RFI - ADG1451.22 Dewatering Management Plan_Rev0_28.02.23

of 34

Page text read automatically using OCR, there may be inaccuracies

Plans and drawings: the text below has words only, no drawings.

Log in to see the plans as drawn
                                                                                      ADG Consulting Pty Ltd



     A plan showing the proposed shoring and dewatering system is provided at Appendix C.
5.6 Groundwater treatment
     All extracted groundwater will be treated on‐site using available technologies prior to discharge to the
     stormwater network. The following treatment measures will be adopted, and will be installed and
     operational prior to the commencement of dewatering:

     1.    A groundwater pH buffering treatment system (primary treatment)
     2.    A sedimentation tank to provide additional residence time and sedimentation (secondary
           treatment).
     3.    Installation of fine media filtration to retain suspended sediments and/or heavy metals (tertiary
           treatment), if required.

     Details of the treatment systems and methodologies are provided in Section 6 of this report.

     Note: Consideration should be taken, regarding placement of treatment gear on site to enable easy
     cleaning and maintenance throughout the dewatering phase for the project. Consider the potential
     requirement for regular de‐sludging of sedimentation tank/s to suitable area onsite, if available (cost
     minimisation).
5.7 Nominated Hold Points
     In accordance with anticipated DA Conditions, nominated hold points to be enacted during construction
     have been proposed to facilitate for certification by the suitably qualified person experienced with Acid
     Sulfate Soils, as well as Council Development Engineer to ensure all possible avenues for continual
     dewatering below permanent groundwater level, including around pipework bedding that outlet to
     waterways, are appropriately sealed. The nominated hold points regarding dewatering for this project
     are:
     1. Prior to commencement of dewatering/initial pump out
     2. At finished excavation level, prior to blinding layer application
     3. External to basement service installation trench opening/s prior to backfilling.

     The above nominated hold points are subject to confirmation by the consulting engineer, and liaison with
     council representatives and the Site Manager.




ADG1451.22 Dewatering Management Plan_Rev0_28.02.23                                                    Page 11
Log in to download the original file

RFI - ADG1451.22 Dewatering Management Plan_Rev0_28.02.23.pdf · 6.3 MB (large file)

The download may take up to a minute.

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.