B - Code Compliance
Earthworks Code
Overall Outcome Response
The Overall Outcomes of the Earthworks Code are:
2a). Earthworks are designed and constructed to be structurally sound. Not Applicable
No earthworks are proposed.
2b) All onsite works provide land stability (including differential settlement or Not Applicable
expansion in reactive soils). No earthworks are proposed.
2c) Earthworks avoid contamination of land. Not Applicable
No earthworks are proposed.
2d) Flooding and drainage are appropriately addressed.. Not Applicable
No earthworks are proposed.
2e) Groundwater, watercourses and wetlands are protected. Not Applicable
No earthworks are proposed.
2f) The loss of native remnant or regrowth vegetation is avoided. Not Applicable
No earthworks are proposed.
Performance outcomes Acceptable outcomes Response
Effects of Works
PO1 AO1 AO1 – Not Applicable
Finished surface levels ensure land is free draining. Filled or excavated areas have a minimum gradient of No earthworks are proposed.
0.5% and drain to Council’s stormwater infrastructure
where available, or where stormwater infrastructure is not
available, toward the street
PO2 AO2 PO2 – Not Applicable
Change to the levels on site do not have an adverse No acceptable outcome provided No earthworks are proposed.
impact on the flooding and drainage characteristics
off-site.
PO3 AO3.1 AO3.1 – AO3.2 – Not Applicable
Earthworks do not result in geotechnical instability Filling works are undertaken in accordance with No earthworks are proposed.
on-site or to nearby premises. Council’s Planning Scheme Policy PSP6 Engineering
design standards - roads, drainage and earthworks.
Preview the original
The page text is free to read. Previews and downloads of original files need an account.
Log in to previewLog in to download the original (B - Code Compliance.pdf)
Searchable page text hides email addresses. Original files are unchanged and may show email addresses.