2019-02-12 Attachment 1 to Item 3 - Stormwater Infrastructure Asset Management Plan

of 27

Page text shows just the words. Original shows the document exactly as it was published.

Page text read automatically using OCR, there may be inaccuracies

Text sections have not been matched to the original PDF pages. Use the original document to check page numbers.

Plans and drawings

This document appears to be plans or drawings. Its page text below holds only the words printed on the drawings, without the drawings themselves, so it may be jumbled or hard to follow. To see the plans as drawn, choose Original above or download the file (both need you to log in).

Log in to see the plans as drawn
5. Risk Management
Risk management is a coordinated approach to the management and control of risk by Noosa
Council having regard to the Council’s strategic and operational objectives.
       Critical Assets
The identification of critical assets based on the consequence of failure multiplied by the likelihood
of failure; as adapted from the International Infrastructure Manual 2015 Section 3.2.4 has been
undertaken to enable the prioritization of asset management and financial resources. Stormwater
Infrastructure is identified as a critical asset to the Noosa Community and has a high asset value on
Council’s asset register. The management of Council’s Stormwater Infrastructure assets should
continue to be prioritised to ensure any significant risks are mitigated before they escalate further
and impact on the Community.
       Risk Assessment
It is important to have a good understanding of the risks associated with the operation of the
Stormwater Infrastructure Assets. Council continues to develop its Stormwater Infrastructure
management activities to ensure that the Stormwater Infrastructure is meeting the intended design
life, and where necessary work on the optimised intervention for undertaking rehabilitation and
renewal activities.

The key risks associated with achieving the above objectives of Council’s Stormwater Infrastructure
management activities and associated levels of service have been identified throughout this AMP
and are outlined below:

1. Unanticipated Stormwater Infrastructure deterioration and structural failure – It’s likely that
   this risk will be accelerated by the increasing severity in weather and climate change conditions
   for certain stormwater assets. Predictions and events will need to be monitored closely to ensure
   this risk is managed appropriately.

2. Asset Performance – Asset failures that influence the determined service levels. A complete
   understanding of all Stormwater Infrastructure assets and their relevant asset condition will assist
   in mitigating potential risks.

3. Asset Knowledge - The need to understand the performance of all the Stormwater Infrastructure
   assets at component level is essential in mitigating risks to desired performance. Detailed
   inspections and asset data are essential for informed decision-making. Assets such as bio
   retention basins, end walls and structures require more detailed inspections and improved
   maintenance activities to ensure assets do not become a risk to the community.

4. Funding – the ongoing operational and maintenance costs for Stormwater Infrastructure will
   continue to rise and efficiencies and cost savings are reviewed regularly. Grant opportunities for
   renewals/upgrades must always be considered as well as cost benefit analysis of alternative
   designs and materials.

The above risks and all other current risks will be regularly reviewed by the stormwater infrastructure
working group and the high level risks documented in the annual Branch Plan – Civil Operations.
Should there be a need for them to be further escalated they can be addressed for consideration by
the Asset Management Working Group, Executive Team, and Audit and Risk Committee. To mitigate
these risks there are resulting actions from this AMP. For Council to make informed decisions, it is
understood that focus must be placed on consistent cyclical inspections across all Stormwater
Infrastructure assets with condition data accurately recorded in T1 asset management system. This
then supports the reconciling of financial asset data, GIS data and inspection data to have a single
point of truth for all Stormwater Infrastructure assets.


Asset Management Plan: Stormwater Infrastructure                                               Page 16
Log in to download the original file

2019-02-12 Attachment 1 to Item 3 - Stormwater Infrastructure Asset Management Plan(PDF, 1MB).pdf · 1.2 MB (small file)

Searchable page text hides email addresses. Original files are unchanged and may show email addresses.

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.