monitoring of field parameters (pH, electrical conductivity, dissolved oxygen
           and oxidation‐reduction potential) in the extracted groundwater (prior to treatment) to assess
           changes in groundwater chemistry associated with PASS oxidation.
          Pre‐discharge/initial laboratory analysis of extracted groundwater (prior to treatment) for
           suspended solids, dissolved 0.45µm filterable metals (aluminium, arsenic, cadmium, chromium,
           copper, iron, lead, nickel, zinc and mercury) and for soluble sulfate and chloride to assess changes
           in groundwater chemistry associated with PASS oxidation. Total aluminium and iron will also be
           analysed, if required.
          Laboratory analysis of untreated groundwater would also be performed periodically (monthly) if
           changes in untreated groundwater pH levels are detected that may indicate local acidification, and
           to determine any changes in local groundwaters that may require further investigation of potential
           environmental impacts.
     All samples will be recovered by a suitably qualified Environmental Scientist and submitted to a National
     Association of Testing Authorities (NATA) accredited laboratory for analysis.
6.5.3 Monitoring responsibilities
     The persons responsible for undertaking the compliance monitoring described in Section 6.5.2 above are
     shown in Table 5.

     Table 5 Monitoring responsibilities

                           Activity                        Frequency        Responsibility         Person

       Monitoring of field parameters in discharge water
                                                             Daily          Site Manager        Site Manager
       and untreated extracted groundwater

       Monitoring of field parameters in untreated
                                                                                               Environmental
       extracted groundwater, discharge water,              Weekly         ADG Consulting
                                                                                                 Consultant
       receiving waters and background waters

       Laboratory analysis of samples recovered from                                           Environmental
                                                            Weekly         ADG Consulting
       discharge water and receiving waters                                                      Consultant




ADG1451.22 Dewatering Management Plan_Rev0_28.02.23                                                     Page 14

Page 19

                                                                                       ADG Consulting Pty Ltd



       Monitoring of field parameters in extracted                                            Environmental
                                                           Weekly           ADG Consulting
       groundwater (pre‐treated)                                                                Consultant

       Laboratory analysis of samples recovered from   Initially, then as                     Environmental
                                                                            ADG Consulting
       extracted groundwater (pre‐treated)                 required                             Consultant

6.6 Maintenance
     The groundwater treatment systems must be regularly maintained. Maintenance must include:


          Regular cleaning and or replacement of the filters within the filtration unit, where required to be
           installed.
          Regular removal of sediment from the sedimentation tank. The sediment must be either returned
           to the excavation pit for dewatering and bulking out with excavated material, or removed from the
           site by a licensed liquid waste contractor.
          Regular check of the dosing system and top‐up of buffering solutions and flocculants.
6.7 Reporting
     Dewatering management procedures and monitoring results will be reviewed by ADG Consulting weekly
     to ensure that the treatment procedures are effective, and that the receiving waters are not being
     impacted by the extracted groundwater being discharged.

     The following reporting procedures will be adopted:


          A summary report will be prepared upon completion of the initial pre‐discharge monitoring. The
           report will be submitted to the Site Manager, Dewatering Contractor, and NSC upon request.
          Weekly interim reports will be prepared upon receipt of laboratory data for each round of ongoing
           compliance monitoring. The interim reports will display all data obtained during the previous
           monitoring event, and provide comments and recommendations based on the results.
          A dewatering compliance report will be prepared on completion of the project (upon request).
     The above reports will be prepared by ADG Consulting and provided to the Site Manager and Dewatering
     Contractor as they become available. The reports will include all water quality results and comparison to
     the WQOs, corrective actions and recommendations made to the Site Manager and Dewatering
     Contractor during the monitoring period.

     The Site Manager must keep records of complaints, volumes of chemicals used, and treatment methods
     employed. These records must be available on‐site at all times and submitted to NSC by the Site Manager
     upon request.
6.8 Contingencies
     If water quality monitoring indicates ongoing exceedances of the performance criteria, and the water
     quality objectives for the receiving waters cannot be met, then corrective actions will be adopted as
     necessary. Possible contingencies may include one or more of the following:


          Installation of additional sedimentation tanks to provide increased residence time and assist with
           the retention of precipitated iron hydroxides, other heavy metals and/or suspended sediments.
          Installation of additional flocculant and/or coagulant dosing systems to assist in precipitation of
           suspended sediments and/or heavy metals.
          Installation of activated carbon filtration or other fine media filtration to retain suspended
           sediments and/or heavy metals.



ADG1451.22 Dewatering Management Plan_Rev0_28.02.23                                                    Page 15

Page 20

                                                                                        ADG Consulting Pty Ltd


          Install a floating sediment curtain/s around the stormwater termination point in the receiving
           waterway to prevent unsightly plumes and contain sediment and/or heavy metals for periodic
           removal (subject to approval by Noose Shire Council).
          Preventive and corrective actions shall be taken in the event that groundwater monitoring
           observations indicate that unexpected groundwater contamination has been encountered during
           dewatering. The most appropriate action(s) shall be dependent on the stage of construction and
           risk of adverse impacts to groundwater users and the receiving environment.
          Any modification to the dewatering system and pumping rates shall be in consultation with a
           suitably qualified scientist/geotechnical/engineer.
          Following heavy rainfall all ponded surfaces waters are to meet discharge criteria (Table 3) prior to
           offsite discharge. Where discharge criteria not met, Site Manager to obtain approval from
           Dewatering Contractor regarding treating surface waters with treatment gear before offsite
           discharge.
          Pumping systems and shoring works to be maintained in fit for purpose state by Dewatering
           Contractor and/or shoring contractor. In the event that dewatering equipment has failed and is
           likely to cause a significant impact on the environment, or surrounding properties (i.e. flooding) the
           Dewatering Contractor is to be contacted immediately. The Principal Contractor, in consultation
           with the Dewatering Contractor shall be responsible in rectifying the failure in a practicable time
           frame to minimise potential impacts. Equipment, spare parts, materials and tools necessary to
           manage aspects of the system/s which present a high risk of significant impacts in the event of
           failure (if any) shall be readily available.
          Construction vibrations could potentially cause settlement in the loose upper level sands, thereby
           damaging nearby structures founded in these strata. Prior to commencement of construction on
           site (including staged works), it is recommended that a detailed dilapidation survey be undertaken
           to establish the condition of all existing adjacent structures, roads and services.




ADG1451.22 Dewatering Management Plan_Rev0_28.02.23                                                       Page 16

Page 21

                                                                                        ADG Consulting Pty Ltd


7    Noise & odour management
7.1 Responsibility
     The Project Manager is responsible for ensuring the appropriate management of noise and odour during
     dewatering operations.
7.2 Operational policy
     To minimise noise and odour emissions generated from the site during dewatering.
7.3 Performance criteria
     The appropriate criteria to measure the performance of dewatering management at the site are provided
     below.
     1.    No noise or odour related complaints received from neighbouring residents or the community.
     2.    No degradation of air quality due to fumes or odours emanating from the dewatering process.
7.4 Implementation strategy
     Noise and odour emissions will be managed as described in the following sections.
7.4.1 Noise
     All dewatering equipment must be operated appropriately and maintained in good working order. All
     dewatering systems and plant must be fitted with the appropriate noise reduction equipment to comply
     with the performance criteria. Non‐complying dewatering plant will be replaced or repaired as necessary.

     It is proposed to employ noise mitigation strategies including use of electric pumps and dewatering
     systems rather than diesel powered equipment. Noise attenuation blankets and screens will be installed
     around noise generating dewatering pumps and equipment where practicable. Noise monitoring
     equipment (unattended) will be installed by the site manager prior to commencement and monitored for
     the duration of dewatering.
7.4.2 Odour
     All dewatering plant must be fitted with the appropriate emission reduction devices. Where practicable,
     all dewatering plant will be sealed to prevent the release of odours to the atmosphere. Fine mist odour
     control sprays will be applied to reduce offensive odours if complaints are received from neighbouring
     residents.
7.5 Monitoring
     An inspection of the site and dewatering equipment shall be undertaken daily by the Site Manager to
     identify the following:
          Excessive noise being generated by the dewatering systems and plant; and
          Strong or offensive odours being generated by the dewatering equipment and/or extracted
           groundwater.
     Noise monitoring equipment (unattended, continuous logging) is proposed to be installed by the Site
     Manager prior to commencement and monitored for the duration of dewatering. The Environmental
     Protection (Noise) Policy 2019 (EPP(Noise)) identifies specific acoustic quality objectives (noise criteria)
     to assist in preventing significant impacts on noise sensitive receptors and as a guide to long‐term
     acoustic quality for sensitive receptors. The primary EPP(Noise) criteria relevant to this investigation is
     outside a dwelling (i.e. adjacent dwellings), which should not have noise at levels in the daytime or
     evenings greater than 50dB(A) LAeq,adj,1hr. This means that noise levels in the receiving environment
     outside of nearby dwellings (i.e. on balconies) should not exceed an equivalent sound energy as would
     be received from a one hour continuous sound of 50 decibels on the A‐weighted scale (adjusted for tonal
     character perceptible by the human ear).




ADG1451.22 Dewatering Management Plan_Rev0_28.02.23                                                       Page 17

Page 22

                                                                                      ADG Consulting Pty Ltd


     While this report has not been generated for the purpose of assessing compliance with the requirements
     of workplace health and safety legislation, it is noted that a person conducting a business or undertaking
     must ensure that workers are not exposed to noise that exceeds the exposure standard for noise. The
     exposure standard for noise is defined in the Work Health & Safety Regulation 2011 (QLD) as LAeq,8h of
     85 dB(A) or an LC,peak of 140 dB(C). As such, it is considered appropriate to adopt these exposure
     standards to assess average and peak noise generated at the site with the potential to affect exposure
     levels of nearby sensitive receptors (noting there will be some attenuation between source and receptors
     and actual noise experienced by receptors would need to be measured at the receptor location).
7.6 Reporting
     The Site Manager must keep records of complaints, monitoring records (including continuous noise
     monitoring data), and corrective and preventive actions/methods employed for noise abatement. These
     records must be available on‐site at all times and submitted to NSC by the Site Manager upon request.
7.7 Contingencies
     If noise levels consistently exceed the performance criteria, temporary acoustic barriers will be
     constructed around the offending dewatering systems and plant. Odour control sprays will be applied as
     necessary to mask odour emissions if complaints are received from neighbouring residents. This may
     include the direct injection of deodorisers to the groundwater treatment system.




ADG1451.22 Dewatering Management Plan_Rev0_28.02.23                                                     Page 18

Page 23

                                                                                         ADG Consulting Pty Ltd


8    Limitations
     ADG Consulting Pty Ltd has prepared this report for Craig & Nathan Francis and SCG Consulting Engineers
     in accordance with the agreed scope of work. The services performed by ADG have been conducted in a
     manner consistent with the normal level of care and expertise exercised by members of the
     environmental consulting profession. No other warranty or guarantee, expressed or implied, is made as
     to the professional advice included in this report.

     This report is solely for the use of Craig & Nathan Francis and SCG Consulting Engineers and ADG accepts
     no responsibility for the use of any part of this report for any other purpose or by third parties, as it may
     not contain sufficient information for the purposes of other parties or users. This report must only be
     presented in full, and may not be used for any other objective, except where prior written approval is
     obtained from ADG. This report does not comment on legal obligations, as legal advice can only be given
     by qualified legal practitioners.

     The information contained in this report is provided to minimise potential impacts on the receiving
     environment, however implementation of the described management procedures does not guarantee
     that the objectives will be achieved.

     The information contained in this report is considered to be accurate at the date of issue. Subsurface
     conditions, including contaminant concentrations can change in space and time, either through natural
     processes or by the accidental or intentional addition of contaminants to a site. Where conditions
     encountered subsequently at the site are significantly different from those reported herein, ADG must
     be notified and be provided the opportunity to review the conclusions and recommendations of this
     report.




ADG1451.22 Dewatering Management Plan_Rev0_28.02.23                                                        Page 19

Page 24

                                                                                   ADG Consulting Pty Ltd


9    References
     ANZG 2018. Australian and New Zealand Guidelines for Fresh and Marine Water Quality. Australian and
     New Zealand Governments and Australian state and territory governments, Canberra ACT, Australia.

     ANZECC/ARMCANZ. 2000. Australian and New Zealand Guidelines for Fresh and Marine Water Quality.
     Australian and New Zealand Environment and Conservation Council and Agriculture and Resource
     Management Council of Australia and New Zealand.

     DES. 2019. Environmental Protection (Water & Wetland Biodiversity) Policy 2019. Department of
     Environment and Science, Queensland Government. Brisbane, Queensland, Australia.

     DEHP. 2013. Queensland Water Quality Guidelines 2009, Version 3. Department of Environment and
     Heritage Protection. Brisbane, Queensland, Australia.

     DES. 2022. Noosa River environmental values and water quality objectives. Department of Environment
     and Science (DES), Queensland Government.

     DES. 2018. Monitoring and Sampling Manual 2018, Version 2 June 2018. Department of Environment and
     Science. Brisbane, Queensland, Australia.

     DNRME. 2002. Redcliffe to Teewah – Map 2 1:25,000. Queensland Department of Natural Resources and
     Mines. Brisbane, Queensland, Australia.

     Government of Western Australia. 2011 (Amended 2015). Cone of Depression. Department of Water and
     Environmental Regulation. Accessed 28 February 2023, https://www.der.wa.gov.au/your‐
     environment/acid‐sulfate‐soils/66‐cone‐of‐depression.

     NHMRC. 2018. Guidelines for Managing Risks in Recreational Water. Australian Government, National
     Health and Medical Research Council.

     Noosa Shire Council. Noosa Council Interactive Mapping, Stormwater Infrastructure. Accessed 28
     February 2023.
     https://enterprise.mapimage.net/IntraMaps910/?project=Public&module=Property%20Recreation%20
     Utilities&configId=64251f07‐9411‐4a61‐930e‐2bd9b45d8fff&startToken=8fb07456‐4db7‐45a7‐89df‐
     64e9b5a76aff&touch=false

     Pacific Geotech Pty Ltd. November 2022. Acid Sulfate Soil Investigation, Proposed Residential
     Development, 128 – 132 Gympie Terrace, Noosaville. Ref: PG‐9236, 2022‐10‐31, ASR VER 1.

     Pacific Geotech Pty Ltd. November 2022. Geotechnical Investigation, Proposed 128 – 132 Gympie Terrace,
     Noosaville. Ref: PG‐9236, 2022‐11‐08, GR VER 1.




ADG1451.22 Dewatering Management Plan_Rev0_28.02.23                                                 Page 20

Page 25

                                                                      ADG Consulting Pty Ltd




Appendix A:         Figures
                    Figure 1 Site and proposed monitoring locations




ADG1451.22 Dewatering Management Plan_Rev0_28.02.23

Page 26

Figure 1 - Site and proposed monitoring locations                                                                            A product of

Lots 2 & 3 on MCH3881, 130-132 Gympie Terrace, Noosaville, QLD
26°23'47"S 153°3'4"E                                             26°23'47"S 153°3'25"E




                                                                                              Legend located on next page




                                                                                                                        0                      50 metres
                                                                                                                               Scale: 1:1945

                                                                                                                               Printed at: A3
                                                                                                                           Print date: 28/2/2023
                                                                                                                 Not suitable for accurate measurement.
                                                                                                              Projection: Web Mercator EPSG 102100 (3857)
                                                                                          For more information, visit https://qldglobe.information.qld.gov.au/help-info/Contact-
                                                                                                                                   us.html
                                                                                         Includes material © State of Queensland 2023. You are responsible for ensuring that
                                                                                         the map is suitable for your purposes. The State of Queensland makes no
                                                                                         representation or warranties in relation to the map contents and disclaims all liability.
                                                                                         If imagery is displayed, imagery includes material © CNES reproduced under license
                                                                                         from Airbus DS, all rights reserved © 21AT © Earth-i, all rights reserved, © Planet Labs
                                                                                         PBC, 2023




26°24'2"S 153°3'4"E                                               26°24'2"S 153°3'25"E                                 Department of Resources

Page 27

Figure 1 - Site and proposed monitoring locations
Lots 2 & 3 on MCH3881, 130-132 Gympie Terrace, Noosaville, QLD
   Legend                                                                  Attribution



                                                                       Includes material © State of Queensland (Department of Resources); ©
    Registered water bores [RDMW           Places: My Places           Commonwealth of Australia (Geoscience Australia); © 21AT, © Earth-i, all rights
    and private]                                                       reserved, 2023.
                                              Site Discharge
                                                                       © State of Queensland (Department of Resources) 2021
       Artesian bore                          Receiving Waters (TBC)
       Artesian bore (abandoned but                                    © State of Queensland (Regional Development, Manufacturing and Water) 2021
                                              Background Waters tide
    useable)                               dependent (TBC)             © State of Queensland (Department of Resources) 2022
       Artesian bore (abandoned and           Background Waters tide
    destroyed)                             dependent (TBC)
       Artesian bore, ceased to flow
                                           Cities and Towns
       Artesian bore, ceased to flow
    (abandoned but useable
                                           Road Crossing
       Artesian bore, ceased to flow
    (abandoned and destroyed)                 Bridge
       Sub-artesian facility                  Tunnel
       Sub-artesian facility (abandoned
                                           Road
    but useable)
       Sub-artesian facility (abandoned       Highway
    and destroyed)                            Main
       Surface water facility                 Local
       Surface water facility (abandoned      Private
    but useable)
       Surface water facility (abandoned
    and destroyed)

    Places: Land parcel

       2MCH3881
       3MCH3881

    Railway

Page 28

                                                      ADG Consulting Pty Ltd




Appendix B:         DRDMW licenced bore search




ADG1451.22 Dewatering Management Plan_Rev0_28.02.23

Page 29

DRDMW Licensed Bore Search                                                                A product of

500 m radius
26°23'46"S 153°3'2"E         26°23'46"S 153°3'26"E




                                                          Legend located on next page




                                                                                      0                    50 metres
                                                                                           Scale: 1:2256

                                                                                           Printed at: A3
                                                                                       Print date: 28/2/2023
                                                                             Not suitable for accurate measurement.
                                                                          Projection: Web Mercator EPSG 102100 (3857)
                                                      For more information, visit https://qldglobe.information.qld.gov.au/help-info/Contact-
                                                                                               us.html
                                                     Includes material © State of Queensland 2023. You are responsible for ensuring that
                                                     the map is suitable for your purposes. The State of Queensland makes no
                                                     representation or warranties in relation to the map contents and disclaims all liability.
                                                     If imagery is displayed, imagery includes material © CNES reproduced under license
                                                     from Airbus DS, all rights reserved © 21AT © Earth-i, all rights reserved, © Planet Labs
                                                     PBC, 2023




26°24'3"S 153°3'2"E           26°24'3"S 153°3'26"E                                 Department of Resources

Page 30

DRDMW Licensed Bore Search
500 m radius
   Legend                                                         Attribution



                                                              Includes material © State of Queensland (Department of Resources); ©
    Registered water bores [RDMW           Road crossing      Commonwealth of Australia (Geoscience Australia); © 21AT, © Earth-i, all rights
    and private]                                              reserved, 2023.
                                              Bridge
                                                              © State of Queensland (Department of Resources) 2021
       Artesian bore                          Tunnel
       Artesian bore (abandoned but                           © State of Queensland (Regional Development, Manufacturing and Water) 2021
    useable)
                                           Road
                                                              © State of Queensland (Department of Resources) 2022
       Artesian bore (abandoned and           Highway
    destroyed)                                Main
       Artesian bore, ceased to flow          Local
                                              Private
       Artesian bore, ceased to flow
    (abandoned but useable
                                           Cities and Towns
       Artesian bore, ceased to flow
    (abandoned and destroyed)
       Sub-artesian facility               Railway
       Sub-artesian facility (abandoned
    but useable)
       Sub-artesian facility (abandoned
    and destroyed)
       Surface water facility
       Surface water facility (abandoned
    but useable)
       Surface water facility (abandoned
    and destroyed)

    Places: Land parcel

       2MCH3881
       3MCH3881

    Places: My Places

       200 m radius

Page 31

                                                         ADG Consulting Pty Ltd




Appendix C:         Basement Installation Plan (Draft)




ADG1451.22 Dewatering Management Plan_Rev0_28.02.23

Page 32

 

DRAWING SIZE — At

 

HEIGHT DATUM

LOT 2 & 3 ON MCH3881
Level Datum AHD iI
Level Origin PM 105735, RL 4.577

Gympie Tce, Noosaville

Survey information provided by
Max Watterson & Associates

 

 

 

 

SITE _DEWATERING

— THE SITE IS TO BE CONSTANTLY DE-WATERED UNTIL THE GROUND
LEVEL SUSPENDED SLAB IS POURED.

— THE DESIGN AND INSTALLATION OF THE DEWATERING SYSTEM IS TO
BE BY A SPECIALIST CONTRACTOR.

—APPROX GROUND WATER TABLE OF 1.0m BELOW EXISTING GROUND
LEVEL. SEASONAL & TIDAL VARIATIONS NOT CONSIDERED

—GIVEN THE CLOSE PROXIMITY TO THE NOOSA RIVER, GROUNDWATER
LEVELS WILL VARY WITH TIDAL INFLUENCE AND PREVAILING WEATHER
CONDITIONS.

—EXTRACTED GROUNDWATER IS TO BE TREATED IN ACCORDANCE WITH
RECOMMENDATIONS PROVIDED IN A FUTURE DEWATERING MANAGEMENT
PLAN & SITE GEOTECHNICAL REPORT

— TREATED EXTRACTED GROUNDWATER IS TO BE DIRECTED TO COUNCIL
STORMWATER, FINAL OUTLET LOCATION TO BE APPROVED BY NOOSA
COUNCIL.

— PUMPING MUST NOT CAUSE NUISANCE FOR NIEGHBOURS. ENCLOSING
WITHIN A SOUND PROOF ENCLOSURE MUST BE CONSIDERED.

 

 

 

 

TEMPORARY CFA PILED RETAINING WALLS
— CFA PILED RETAINING WALL DESIGN AND INSTALLATION
BY A SPECIALIST CONTRACTOR

— DRIVING OF PILE WALLS NOT PERMITTED

— INSTALLATION OF GROUND ANCHORS INTO NEIGHBORING
PROPERTIES NOT PERMITTED WITHOUT OWNERS CONSENT
— ADDITIONAL MEASURES SUCH AS GROUTING THE JOINTS
IS RECOMMENDED TO REDUCE GROUNDWATER INFLOWS.

— PROVIDE GROUND MONITORING/VIBRATION CONTROL
DURING INSTALLATION.

— ESTABLISH SURVEY MONITORING POINTS ALONG PILED
WALL TO MONITOR WALL ALIGNMENT/ GROUND MOVEMENT

 

 

 

    

ESTABLISH SURVEY MOITORING POINTS ALONG PILE WALL
CAPPING BEAM TO MONITOR WALL ALIGNMENT/GROUND
MOVEMENT, PILING CONTRACTORS ENGINEER TO BE ADVISED OF
ANY OBSERVED MOVEMENT

 

EXISTING STRUCTURE /DWELLING
INCLUDING NEIGHBOURING
ALLOTMENTS

 

 

THE BUILDER /CONTRACTOR
SHALL CONFIRM ALL
RELEVANT LEVELS PRIOR 10
COMMENCING WORKS.

 

 

 

 

 

 

Ground /
pad level
UNSTABLE
&
Mey A
THIS FOOTING IS FOUNDED X
BELOW CRITICAL DEPTH ER Lo
LINE AND IS STABLE. STABLE NG
PIERS OR UNDERPINNING FOUNDED

 

 

BELOW THE CRITICAL DEPTH LINE
WOULD BE NEEDED TO SUPPORT

 

I

t

1 THIS FOOTING WITHOUT
t_ PIERS IS FOUNDED

ABOVE CRITICAL DEPTH
LINE AND IS UNSTABLE.

LINE OF PROPOSED

TRENCH.

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

   

EX. SWPT EXISTING STORMWATER PIT

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

   

 

ANY FOOTING THAT IS FOUNDED

ABOVE THE CRITICAL DEPTH LINE. Horizontal 30 De

CRITICAL DEPTH LINE

     

{
!
\
{
|—— EXCAVATION OR OTHER
{
!
\

 

ees

NOTE:

 

 

 

 

 

 

 

 

 

 

 

 

 

THIS DETAIL ALSO APPLIES TO EXISTING

FOUNDATIONS ON NEIGHBOURING
PROPERTIES. SHEET PILING MUST BE
INSTALLED WHERE EXISTING FOOTINGS WILL
BE FOUNDED ABOVE ANY EXCAVATION
CRITICAL DEPTH LINE

LEGEND

_---77 INDICATES PROPOSED SURFACE
18.07

+100

YD

FILL (POSITIVE) AS NOTED

 

 

 

INDICATES AREA OF CUT

 

INDICATES AREA OF FILL

 

INDICATES POSITION OF TEMPORARY
SHORING, DESIGN AND INSTALLATION BY

SPECIALIST CONTRACTOR

— E — INDICATES OVERHEAD ELECTRICITY

SUPPLY LINE
INDICATES EXISTING SEWER LINE

w———_ INDICATES WATER MAIN APPROX

CONTOURS AND LEVELS TO AHD.

EXISTING SURFACE SPOT LEVELS.

INDICATES DEPTH OF CUT (NEGATIVE) OR

ALIGNMENT, BUILDER TO CONFIRM EXACT

LOCATION PRIOR TO WORKS

| ——___ INDICATES TELSTRA LINE APPROX

ALIGNMENT, BUILDER TO CONFIRM EXACT

LOCATION PRIOR TO WORKS

AS NOTED

INDICATES STORMWATER DRAIN EXISTING

INDICATES POSITION OF RETAINING WALL

 

www.dialbeforeyoudig.com.au

SS DIAL 1100

yy BEFORE YOU DIG

 

  

 

 

 

TO STRUCTURAL ENGINERS DETAIL.

BUILDER TO MAINTAIN STABILITY
OF ALL NEIGHBOURING STRUCTURES,

REFER CRITICAL DEPTH LINE DETAIL
ON THIS SHEET

 

 

 

 

 

 

 

 

 

Soo BASEMENT WALLS TO STRUCTURAL FINAL BASEMENT SLAB THICKNESS TO
z | ENGINEERS DETAIL BE DETAILED BY STRUCTURAL K
we | ENGINEER
=|8
ae! PAVEMENT AS EX: SMH
“FE ? RAFT SLAB 10 Ore ON ORS COB.
I STRUCTURAL Ka&c
I ENGINEERS DETAIL.
i| NSLL.
5 FH.
ly ay
2 TP
a Ee FPL AS a EP.
“ez FPL AS NOMINATED. S KERB
| “ a NOMINATED. S RCEW
7/7 S.V
_ Vy CLL YY Y t W.M
CL
CL 7
eR TANKING WATERPROOF BLANKET WITH
PRIMER & PROTECTIVE COATING INSTALLED
BY SPECIALIST CONTRACTOR TO DRIVEWAY / CARPARK PAVEMENT
MANUFACTURERS’ SPECIFICATIONS &
CERTIFICATION.
FINISHED LEVELS. DIAGRAM FINISHED LEVELS DIAGRAM
TYPICAL SECTION
TYPICAL SECTION
—— — “ip
+ Lp —_—__ : -
«CHAPLAIN PARK |
———— 7 : /s , . ae _ /
ae
6] POOL Oo
EXCAVATION
TOP : 2.10 vo) ba | EXCAVATION TOP : 2.10
BTM : 1.65 + ob Re ye -0.828 | BTM : 1.45
= 0.45m aM T0651 H = 0.65m
7 5 } !
= 0.670] |
0.584 page — ~2-——=-+----- 4 =2.124
Ne ae 1 a -grc tron | INDICATES CFA CONCRETE PILING OR SIMILAR, DESIGN AND
ENSURE 600mm MIN. BEHIND 12.218 i \* | * #” [-2140; | INSTALLATION BY OTHERS. MINIMUM VIBRATION TECHNIQUES TO
PILING TO ALLOW FOR | | SN | | | BE USED FOR INSTALLATION, VIBRATION CONTROL AND
ACCESS FOR BASEMENT |: | | va | |—— MANAGEMENT BY PILING CONTRACTOR. BUILDER TO CONFIRM
WALL WATERPROOFING. | I >< an iN | EXTENT REQUIRED TO SATISFY CRITICAL DEPTH LINE
TYPICAL, 600mm _ MIN. | MN Le _ PROTECTION | oF NEIGHBOURING STRUCTURES.
ct | ‘. a7 \ 5
H S71 + . |
| | ‘¢ iE a f
! | RESIDENTIAL ~
mee | DEVELOPMENT N
0.511 Ai | Ny ESTABLISH SURVEY MOITORING POINTS ALONG PILE WALL
I FFL: —0.300 1 CAPPING BEAM TO MONITOR WALL ALIGNMENT/GROUND
| Sp . . | _ [MOVEMENT, PILING CONTRACTORS ENGINEER TO BE ADVISED OF
| FPL: —0.700 ; LAN oBsERVED MOVEMENT
om | 1 > ! | |
TOP : 2.10 | OK 2.296 -2.200}! 0.600] | TOP: 2.10
BIM : 1.80 i | ARS ag 0 | |BIM : 1.55
= 0.30m \ | | \ , A ex A: * | / H = 0.55m
| AK |
L-~ ! af DASHED LINE INDICATES 1\ Bf TOP : 2.50
TOP : 250 [> goo LF —7.300 aa #° PROPOSED BUILDING | BM : 1.50
BIM : 1.70 : 1 ! i Za FOOTPRINT MK 4 H = 1.00m
= 0.80 ‘a
m jo | 4
4 6 —_\ Ub
+ j | + 7 | #
8 a | |
1 ye | i
! ve + :
TOP : 2.30 I 8 14-9949 | |
BTM : 1.50 ee 2.236
H = 0.80m 48 ]
__ [0.964 SRS TOP : 2.30
cr TI 764 Ot | BTM : 1.50
+ a ee DRIVEWAY 7H = 0.80m
01 REFER Drg. OW4.1 &
OW4.2 FOR DETAILS. |

 

 

 

 

 

 

 

 

 

 

 

 

 

   
 
   
   

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

  

TERRACE

SITE PLAN — EARTHWORKS & PILING PLAN

Scale 1: 200

 

 

PRIOR TO COMMENCING WORKS,
UNDERTAKE DILAPIDATION REPORTS OF

ALL NEIGHBORING DWELLINGS/STRUCTURES

 

 

ALL SERVICES SHOWN ON THIS PLAN INDICATIVE
ONLY CONTRACTOR TO LOCATE ALL SERVICES
PRIOR TO COMMENCING WORKS ON SITE. ALL

 

 

CONTRACTOR TO REPAIR ADJACENT THE
CONSTRUCTION SITE KERB, FOOTPATH OR
ROAD RESERVE IF ANY DAMAGE IS SUSTAINED

DURING CONSTRUCTION. GRASSED AREAS ARE
TO BE RE TOP SOILED AND TURFED.

 

 

SERVICES ARE TO BE PROTECTED IN
ACCORDANCE WITH THE AUTHORITY
RESPONSIBLE FOR THE SERVICE

 

 

 

NOTE:

CUT/FILL LEVELS SHOWN REPRESENT THE FINISHED PAD
LEVEL (FPL) TO THE UNDERSIDE OF THE GROUND BEARING
SLABS AND PAVEMENTS AND INCLUDES THE CRUSHER
DUST OR ROAD BASE LAYERS 10 BE PROVIDED UNDER THE
SLABS. ADDITIONAL LANDSCAPING FILL NOT INCLUDED.

 

 

SITE GEOTECHNICAL

INFORMATION/ RECOMMENDATIONS PRESENTED IN
A FUTURE GEOTECHNICAL INVESTIGATION REPORT
COMPLETED BY A GEOTECHNICAL ENGINEER.

 

 

DILAPIDATION REPORT:
PRIOR TO ANY CONSTRUCTION

UNDERTAKE DILAPIDATION REPORT OF ALL
NEIGHBORING DWELLINGS/ STRUCTURES.

 

RC PILES, DESIGN
BY OTHERS

EXCAVATION DEPTH
V

©O--

EXISTING SEWER MANHOLE
EXISTING SEWER CONNECTION POINT
EXISTING EDGE OF BITUMEN
EXISTING KERB & CHANNEL
NATURAL SURFACE LEVEL

FIRE HYDRANT

TELSTRA PIT

ELECTRICAL PILLAR

EXISTING KERBING

REINFORCED CONCRETE END WALL
STOP VALVE

WATER METER

EXISTING GROUND LEVEL
—_ Y

 

 

   
 

   

PILE DESIGN BY OTHERS

  

      

    
 

 

 

 

(OC) CONCRETE PILED RETAINING WALL

 

\ 7 SECTION

CONSTRUCTION NOTES

GENERAL:

1. DO NOT SCALE FROM THIS DRAWING.

2. ALL DIMENSIONS IN MILLIMETRES

3. SETTING OUT DIMENSIONS ARE TO BE OBTAINED FROM THE
ARCHITECTURAL DRAWINGS.

4. ANY DISCREPANCIES BETWEEN THESE DRAWING AND THE
ARCHITECTURAL DRAWINGS ARE TO BE REFERRED TO THE
ENGINEER IMMEDIATELY.

5. THE BUILDER IS RESPONSIBLE FOR LOCATING ALL EXISTING
SERVICES WITHIN AND ADJACENT THE ALLOTMENT AND SHALL
ENSURE THAT ALL NEW WORKS ARE IN ACCORDANCE WITH
THE ATTACHED CRITICAL DEPTH LINE DIAGRAM.

FILLING NOTES

—THE SITE IS TO BE SCRAPED CLEAR OF ALL ORGANIC
MATERIAL AND DEBRIS.

—THE SUBGRADE IS TO BE ROLLED WITH A VIBRATING STEEL
DRUM ROLLER TO ACHIEVE A MINIMUM RELATIVE FIELD
DENSITY OF 98%. THE COMPACTION IS TO BE SUFFICIENT TO
ACHIEVE A BLOW COUNT OF 7 BLOWS PER 300mm WITH AN
APPROVED PERTH SAND PENETROMETER FOR A DEPTH OF
1.0m BELOW EXCAVATED LEVEL. COPIES OF COMPACTION TEST
RESULTS SHALL BE PRESENTED TO SCG CONSULTING
ENGINEERS FOR APPROVAL.

—UNLESS NOTED OTHERWISE A MINIMUM BEARING CAPACITY
OF 100kPa SHOULD BE ACHIEVED WITHIN COMPACTED FILLING.
COMPACTION & BEARING CAPACITY TEST RESULTS MUST BE
PRESENTED TO SCG CONSULTING ENGINEERS FOR APPROVAL
PRIOR TO WORKS PROCEEDING.

—THE FILL MATERIAL CLEAN GRANULAR MATERIAL (I.E. SAND
TO A CLAYEY SAND IN ACCORDANCE WITH AS1726) BE FREE
OF ANY ORGANIC MATERIAL AND HAVE A CLAY CONTENT OF
LESS THAN 12% (PLASTICITY INDEX LESS THAN 25%, LINEAR
SHRINKAGE OF 15%). THE PROPOSED MATERIAL IS TO BE
INSPECTED BY SCG CONSULTING ENGINEERS PRIOR TO ITS
REMOVAL TO ENSURE ITS COMPATIBILITY.

—THE FILL IS TO BE PLACED AND COMPACTED IN
ACCORDANCE WITH AS3798-1996 TO A LEVEL SUFFICIENT TO
ACHIEVE A LEVEL 2 CERTIFICATION WITH A MINIMUM RELATIVE
FIELD DENSITY OF 98%. COPIES OF COMPACTION TEST
RESULTS SHALL BE PRESENTED TO SCG CONSULTING
ENGINEERS FOR APPROVAL.

FILLING AND COMPACTING ADJACENT EXISTING STRUCTURES
IS TO BE IN STRICT ACCORDANCE WITH THE ASSOCIATED
DETAILS AND SPECIFICATIONS.

—AREAS WHERE EXISTING STRUCTURES OR TREES ARE
REMOVED SHALL BE BACKFILLED WITH THE APPROVED FILL
MATERIAL COMPACTED IN ACCORDANCE WITH AS2870-1996 TO
ACHIEVE A MINIMUM RELATIVE FIELD DENSITY OF 987.

—ANY LOOSE OR SOFT MATERIAL UNCOVERED IN THE SITE
PREPARATION SHALL BE REMOVED AND REPLACED WITH THE
APPROVED FILL MATERIAL COMPACTED IN ACCORDANCE WITH
AS2870-1996 TO ACHIEVE A MINIMUM RELATIVE FIELD
DENSITY OF 98%.

—SITE DRAINAGE AND SILT PROTECTION MEASURES MUST BE
ISTALLED PRIOR TO CONSTRUCTION COMMENCING.

 

 

Revision | Description Date

 

 

 

“FOR APPROVAL

 

DO NOT SCALE FROM THIS DRAWING

The design and associated details contained on this and associated
drawings are copyright and are not to be used or reproduced without
the written permission of SCG Consulting Engineers.

 

Unit 1/11 Project Ave,
Noosa Heads

Ph (07) 5455 5604
email:[email protected]

web:www.scg-engineers.com
ABN 40 098 481 899

C) Ste

DEBUILD T/A

 

Title:

EARTHWORKS PLAN

 

 

 

 

 

Project
150-132 Gympie Tce,
Noosaville
Date: Sept 22 Drawe Design TH
_| Checked: Drg No. Re
15400 @ AS i SRicherdson |) | O2220 —OW3.1) .

 

 

 

 

Page 33

                                                      ADG Consulting Pty Ltd




Appendix D:         Dewatering calculation output




ADG1451.22 Dewatering Management Plan_Rev0_28.02.23

Page 34

Cone of depression

 

DER requires @ preliminary assessment of the radial extent of the cone of depression and pumping

rates and times for all dewatering operations in ASS areas.

Empirical methods to calculate the radial extent of the groundwater cone of depression and
pumping rates and times for dewatering operations are outlined in Appendix E of @) Treatment and
maenegement of soils and water in acid sulfate soil landscapes 1.59 MB (Published July 2011, Revised

June 2015)

Calculator

Input

Length of excavation 35
(metres):
Width of excavation 30
(metres):
Required groundwater 23
drawdown (metres):
Saturated thickness of the,
unconfined aquifer!
(metres):

Hydraulic conductivity of
the aquifer (K) (metres
per second):

0.0000949

4
=
&

Results

Effective radius of
pumping well, R.
(metres):

Radius of influence of
dewatering, R, (metres):
(i.e. radius of the cone of
depression)

Total pumping rate (litres
per second):

Time taken to establish
the cone of depression
(hours):

m/sec

18m

67m

9l/sec

76hrs

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.