f. The property access must be located a minimum of 1m clear of existing power poles,
streetlights or other signage. The developer is responsible for any necessary relocation
of existing services to provide this clearance and must contact the relevant service
authorities and comply with their requirements in relation to these works.
Stormwater Drainage
85. Stormwater drainage works must be constructed in accordance with the approved plans and
in compliance with the relevant standards and best engineering practices
86. Appropriate scour protection must be provided at the outlet of all stormwater pipes including
temporary outlets.
87. Works associated with this permit must not adversely impact on the existing drainage
conditions on other properties (eg by blocking or interfering with natural overland flows).
88. Construction of all internal stormwater drainage works must comply with the relevant
section/s of Australian Standard AS/NZS 3500.3.
Erosion & Sediment Control
89. All necessary erosion and sediment control measures must be provided and established prior
to the demolition works being carried out on the site.
90. All reasonable measure must be provided and established prior to commencement of
earthworks to prevent entrainment and export of sediments into the existing downstream
stormwater system.
Where required construction hold point/s with a council delegate and supervising RPEQ must
be discussed at the prestart meeting and established prior to commencement of earthworks
for the development. The hold point must be held as soon as reasonably practical and prior
to the first rain event forecast following initial tree clearing or removal of soil stabilising
material. At the hold point/s inspection, all required sediment basins, drains and/or bunds to
divert waters away from disturbed soil or soils about to become exposed through cut to fill
activities must be installed.
91. Prescribed Water Contaminants (as defined in Schedule 9 of Environmental Protection
Regulation 2008) must not be released from the site or to waters within the site, or be likely
to be released should rainfall occur, unless all reasonable and practicable measures are
taken to prevent or minimise the release and concentration of contamination.
92. Sediment and erosion control measures must be in place prior to works commencing. If such
measures are not in place or are not satisfactory, “on the spot” fines may be issued. Such
fines can be issued if sediments from the site are found to enter or have the potential to enter
Council’s stormwater system, natural waterways, any downstream stormwater filtration
system or adversely impacting on other properties. The sediment and erosion control design
and measures have NOT been approved, it is the site's Supervising Engineer who is
responsible for ensuring that the sediment and erosion control measures have:
a. Been duly designed by an RPEQ or CPESC and constructed in accordance with "best
practise" methods,
b. Been revised by an RPEQ or CPESC to address the issues raised by changes in the
projected construction schedule and/or methods,
c. Been revised to address predicted rainfall events, and
d. Achieve the desired environmental outcomes.
Council may request further controls to be installed should the implemented measures be
found inefficient.
93. The erosion and sediment control measures must be designed, installed and maintained in
accordance with the supervising engineer instructions and the current best practice
standards * (Refer to Advisory Note).
Page 13 of 21
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalUsed in these records
Negotiated Decision Notice MCU20 0071Related documentApplication case desk ↗
About this file
- File size
- 352 KB (small file)
- File type
No other editions are linked here.